MIS 578 Chapter 3 Flashcards

1
Q

Project Charter

A

A project charter is like an informal contract between the project team and the sponsor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why is a project charter used?

A

The project charter is used to authorize PROJECT MANAGER to proceed, help develop common understanding, help team and sponsor to commit, and screen out poor projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a preliminary scope statement?

A

It is a more detailed version of scope overview section of the charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Typical elements of a charter

A

1) Title
2) Scope overview
3) Business case
4) Background
5) Milestone schedule w/ acceptance criteria
6) Risks, assumptions, & constraints
7) Spending approvals or budget estimates
8) communication plan requirements
9) Team operating principles
10) Lessons learned
11) signatures and commitment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Title

A

A meaningful title helps people understand the project quickly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Scope overview

A

The “what” of the project. The project in a nutshell: what needs to be delivered and what work
is involved in creating it.

This is the “elevator speech” – a half minute summary of the project. Ideally, sponsor provides
rough draft or at least input. Each of these sections should be of one to four sentences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Business Case

A

The “why” of the project. How the project will benefit the organization – how it supports the
organization’s strategy.

This is the “elevator speech” – a half minute summary of the project. Ideally, sponsor provides
rough draft or at least input. Each of these sections should be of one to four sentences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Background

A

Optional. More details under business case if needed.

If team wants more detail than four sentences in any of the previous sections, the extra details
can be included in this optional section.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Milestone schedule with acceptance criteria

A

Powerful visual summary of high-level schedule combined with how key stakeholder will
evaluate progress at each point.

Table with four columns one each for milestones, dates, stakeholder (who will judge), and
acceptance criteria can be used. Six-step process includes describing current situation,
describing desired end state, describing end state stakeholder and acceptance criteria,
determining milestones, determining expected completion dates for each milestone, and
identifying stakeholder and acceptance criteria for each milestone.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Risk, assumptions, & constraints

A

Risks are uncertain events, assumptions are factors believed to be true, and constraints are
limitations. Each can influence the project.

This section can vary. At a minimum, brainstorming is done about risks and one risk is noted per
Post-It® Note, determining by group consensus the likelihood and the impact of each risk,
creating contingency plans and assigning ownership for each big risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Spending approvals or budget estimates

A

Preliminary project budget or at least pre-approval to cover minor expenses.

Listing any preliminary budget or at least authorization to spend minor amounts of money
without further approval.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Communication plan requirements

A

Table with stakeholders identified along with what each needs to know, when, and the most
effective way for them to receive it.

A five-column table is created listing stakeholders, what the project team needs to learn from
each, what the project team needs to share with each, the timing for each communication, and
the method that will be most effective for the stakeholder to receive and understand it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Team operating principles

A

Guidelines to enhance team functioning. Often include meetings, decision-making, accomplishing work, and showing respect.

Either existing team principles are discussed or new ones are formulated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Lessons learned

A

How the current project will be better because of learning on previous project(s).

Useful practices are identified to copy or tailor from previous projects and/or less useful
practices to be avoided.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Signaturess and commitment

A

Public and personal commitment to the project.

Signature blocks are created to be signed after ratifying charter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Ratifying the project charter

A

Project manager and team present draft charter to sponsor (and sometimes team of executives). After interactive discussion, often leading to adjustments, ideally everyone is satisfied and sponsor, project manager, and core team sign charter. Everyone feels committed to the project.

17
Q

What is a charter?

A

Informal contract between sponsor and project team (core team and project manager)

18
Q

How is a charter like a contract?

A

It is an agreement entered into by the two parties through consensus and one of them cannot
arbitrarily change it. It is a living document that can be changed if both parties agree and both
receive something of value. This means that if a sponsor needs to change the terms of the project
such as to make a demand for earlier completion, the sponsor then needs to work with the team to
determine how to accomplish it – not just demand more overtime with no compensation.

19
Q

How is a charter different from a contract?

A

A charter is different from a contract in that the parties are agreeing to the “spirit” of the project.
The details are not worked out yet, so there is no “fine print” as in many contracts. The schedule,
budget, exact deliverables, etc. may change, but all parties agree to keep working hard to help make
the project successful.

20
Q

What are typical elements in a charter? What is the purpose of each element?

A
  • Scope overview – Determine how big the project will be
  • Business case – Why the project is needed
  • Background – Optional – if more details are needed
  • Milestone Schedule – When each intermediate point needs to be done
  • Acceptance criteria – How will the quality of work be judged along the way?
  • Risks – Identify what could go wrong and include in planning
  • Spending approvals – How much can the project manager spend without further approval?
  • Communication plan – Who needs to know what and when?
  • Team principles – How will we work together?
  • Lessons learned – Let’s learn from the success/failure of other projects
  • Signatures – Commitment to the project.
21
Q

List at least three important purposes of a charter?

A
  • Authorize the project manager to proceed.
  • Help project manager, team, and sponsor develop common understanding.
  • Help project manager, team, and sponsor to commit, and
  • Quickly screen out obviously poor projects
22
Q

What are the possible project outcomes that may come from using a charter?

A
  • Teamwork develops.
  • Agreement, trust, communication, and commitment develop.
  • Project team no longer worries what management will decide.
  • Sponsor is less likely to unilaterally change original agreement
23
Q

How long should a typical charter be?

A

A typical charter is about 2 to 4 pages.

24
Q

The charter signing marks the transition between which two project stages?

A

From the high-level project initiating into the more detailed project planning stage.

25
Q

The team always writes the charter rough draft. True or false?

A

False. The team usually writes the rough draft, but an executive team or a sponsor could write the first draft.

26
Q

Charters help secure both formal and informal authority. True or false?

A

True. The charter is the official form that formally authorizes the project manager to proceed, but it is also good at informally developing commitment.

27
Q

How does the preliminary scope statement compare to a charter?

A

The preliminary scope statement is basically a more detailed version of scope overview section of
charter. On large projects, both are frequently used. On small projects, often only the charter is used.

28
Q

Each contingency plan should have an “owner” who is responsible. True or false?

A

True. That helps to ensure it will be accomplished if the risk event happens.

29
Q

Ideally, who should create the first draft of the “elevator speech”?

A

Ideally the sponsor should create the first draft of the elevator speech. That gives the project team
more guidance for creating the remainder of the charter.

30
Q

What are the four columns of the milestone schedule?

A
  • Milestone,
  • Date,
  • Stakeholder, and
  • Acceptance criteria.
31
Q

On most small to medium sized projects, how many intermediate milestones should be identified in the
charter?

A

About three to eight.

32
Q

What are the two most frequently used dimensions of risk?

A
  • Probability of occurrence and

* Impact if realized.