Management of Schedule: Estimate activity duration Flashcards
What should you do before duration processes begin? Think units
Select duration unit (wks, days, hrs)
What did Apollo say about a modern perspective on probabilistic approaches?
Although they are often only implemented for uncertain/high risk activities. It is sensible to implement these across all activities.
What should you do with duration estimation with workers expertise?
Let the workers estimate durations, it stimulates better progress as it incentives them to finish works on time!
What is good practice to refer to when considering activity durations?
- Activity list
- Project network diagram (PND)
What are the 4 estimation techniques and is each one probabilistic or deterministic or first principles?
- Analogous estimating (deterministic)
- Parametric estimating (deterministic)
- Three-point estimating (probabilistic)
- Bottom-up estimating (first principles, time consuming!)
What is analogous estimating
Using duration estimates from previous projects with similar characteristics
What is parametric estimating
CESMM4 hourly rates and quantities (rate * quantity)
What is three point estimating
Probabilistic approach estimating a duration for optimistic, most likely and pessimistic cases
What is bottom up estimating?
Working out durations from first principles! Estimations are made using the lower level components of the WBS.
What tools and techniques can you say pretty much about every single fucking thing in schedule?
- Organise meetings with other project managers
- Leverage the experience of industry professionals can result in more accurate duration estimates. Let the workers determine durations/sequence of activities!
For the deterministic approaches such as parametric estimating or analogous estimating, we can increase the number of labour gangs to increase the rate works are completed. What tool is important to consider when doing this, what can be assumed, and what needs considering?
Tool: Expert judgement
Assumption: It can be assumed doubling labour gang halve the rate.
Consider: Think of the practical limitations, logistical constraints and worksite safety! (10 labour gangs won’t decrease the rate by 10*)