Management of Schedule: Controlling schedule Flashcards
1
Q
What generally should be kept in mind when controlling schedule?
A
- The schedule may be prone to change and require iterations
- It should be reviewed frequently
PDCA! Kaizen
2
Q
What 3 techniques that can be implemented to control schedule?
A
- Earned Value Analysis (EVA)
- Performance reviews
- Trend analysis
3
Q
What is earned value analysis? (EVA)
A
- Measures the value of work completed against the planned value and actual costs incurred
- Forecasts completion date and final cost
4
Q
What is a performance review?
A
Measures level of actual performance (e.g. actual durations) against planned performance.
5
Q
What is trend analysis?
A
Examine performance over time to determine whether it is improving or deteriorating
6
Q
What project management information system should be used for controlling schedule?
A
Microsoft Project