Management of schedule: Develop schedule Flashcards

1
Q

What computational tool should be used to develop the schedule and why?

A

Microsoft Project as it increases overall efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What 4 things do you need to refer to when developing the schedule?

A

Project network diagram (PND)
Activity list
Duration estimates
Dependency determination and integration results

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What method traditionally should you implement to deduce the critical path and why is this important?

A

Use the critical path method
It is important as it highlights key activities that will have the largest knock on effect to the schedule if not completed on time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you perform the critical path method traditionally (CPM)?

A
  1. Extract early and late finish times from Microsoft project
  2. Calculate the float
  3. Activities with no float are considered critical
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why should resource optimisation be completed after a preliminary schedule is devised?

A

To minimise resource fluctuation on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the two types of resource optimisation and when should they be used?

A
  1. Resource smoothing - Executed on non-critical activities, used for works where time constraints take priority.
  2. Resource levelling - Executed on non-critical activities, used in other cases when resources take priority.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How would you apply resource smoothing to a non-critical activity and how does it affect the schedule?

A
  1. It does not affect the schedules total duration!
  2. Adjust activity within it’s early and late start times to allow most work to be done. (Time constraints take priority! Total project duration not increase or decrease)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you apply resource levelling to a non-critical activity and how does it affect the schedule?

A
  1. Potentially extends the total duration
  2. Adjust start and finish times of activity to level resources.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When would schedule compression be good practice?

A

When meeting a fixed deadline. Time constraints take priority!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the two forms of schedule compression?

A
  1. Crashing
  2. Fast tracking

If time constraint takes priority over cost constraint. Use fast tracking!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is crashing?

A
  1. A form of schedule compression
  2. Considers the cost and schedule trade-offs
  3. Determines how to obtain the greatest amount of compression for lowest cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is fast tracking? (Clue: Start roof truss fabrication before structural design complete)

A
  1. A form of schedule compression
  2. Overlap activities that would normally be done in sequence

Use modular construction!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a sensitivity analysis? (What-if analysis)

A

Create versions of the schedule considering alternate scenarios.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Monte Carlo simulation and what type of approach is it? (Remember cannot use with parametric estimating or analogous estimating as deterministic!)

A
  1. Probabilistic approach that performs risk analysis.
  2. Monte Carlo considers different duration estimates for given activities from three point estimating and assigns probabilities to each of those estimates.
  3. It then creates the schedule randomly using this information.
  4. Produces a cumulative probability distribution of possible durations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is some higher level analysis regarding devising the critical path of the project? (Clue: First state traditional approach, but what you would use?)

A

A traditional approach would be deterministic, extracting the earliest finish and latest finish times from MS Project, and calculating the float. A float of zero would mean an activity is critical.

However, I regard it as more desirable to deduce the critical path using the probabilistic approach of Monte Carlo simulation. As this also performs risk analysis and creates a cumulative distribution of possible schedules.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly