M6 - Estimating - How & When Flashcards

1
Q

Estimation Techniques in AgilePM

A
  • Use the DSDM contingency provided by applying MoSCoW to scope out the features
  • Asking people involved for estimates
  • Creating estimates as precise and accurate as necessary for their purpose
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Top down estimating (4)

A

Re-estimation happens throughout the project. Don’t stick to original numbers when you get more information!

  • Best estimates happen when the SDT work together.
  • The team who does the work should do the estimate
  • Allow for non productive time (buffer)

T Shirt Estimating

Assigns S, M, L, XL

Estimating by Story Point

Consensus based that uses group discussion to assign a relative size to each story

Points are calibrated against time

Estimating by Example

Used for T-shirt and Story point estimation

Estimating by Velocity

Uses teams previous performance to project what can be expected in the future

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bottom Up style of Estimating

A
  • Each component broken into individual elements, makes it much more accurate but takes much longer.
  • Can be time consuming for large pieces of work. Not a practical choice for project or increment estimating in the early project Lifecyle phases.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly