Lyme regis Flashcards
when was phase 1
1990-1995
what did they construct in phase 1
a new sea wall and promenade to the east of the mouth of the river lim
what happened in phase 1 in the winter of 2003-4
emergency 1.4 million to stabilise the cliffs
when was phase 2
2005-7
what happened in phase 2
-new sea wall and promenade
-a wide shingle & sand beach to absorb wave energy
-extension of rock armour at Cobb and eastern beach to absorb wave energy
-costing around £2 million
when was phase 3
not undertaken
what was to happen in phase 3
prevent coastal erosion and land slips to the west of the cobb
-not undertaken because the price outweighed the benefits
when was phase 4
2013-15
how much money was phase 4
£20 million
what happened in phase 4
- new 390 m sea wall in front of existing wall
-extensive nailing, piling and drainage to help 490 homes