Lesson 4 Keeping the Team on Track Flashcards

1
Q

power/interest grid

A

grid to classify stakeholders by the two dimensions of power and interest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

power/influence grid

A

grid to classify stakeholders by the two dimensions of power and influence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

salience model

A

three dimensional model used to classify stakeholders based on power, legitimacy and urgency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

actual costs (AC)

A

actual costs incurred for a project or specific activity; needed to determine cost variance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

earned value (EV)

A

a measure of work performed expressed in terms of budget authorized for that work; default formula :
EV = Budget at Completion (BAC) X % Complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Budget at Completion (BAC)

A

the sum of all budgets established for the work to be performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Planned Value (PV)

A

the authorized budget assigned to scheduled work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

cost variance (CV)

A

cost variance expressed as the difference between the earned value and actual costs; formula:
CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

schedule variance (SV)

A

a measure of schedule performance expressed as the difference between earned value and planned value; formula:
SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost performance index (CPI)

A

a measure of cost efficiency expressed as a ratio of earned value to actual cost: formula:
CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule performance index (SPI)

A

a measure of schedule efficiency expressed as a ratio of earned value to planned value; formula:
SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-complete-performance-index (TCPI)

A

a measure of the cost performance required to be achieved with the remaining resources in order to meet a specified management goal; formula:
(BAC - EV) / (BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate at Completion (EAC)

A

The expected total cost of completing all work for the project taking the sum of the actual costs plus the estimate to complete; formula:
EAC = AC + ETC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate to Complete (ETC)

A

the expected cost to complete the remaining work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Variance at Completion (VAC)

A

the variance between the original budget and the estimate at completion; formula:
VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

throughput metrics

A

measurement of the team’s work that has moved from one stage to another stage over a certain time

17
Q

cycle time

A

time required from initiation of work until completion of work or delivery

18
Q

value stream map

A

presents a visual representation of a process and the actions in each step to determine efficiencies and waste

19
Q

Tuckman’s ladder

A

the stages of team development: forming, storming, norming, performing and adjourning

20
Q

emotional intelligence (EI)

A

the ability to identify, assess and manage the personal emotions of oneself and others

21
Q

nominal group technique (NGT)

A

a technique that enhances brainstorming with a voting process

22
Q

active listening

A

communication technique that involves acknowledging what you hear and confirming that what you heard is what the sender intended

23
Q

Maslow’s hierarchy

A

theory that places the needs of an individual in a pyramid or triangle; lower-level needs must be satisfied before a high level one can be addressed

24
Q

McGregor’s Theory X and Y

A

Theory X states that people need to be managed to maintain productivity; Theory Y is the opposite: people want to work and do not require constant supervision

25
Q

McClelland’s Achievement Theory

A

people are motivated by achievement, power or affiliation

26
Q

Herzberg’s Motivation Theory

A

success is based on two factors: hygiene factors relate to expected working conditions and are not motivators; motivating factors relate to feelings of achievement, recognition and career growth