Lesson 4 Keeping the Team on Track Flashcards
power/interest grid
grid to classify stakeholders by the two dimensions of power and interest
power/influence grid
grid to classify stakeholders by the two dimensions of power and influence
salience model
three dimensional model used to classify stakeholders based on power, legitimacy and urgency
actual costs (AC)
actual costs incurred for a project or specific activity; needed to determine cost variance
earned value (EV)
a measure of work performed expressed in terms of budget authorized for that work; default formula :
EV = Budget at Completion (BAC) X % Complete
Budget at Completion (BAC)
the sum of all budgets established for the work to be performed
Planned Value (PV)
the authorized budget assigned to scheduled work
cost variance (CV)
cost variance expressed as the difference between the earned value and actual costs; formula:
CV = EV - AC
schedule variance (SV)
a measure of schedule performance expressed as the difference between earned value and planned value; formula:
SV = EV - PV
Cost performance index (CPI)
a measure of cost efficiency expressed as a ratio of earned value to actual cost: formula:
CPI = EV / AC
Schedule performance index (SPI)
a measure of schedule efficiency expressed as a ratio of earned value to planned value; formula:
SPI = EV / PV
To-complete-performance-index (TCPI)
a measure of the cost performance required to be achieved with the remaining resources in order to meet a specified management goal; formula:
(BAC - EV) / (BAC - AC)
Estimate at Completion (EAC)
The expected total cost of completing all work for the project taking the sum of the actual costs plus the estimate to complete; formula:
EAC = AC + ETC
Estimate to Complete (ETC)
the expected cost to complete the remaining work
Variance at Completion (VAC)
the variance between the original budget and the estimate at completion; formula:
VAC = BAC - EAC