Lecture 8 Flashcards
How is risk analysis calculated?
Probability and Impact are given a value each from 1-5. Then PxI=Risk value
What values from the risk analysis mean that a risk response is necessary?
Over 10-15
What is GAP-Analysis in risk mini method?
Assessing what can be done to bring down the risk to the desired level
What are some tasks of a project manager?
-Reporting outcomes and handling risks and changes
-Calling and leading project meetings
What are two important rules for sprints?
-No changes can be made that jeopardise the sprint goal
-Content can be renegotiated with the product owner if there are new insights
What might be three headings of a Scrum taskboard?
-To do
-Doing
-Done
What is shown in a sprint burndown?
Development in the sprint and progression towards the goal
The project result is delivered to who?
Project owner
Who documents needs to be handled in a structured way?
Project manager
Who is responsible for closure and hand-over of a project?
Project manager
Who assesses the impact of the project?
Can be either management or project owner