Lecture 4A: Cost estimating Flashcards

1
Q

WHy estimates?

A
  • To ibtain contracts
  • establish budget
  • determine feasibility
  • Control cost during design
  • consider alternatives
  • appraise value
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is estimate for conceptual planning.

A
  • Based on only general parameters of facility size, anticipated quality of construction, and use of the facility.
  • The primary purpose of these estimates is to provide an idea of the likely cost of the facility to determine the amount of money needed to finance the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Estimates for feasibility

A
  • Based on prelimitary design information and is prepared after the project scope is completely defined.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Estimates for project execution/construction

A

These are itemized cost computations based on a complete set of contract documents.
- These are prepared using historical average costs or by creating crews/manufacturing units and considering their production

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimates for change orders

A
  • Developped during project implementation in response to an owner directed change in project scope.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Contingency

A
  • Amount added to an estimate to allow for items, for which the experience shows will likely result in additional costs.
  • Based on estimator’s past experience
    • planning and estimating errors and omissions
    • possible price escalations.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is triangulation estimation model

A

– Approaching the estimate from different perspectives and sources
– Using different sources to arrive at the estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Learning curve learning model

A
  • A percentage or rate at which the output is increased due to repetition
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the equation of learning curve

A

Tn = Tinitial x N^r

Where
Tn = time required for Nth unit of production
Tinitial = time required for the first unit of production
N = number of completed units.
r = learning curve exponent = log (learning curve as a decimal) / log(2.0)

let 1 takes 10min, learning rate 80%
1st unit takes 10 min
2nd takes 10 *0.8 = 8 min
4th takes 8 * 0.8 = 6.4min
8th unit takes 6.4 * 0.8 = 5.12min

Total time - summation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the three types of cost estimating

A
  • Rough (ballpark)
  • Budget (comparative)
  • Detailed (definitive)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Rough estimate

A
  • Used in inital planning and evaluation phase
  • Little detail and accuracy
  • Used only for quantification
  • Mad quickly and easily
  • (-30%) to +60%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Budget estimate

A
  • Used for budgeting only at conception / preliminary stage of project.
  • more detailed than rough -> more time and ressources
  • (-15%) to +20% accurate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Detailed estimate

A
  • Used during project’s detailed design and contract bidding phase.
  • made from detailed quantitative models, blueprints, product specification sheets, vendor quotes.
  • Require more time and resources
  • (-3% to +5% accurate)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Difficulties in estimating

A
  • one of a kind estimates
  • Time and effort available:
  • estimator expertise
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is one-of-a-kind difficulty

A

Especially difficult since (almost) all parameters must be estimated.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is time and effort available difficulty

A

Both are required for a detailed estimate (these resources must be planned/scheduled)

17
Q

what is Estimator expertise difficulty

A

More experienced and knowledgeable estimator usually makes better estimates.

18
Q

What are the estimating models

A
  • Per-unit models
  • Segmenting model
  • Cost indexes
  • Power-sizing model.
19
Q

What is per-unit model

A
  • Uses ‘per unt’ factor to develop an estimate (utility cost per m^2, etc.)
  • Simple and useful.
  • Only for rough estimate.
20
Q

What is segmenting model

A
  • Divide estimate into its individual components (based on WBS)
  • Prepare estimates for each of these components.
  • Total estimate is sum of all component estimates.
21
Q

What are Cost indexes

A

Dimensionless numbers reflecting the change in price over time (commodity price indexes, etc.)

22
Q

What is the formula for cost indexes

A

Cost at time A / Cost at time B = Index at time A / Index at time B
A is of target estimate, based on B which is known, both indexes are known

Example:
Labour cost index value was 124 ten years ago and is 188 today
* Annual labour costs for a similar facility were $575,500 ten years
ago

(188/124) * 575.5K = 871.8k

23
Q

Power-sizing model

A

used to estimate costs of industrial plants and equipment. Uses exponent x - the power sizing exponent, to represent economies of scale in size or capacities.

24
Q

What is the formula of power-sizing model

A

Cost Equip. A / Cost Equip. B = ( capacity equip A / capacity equip B) ^ x

x=1 -> Linear relationship
x > 1 -> diseconomies of scale
x < 1 -> economies of scale

capacity A and B must be same units
Costs A and B must be at the same point in time
- Use cost indexes to make it the same time (if needed)