Lecture 2A: Project Delivery methods and contracts Flashcards
Traditional delivery method
Design activities are completed, only then can the building start.
Phased devliry method
Each design activity is completed, and thier respective build activities can start.
Fast track delivery method.
Part of the design activity is completed, and the respective build activities start.
Main points of traditional delivery method
- Longest duration
- Suitable for using a single contractor.
main points of phased delivery method
- Shorter overall duration
- Multiple contractors; requires project management.
main points of fast track
- Build starts before design is finalized.
- shortest overall duration.
- Difficult to manage, requires PM and multiple contractors.
Why do we use contracts?
- Describe scope of work
- specify duration
- specify the amount and method of payment.
- Control mechanisms
- manager/allocate risks
- Assign responsibilities and obligations
What is a contract?
Agreement between onwer and performing organization to execute a defined scope of work.
Things specified in a contract:
- NAMES of parties involved
- SCOPE OF WORK covered by contract.
- PERIOD of the contract
- Contract PRICE and METHOD TERMS OF PAYMENT
- The LANGUAGE and SOURCE OF LAW governing the cotract
- LISTING OF DOCUMENTS that are part of the contract.
6 Different types of contracts
- Lump sum
- Unit price
- Cost + fixed percentage
- Cost + fixed fee
- Cost + fixed fee + profit sharing
- Cost + fixed fee + sliding fees
Lump sum contract?
Used where it’s possible to compute accurate quantities of work prior to construction.
- single quoted price for
the entire job based on a complete set of plans and specifications
What is Lump sum equal to?
= Direct cost + indirect cost + Markup
Direct = labor + equipment
Indirect = project + home office overheads
Markup = profit
What is the markup based on and how is the payment made?
The markup is usually higher to account for risk, and the payment is made based on % work complete. ALl risk is on the contractor/seller.
What is the major advantage of the Lump Sum contract?
- Major advantage is that the price quoted is generally assumed to be the guaranteed price for the work.
-Therefore you know how much to budget.
Disadvantges of lump sum
- Ownver must complete plans and specifications before bidding and contructions (traditional delivery)
- Little to no flexibility to make design changes,
- Any deviation from original plans/specs must be handles as a change order -> costs for contract change.