Lecture 2A: Project Delivery methods and contracts Flashcards

1
Q

Traditional delivery method

A

Design activities are completed, only then can the building start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Phased devliry method

A

Each design activity is completed, and thier respective build activities can start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Fast track delivery method.

A

Part of the design activity is completed, and the respective build activities start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Main points of traditional delivery method

A
  • Longest duration
  • Suitable for using a single contractor.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

main points of phased delivery method

A
  • Shorter overall duration
  • Multiple contractors; requires project management.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

main points of fast track

A
  • Build starts before design is finalized.
  • shortest overall duration.
  • Difficult to manage, requires PM and multiple contractors.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why do we use contracts?

A
  • Describe scope of work
  • specify duration
  • specify the amount and method of payment.
  • Control mechanisms
  • manager/allocate risks
  • Assign responsibilities and obligations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a contract?

A

Agreement between onwer and performing organization to execute a defined scope of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Things specified in a contract:

A
  • NAMES of parties involved
  • SCOPE OF WORK covered by contract.
  • PERIOD of the contract
  • Contract PRICE and METHOD TERMS OF PAYMENT
  • The LANGUAGE and SOURCE OF LAW governing the cotract
  • LISTING OF DOCUMENTS that are part of the contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

6 Different types of contracts

A
  1. Lump sum
  2. Unit price
  3. Cost + fixed percentage
  4. Cost + fixed fee
  5. Cost + fixed fee + profit sharing
  6. Cost + fixed fee + sliding fees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Lump sum contract?

A

Used where it’s possible to compute accurate quantities of work prior to construction.

  • single quoted price for
    the entire job based on a complete set of plans and specifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Lump sum equal to?

A

= Direct cost + indirect cost + Markup

Direct = labor + equipment
Indirect = project + home office overheads
Markup = profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the markup based on and how is the payment made?

A

The markup is usually higher to account for risk, and the payment is made based on % work complete. ALl risk is on the contractor/seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the major advantage of the Lump Sum contract?

A
  • Major advantage is that the price quoted is generally assumed to be the guaranteed price for the work.
    -Therefore you know how much to budget.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Disadvantges of lump sum

A
  • Ownver must complete plans and specifications before bidding and contructions (traditional delivery)
  • Little to no flexibility to make design changes,
  • Any deviation from original plans/specs must be handles as a change order -> costs for contract change.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are unit price contracts

A

Used when it’s not possible to calculate exact quantity of materials needed. (highways, etc.)

-Broken down into work items based on units (m^3, etc.)
- An estimate on how much of each unit is baesd, and there is a price per unit that is set.

17
Q

Disadvantage of unit price contract:

A

True price is not known until the project is completed (owner needs more budget)
- Uni prices are susceptible to being manupulated via unbalanced bidding for profit.

18
Q

Responsiblity and risk with unit price contracts with owner and contractor

A

Best used when the the responsibility remains with the owner or the design is completed during construction.
Lower risk than lump sump for contractor.

19
Q

Cost + fixed percentage contract.

A
  • Contractor is reimbursed for all direct expenses for labour, materials and equipment, as well as indirect expenses (Reimbursable cost).
  • Also paid a percentage of reimbursable cost as their “fee”

Example, reimbursable cost is 1M, percentage fee is 7%. If the project ends up costing 2M, the contractor will get 140K

20
Q

When is the cost + fixed percentage contract best used?

A
  • For projects with new technology
  • Not recommended for time limited projects.
  • More risk for the owner
21
Q

Cost + fixed fee contract

A
  • COntractor is reimbursed for al direct expenses for labour, materials and equipment, and indirect overhead.
  • Contractor receives fixed fee.
  • This fixed fee is paid regardless of fluctuation of reimbursable cost components, and is usually a percent of an originally estimated total cost figure.

Example: if the project is estimated to be 77M, and agreed upon 1% fee (770k), even if the project ends up costing more or less than 77M, the fee still is 770K

22
Q

What are the benefits of cost + fixed fee

A

Gives incentive to contractor to finish the job as quickly as possible.

23
Q

What is the risk in cost + fixed fee

A

Contractor can lose profit if project is delayed.

24
Q

What is cost + fixed fee + profit sharing

A
  • The contractor aims for a target price, and if the project ends up under target costs, savings are shared on an agreed percentage.
    Example:
    Fixed fee is 1.7M, sharing is 25%.
  • Target price is 17M.
  • If total price was 16M, contractor gets 1.7M + 25% of (17M - 16M)
25
Q

What is cost + fixed fee + sliding fee

A
  • Rewards contractor when underbudget, and punishes when overbudget of target price.
    Sliding fee = %agreed x ( target price - actual cost of construction)

The target price for a project is set as $17,000,000 (i.e. T)
* The contractor’s fixed fee is agreed as being $1,700,000.
* In addition, the base percent value for profit sharing is 5%
(i.e. R).
* If the contractor completes the project at an actual cost of
$15,000,000 (i.e. A), the sliding fee will be:
* Sliding fee = 0.05($17,000,000 – $15,000,000) = $100,000
* The contractor’s total fee will be: $1,700,000 + $100,000 =
$1,800,000

If the contractor completes the project at an actual cost
of $19,000,000, the sliding fee will be:
Sliding fee = 0.05($17,000,000 – $19,000,000)
= –$100,000
– This means the contractor will be penalized an amount of
$100,000)
– Note: The penalization is for +$100,000
* The contractor’s total payment will be: $1,700,000 –
$100,000 = $1,600,000

26
Q

What are some types of risks?

A

– Force majeure: “acts of God” like war, earth-quake, etc.
– Indemnification (Insurance)
– Occupational safety and health of workers
– Suspension of work
– Liquidated damages