Formulas EV, etc Flashcards
1
Q
PV BCWS
A
authorized budget assigned to the work to be
accomplished for an activity
2
Q
EV or BCWP
A
% work performed * PV
3
Q
AC or ACWP
A
actual $ spent on work
4
Q
BAC
A
total budget for the project
5
Q
CV
A
= EV - AC
+ = under budget, - = overbudget
6
Q
SV
A
= EV - PV
+ = ahead schedule, - = behind schedule
7
Q
CPI
A
= EV/AC
greater than 1 means cost underrun of performance to date
8
Q
SPI
A
= EV/PV
greater than 1 means more work was completed than planned
9
Q
ETC
A
Estimated cost to completion
= (BAC-EV)/CPI if continues CPI
= BAC-EV if atypical
10
Q
EAC
A
estimated cost at completion
= ETC + AC
or BAC/CPI