Formulas EV, etc Flashcards

1
Q

PV BCWS

A

authorized budget assigned to the work to be
accomplished for an activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV or BCWP

A

% work performed * PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC or ACWP

A

actual $ spent on work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC

A

total budget for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

= EV - AC
+ = under budget, - = overbudget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV

A

= EV - PV
+ = ahead schedule, - = behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CPI

A

= EV/AC
greater than 1 means cost underrun of performance to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI

A

= EV/PV
greater than 1 means more work was completed than planned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

ETC

A

Estimated cost to completion
= (BAC-EV)/CPI if continues CPI
= BAC-EV if atypical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EAC

A

estimated cost at completion
= ETC + AC
or BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly