Introduction Flashcards

1
Q

Design –> Bidding / Tender –> Build

A

Traditional Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Owner –> Main Contractor –> Design Consultant & Sub-contractors

A

Design-Build Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

temporary endeavor to create a unique product, service, or result

A

Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

geographical venue of a project

A

site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

determined needs of the users that will guide for the design process

A

Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

sequence, timing, and duration of works to be done to complete the project

A

Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

financial allocation for the project

A

Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

allocated budget for unforseen / other possible changes in the design /construction

A

Contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Money for design changes to accommodate new project requirements

A

Design Contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Money for unforeseen work / materials necessary to complete construction work

A

Construction Contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Money allocated by the owner to possible fund addt’l work or materials

A

Owner Contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Money that may be needed to pay for significant increase in construction cost

A

Escalation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

written info that clarifies/modifies the bidding documents (during the bidding process)

A

Addendum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Addt’l design/mat’l options added to the construction documents to obtain multiple possible cost estimates

A

Alternate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

ANSI

A

American National Standard Institute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

contract drawings that have been marked up to reflect any changes to a project during construction

A

As-built Drawing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

offer a proposal or a price

contractors submit their estimates as to the time and the cost

A

Bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

written documents permitting the construction in accordance w/ the drawings and specifications approved

A

Building Permit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

written documents stating that the building or property meets local standard of occupancy and is in compliance w/ public health and bldg codes

A

Certificate of Occupancy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

written documents signed by the owner and contractor authorizing a change in the work or adjustment in the contract sum or length of time

A

Change Order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

intensive design process for solving architectural problem quickly

A

Charrette

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

direct contractor cost for labor, materials, equipment and services as well as overhead and profit

A

Construction Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

organization and direction of the labor force, materials, and equipment to build the project as designed

A

Construction Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

written agreement giving responsibility for project planning and accomplishment and overall project planning, designing, and construction

A

Construction Management Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

hired by the owner/ architect to provide information and to advice the project in the area of his/her expertise

A

Consultant

26
Q

contractual duties and responsibilities of the architect and engineer during a project’s construction

A

Contract Administration

27
Q

diff. bet. the original contract price and the final completed cost

A

Contract Over/Under-run

28
Q

licensed individual or company that agrees and perform the work as specified

A

Contractor

29
Q

date certified by the architect when the work is to be complete

A

Date of Substantial Completion

30
Q

arrangement wherein a contractor bids or negotiates to provide design and construction services for the entire project

A

Design-Build Construction

31
Q

calculation of the amount of material,labor, and equipment needed

A

Estimating

32
Q

method of construction management in w/c construction work begins before completion of the construction documents, resulting in a continuous design-construction situatiin

A

Fast-Track Construction

33
Q

movable furniture,fixture, or equipment that do not require permanent connection to the structure or utilities

A

FF&E

34
Q

written order calling for a clarification or minor change in the construction work and not involving any adjustment to the terms of contract

A

Field Order

35
Q

licensed individual or company with prime responsibility for the work

A

General Contractor

36
Q

expenses that are not chargeable

A

Indirect Cost

37
Q

NIBS

A

National Institute of Building Sciences

38
Q

central idea governing and organizing a work of architecture

A

Parti

39
Q

desired list of spaces, rooms, and elements as well as their sizes

A

Program

40
Q

line diagram showing proposed and actual starting completion times in a project

A

Progress Schedule

41
Q

all cost for a specific project

A

Project Cost

42
Q

written list of names and addresses of all parties involved in a project

A

Project Directory

43
Q

qualified individual or firm authorized by the owner to be responsible for coordinating time, equipment, money, task, and people

A

Project Manager

44
Q

detailed written specification describing acceptable construction materials and methods

A

Project Manual

45
Q

written request from a contractor to the owner/architect for clarification of the contract documents

A

Request for Information (RFI)

46
Q

plan for performing work; also a chart or table w/in the drawing set

A

Schedule

47
Q

chart, diagram or routine of a system being proposed

A

Scheme

48
Q

written range of view or action for a specific project

A

Scope of Work

49
Q

drawings, diagrams, schedules, and other data specially prepared by the contractor (or subcontractor, others) to illustrate some portions of the work being done

A

Shop Drawing

50
Q

location of a structure or group of structure

A

Site

51
Q

expenses in addition to the direct construction cost

A

Soft Costs

52
Q

listing of minimum acceptable ethical principals and practives

A

Standard of Professional Practice

53
Q

load bearing assembly of beams and columns on a foundation

A

Structural System

54
Q

specialized contractor (subordinate to main contractor)

A

Subcontractor

55
Q

proposed replacement or alternate for a material or process of equivalent cost and quality

A

Substitution

56
Q

interior improvements of the project after the building envelope is complete

A

Tenants Improvement (TIs)

57
Q

written agreement wherein payment is based on actual cost for labor, equipment, materials, and services rendered, in addition to overhead

A

Time and Materials (T&M)

58
Q

process of analyzing the costs versus the value of alternative materials, equipment, and systems

A

Value Engineering (VE)

59
Q

restrictions of areas or regions of land w/in specific areas based on permitted building size, character and uses

A

Zoning

60
Q

document issued that permits land to be used for a specific purpose

A

Zoning Permit