Interim Valuations and Payment Provisions Flashcards
What are the two main pieces of legislation regulating payment provisions?
Housing Grants, Construction and Regeneration Act, 1996
Local Democracy, Economic Development and Construction Act 2009
What is the contract sum?
In the case of lump sum contracts this is a specified sum written into the contract.
What are the primary causes of adjustments of the contract sum for which contracts make provision?
The adjustment of provisional sums
The adjustment of prime costs
Variations to the design/specification
Additions of deduction to scope of works
Loss and expense incurred
Fluctuations in labour and materials costs.
What is the interim valuation date and when is it?
The Interim Valuation Date is detailed in contract particulars. The first interim valuation date should not be more than one month after works commence, and thereafter at intervals of no more than 1 month.
What is the due date date and when is it?
Due Date: Last date for submission of interim application by the contractor is the due date (maximum of 7 days after the interim Valuation Date)
What is the issue date date and when is it?
Issue Date: When Interim Certificate for Payment (payment notice) must be issued (Maximum of 5 days after the Due Date – statute HGCRA)
The payer must issue a payment notice within five days of the due date for payment, even if no amount is due, setting out the sum that the payer considers to be or to have been due at the payment due date, and the basis on which that sum is calculated. Alternatively, if the contract allows, the payee may make an application for payment, which is treated as if it is the payment notice.
What is the final date for payment and when is it?
Final Date for Payment: The date the employer has to pay the contractor (14 days after the due date – can be changed in the contract)
What is a pay less notice and when must it be issued?
A Pay Less Notice is a written notification from the Payer to the Payee of the Payer’s intention to pay less than the value stated in their previous Payment Notice.
It must be issued a minimum of 5 calendar days before final date for payment (contract can be altered change the period)
What is a provisional sum?
An estimated allowance that is inserted into tender documents for a specific element of the works that is not yet defined in enough detail for tenderers to accurately price.
What the two types of provisional sum?
Defined provisional sums are those which have been described in sufficient detail that the contractor is expected to have made allowance for them in their programming, planning and pricing preliminaries.
Undefined provisional sums are less well described and so the contractor cannot be expected to make allowance for them in their programming, planning and pricing preliminaries. This means the contractor may be entitled to an extension of time and/or additional payments when the actual works are undertaken.
Who’s responsibility is it to issue a valuation?
- On larger or more complex projects, often there will be a quantity surveyor (QS) preparing the valuation for the CA to issue; however, this guidance note covers building contracts where a QS will not be employed and so the CA will be named as the QS in the Articles of the building contract.
What should the CA in the event of materials on or off site?
Particular attention should be paid to whether or not the value of materials off site or on site, where they are not fixed to the works, should be included. The CA should be certain that legal title for the materials will pass to the employer if the items have not been fixed and are included in the valuation. To do this the CA may have to see evidence of receipted invoices from suppliers.
When is a certificate of vesting required?
Under the Sale of Goods Act, a seller is entitled to retain ownership until paid. The Contractor will therefore not be entitled to payment for products not incorporated into the Works which are subject to reservation of title.
What is a certificate of vesting?
A vesting certificate certifies that ownership of the goods, plant or materials listed in a schedule will transfer from one party to the other upon payment and confirming that they will be will be properly identified, separately stored, insured and are free from encumbrances (such as retention of title).
What is VAT?
Value added tax is a broadly based consumption tax assessed on the value added to goods and services.
The standard rate of VAT in the UK is 20%
Construction of new qualifying dwellings and communal residential buildings, and certain new buildings used by charities = 0%
What are retention monies?
Retention is a percentage (usually up to 5% of the contract sum) of each payment made under a construction contract which is withheld in order to try and ensure that works under the construction contract are completed to the required standard.