Contract Types Flashcards

1
Q

What is a lump sum contract?

A

Where the contract sum is determined before construction work is started. The contractor undertakes a defined amount of work in return for an agreed sum.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When is a lump sum contract appropriate?

A

For works designed by the Employer, where detailed contract provisions are necessary and the Employer is to provide the Contractor with drawings and specifications to define the quantity and quality of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a measurement contract?

A

Where the contract sum is not finalised until completion but is assessed on remeasurement to a previously agreed basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When is a measurement contract appropriate?

A

Can be used in situations where the design (or type of works) can be described in reasonable detail, but the amount cannot. For example, excavation works.

Often because for a good reason the work cannot be measured accurately before tenders invited.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the different contract types?

A
Lump sum
Measurement
Cost Reimbursement (cost plus)
Design and Build
Contractors design portion
Turnkey
Management contracting
Construction management
Partnering
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a cost reimbursement contract?

A

Where the sum is arrived at on the basis of prime (actual) costs of labour, plant and materials, to which there is added an amount to cover overheads and profit.

Sometimes referred to as ‘cost-plus’ or ‘prime-cost’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When is a cost plus contract appropriate?

A

Often used where the nature and scope of the work to be carried out cannot be property defined at the outset and the risks associated with the works are high, for example urgent repair works or rebuild following fire.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Design and Build contract?

A

Where the project documents will be written with the contractor’s design obligation relating to the whole works in mind.

Differs from ‘works and material’ contract in that they expressly provide for contractor’s design obligations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When is a design and build contract appropriate?

A

Speed – overlapping design and construction period can fast track the projects and reduce the overall programme.

Where price certainty is required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When is a design and build contract NOT appropriate?

A

Quality – Where the specification is not tightly controlled by the client and cost efficiencies are sought by the contractor.

Inflexibility – cost and time implications of changes made further into the contract period are at the discretion of the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Turnkey contract?

A

A form of contract under design and build procurement where the client settles on a complete package, usually to some standard specification from a commercial firm.

Delivers a project in a fully operational state that is ready to use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When is Turnkey contract appropriate?

A

Where the employer wants to be hands off and do not wish to by heavily involved in the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is management contracting?

A

Where the management contractor undertakes to manage the carrying out of the works through trade contractors who are contractually accountable to him.

The management contractor programmes, packages and obtains tenders for the works, which are each let on a competitive basis on lump-sum, firm-price contracts with the management contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is management contracting appropriate?

A

The Management Contracting approach is generally reserved for major projects with high levels of complexity.

Value – reduces risk premium for main contracts and ensures best price for each separately tendered works package.

Speed - This is a quick method of procuring a competitively tendered main contractor; it can also enable a quick start on site.

Flexibility - design activity can extend into the construction period.

Buildability - Early contractor input on the programme, buildability and content of works contract packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When is management contracting NOT appropriate?

A

Highly involved - This method requires a higher level of client involvement in rolling decision-making throughout the construction period, i.e. a very hands-on option for a client.

Cost uncertainty - The final cost is not known until the contract is complete (prime cost)

Programme risk - There is a programme risk, as the scope of work develops well into the construction phase and the final scope is not known until close to completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Construction Management?

A

Where the construction manager undertakes to manage the carrying out of the work through trade contractors, but the client is involved in the directing of the project and the contracts with trade contractors are directly with him.

Contractually, trade contracts are the clients risk.

17
Q

When is construction management appropriate?

A

When employer is experiences and construction savvy

Speed - This method can enable a quick start on site and fast-track project.

Flexibility - design activity can extend into the construction period.

Buildability - Early construction manager input on programme, buildability and the content of works contract packages.

Visibility – give employer complete visibility of amounts payable to trade contractors.

Complex projects – requiring detailed engagement of specialist subcontractors

18
Q

When is construction management NOT appropriate?

A

Fluctuation risk - Delayed procurement exposes the employer to the risk of market inflation fluctuation.

Cost uncertainty - The final cost is not known until the contract is complete.

Cost management - Construction manager has less incentive to tightly manage costs than under lump sum and carries no risk.

Programme risk - Programme certainty will not be achieved until all works contracts are agreed

19
Q

What is a partnering contract?

A

Introduces some form of collaborative working to unite parties to the project and avoid polarisation. The theory is that teamwork results in greater efficiency, resulting in increased cost and time certainty.

20
Q

When is partnering appropriate?

A

Only suitable where there is an intention to take partnering and collaborative working seriously.

The longer the contract, the greater the benefit of partnering as there is more opportunity for building working relationships, finding improvements and planning investment.

21
Q

What is the difference between management contracting and construction management?

A

Under management contracting the trade contracts are made with the management contractor. Under construction management, the trade contractors are contracted to the client but management by the construction manager.

22
Q

What are the pros and cons of lump sum contracts?

A

Pros

  • Cost certainty
  • Quality due to developed design
  • Client risk minimal

Cons

  • Slower procurement process due to separate design and construction stages.
  • Contractor not available to improve buildability.
  • Poor/inadequate design information can lead to disputed.
23
Q

What are the pros and cons of measurement contracts?

A

Pros

  • Can allow an early start on site before the design is completed in sufficient detail for BOQ.
  • Changes can be made relatively easily.

Cons
- The contract sum is not finalised until completion based on remeasurement of the actual works carried out.

24
Q

What are the pros and cons of cost reimbursement contracts?

A

Pros
- Can allow an early start on site before the design is fully developed.

Cons
- This is a high-risk form of contracting for the client as the final cost is not known when the contract is entered into.

25
Q

What are the pros and cons of design and build contracts?

A

Pros

  • Single point of responsibility for both design and construction.
  • Can allow an early start on site.
  • Benefit of contractors experienced harnessed during the design.

Cons

  • Client has to commit to concept design early.
  • Variations from the original brief can be difficult to arrange and expensive.
  • More difficult to compare tenders.
  • Lack of control over quality of final design.
26
Q

What are the pros and cons of Turnkey contracts?

A

Pros

  • Hands off with minimal client involvement.
  • Cost certainty

Cons

  • Relies on a well developed client brief and specification at the outset.
  • Lack of quality control by client.
27
Q

What is a contract?

A

A contract is a legally binding document that defines and governs the rights and obligations of parties to an agreement. Usually in the form of an agreement to provide a service for an agreed sum.