Extension of Time & Loss and Expense Flashcards

1
Q

What are the relevant events listed within the JCT Standard Contract?

A
  1. A variation
  2. An instruction by the Architect/Contract Administrator
  3. Deferment of possession
  4. Suspension of contract
  5. Impediment by the employer
  6. Statutory Undertaking
  7. Exceptionally adverse weather
  8. Loss or damage occasioned by a specified peril (fire, lightening, explosion, storm, flood)
  9. Civil commotion or threat of terrorism,
  10. Strike, lock-out affecting any trade employed upon the works
  11. The excise after the Base Date by the Government or local/public authority of any statutory power which directly affects the work
  12. A Named Specialist becoming insolvent
  13. Force majeure.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a relevant event?

A

A delay that impacts the completion date for the project, which is not the fault of the contractor, and for which they are therefore entitled to an extension of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What must contractor do to obtain an extension of time?

A

The contractor should submit a delay notice to the employer as soon as soon as it becomes reasonably apparent.

The delay notice should:

  • It should be in writing
  • State causes of delay
  • Identify Relevant Event
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the contract administrators obligations in assessing an extension of time?

A

Typically, will request further information

Give an extension of time that is reasonable

Give reasons within 12 weeks

State extension of time relating to each Relevant Event

Fix new completion date

Must issue a new non-completion certificate after each and every extension of time granted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is loss and expense?

A

Loss and expense is a contractual mechanism that allows the contractor to claim for a direct loss and/or expense as a result of the progress of the work being materially affected by the relevant matters for which the client is responsible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a relevant matter?

A

A Relevant Event which is a Client in Control Event and which therefore results in the contractor being awarded time and money for the delay.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Provide 4 examples of relevant matters?

A

Variation or change
Impediment by the employer
Deferment of possession
Delayed instructions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the extension of time procedure under JCT?

A
  1. Contactor to apply as soon as it becomes apparent – using a notice
  2. Architect (or EA in D&B or CA) will instruct QS to ascertain loss and expense.
    QS typically seeks further information required known as: ‘further and better particulars’.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What should a good contractors loss and expense claim notice contain?

A

State a ‘Relevant matter’

Cause and effect

Supporting info

Reference to docs and records

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When is time viewed to be ‘at large’?

A

Without the EOT and liquidated damages provisions, if the contractor is prevented from completing the works by the date for completion for reasons beyond his or her control, time would become ‘at large’ and liquidated and ascertained damages would be unenforceable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the most important clauses in relations loss and expenses claims?

A

The loss and expense must be actual; and the CA should therefore not estimate value but actually find out what the contractor has expended or lost. This will involve the CA making enquiries of the contractor.

Where the contract conditions contain the provision that the contractor must make written application to the CA that direct loss and expense will be incurred the CA must be satisfied that the contractor’s application has been made as soon as required under the conditions of the building contract. Delay in doing so could preclude a claim and this should be considered.

Whenever even part of the loss and expense is ascertained, it should be taken into account in the computation of the next interim certificate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a force majeure?

A

Exceptional, unforeseen events or circumstances that are beyond the reasonable control of a party to a contract and which prevent or impede performance of their obligations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a statutory undertaking?

A

Where a statutory undertaker such as a gas, electricity, or water company or a local authority is carrying out works in pursuance of a statutory obligation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a specified peril?

A

The contractor is entitled to an extension of time in the event that a delay is caused by any of the specified perils stated within the all-risks insurance, such as flood, fire or earthquakes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is concurrent delay?

A

A situation where a construction project is delayed by two events at the same time, one being an event for which the employer takes responsibility under the contract and the other for which the contractor takes responsibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What method of delay analysis are you aware of?

A

As planned vs as built, an planned impacted and Time impact analysis.

17
Q

What methods of delay analysis would you typically undertake on a smaller project?

A

As planned vs as built.

18
Q

What is the critical path?

A

The critical path establishes the relationship between the activities in the programme and applies estimated timings to these. The critical path can be defined as the determination of the shortest possible route from the programme start to the finish.

19
Q

What is a critical path analysis?

A

A critical path analysis is a project planning method that determines those tasks that are dependent on other tasks for their timely completion, which if delayed would ultimately delay the overall completion of the project.

20
Q

What is the procedure for loss and expense?

A

Contractor to provide a valid notice as soon as it becomes reasonably apparent.

CA will then instruct QS to ascertain loss and expense. They will typically see further and better particulars.