Producing a project plan may BEST be descried as:
A. Creating a network logic diagram that identifies the critical path.
B. Using a software tool to track schedule, cost, and resources.
C. Creating a document that guides project plan execution.
D. Creating a plan that contains the entire product scope.
C. Creating a document that guides project plan execution.
The project plan is a single, approved plan that drives execution, monitoring and control, and closure. Note that the definition in answer ‘C’ was not perfect, but it was the best choice.
Project management plan updates are NOT an output of:
A. Perform Integrated Change Control
B. Develop Project Management Plan
C. Direct and Manage Project Work
D. Monitor and Control Project Work
B. Develop Project Management Plan
The project management plan is created in Develop Project Management Plan. It, along with other plans, is updated in the other processes listed.
You are meeting with a new project manager who has taken over a project that is in the middle of executing. The previous project manager has left the company and the new project manager is concerned that change requests are streaming in from numerous sources including his boss, the customer, and various stakeholders. The project manager is not even aware of how to process all of these incoming change requests. Where would you refer him?
A. The project scope statement
B. The project management plan
C. The previous project manager
D. The project charter
B. The project management plan
The project management plan would contain the methods for processing change requests to the project.
Centurion Corporation has initiated a new project to modernize their human resources records and to bring them into compliance. A manager at Centurion is drafting the project charter for review. Which of the following would be the most important item that she would need in order to complete this task and why?
A. Managerial approval to proceedd, ecause it may affect whether or not the project moves forward.
B. A scope statement, because it will set the parameters for the product scope.
C. A scope statement, because it will set the parameters for the project scope.
D. A business case, because it explains the justification for the project.
D. A business case, because it explains the justification for the project.
The business case is one of the business documents that is an input to the process of Develop Project Charter, wherre the charter is created, making this the best choice. The business case provides the reasons why the project needed to be initiated.
The project charter is:
A. Developed before the business case, and after the project management plan.
B. Developed after the business case, and before the project management plan.
C. Developed before the contract, and after the project management plan.
D. Developed before the contract, and before the project management plan.
B. Developed after the business case, and before the project management plan.
In this case, the typical order among the items listed in the business case, contract, project charter, and project management plan. If you analyze the inputs and outputs used by the integration processes, you will gain a better understanding of this order. Questions like this will be on the exam, and in order to answer them, you have to understand the rough order in which the deliverables are produced and processes are conducted.
The project management information system would likely include all of the following EXCEPT:
A. A scheduling tool
B. An informatino distribution system
C. A system for collecting information from team members
D. A system for identifying stakeholders
D. A system for identifying stakeholders
The project managtement information system (PMIS) is an automated system to support the project manager by optimizing the schedule and helping collect and distribute information.
A defect in the product was brought to the project manager’s attention, and now the project team is engaged in repairing it. Which project management process would e the most applicable to this?
A. Perform Integrated Change Control
B. Monitor and Control Project Work
C. Direct and Manage Project Work
D. Close Project or Phase
C. Direct and Manage Project Work
Direct and Manage Project Work is the only process in the list where defects are repaired. Approved change requests are an input, and deliverables are an output.
If you are creating a single document to guide project executino, monitoring and control, and closure, you are creating:
A. The execution plan
B. The project management plan
C. The integratino plan
D. The project framework
B. The project management plan
This is the definition of the project management plan.
Change control meetings are held as part of which process?
A. Direct and Manage Project Work
B. Monitor and Control Project Work
C. Perform Integrated Change Control
D. Evaluate Requested Changes
C. Perform Integrated Change Control
As you think about this one, ask yourself which process group would use a tool like change control meetings. The answer to that questino is “monitoring and controlling”. Now, you can immediately narrow it down to two processes in mind. Change requests flow out of Monitor and Control Project Work and into Perform Integrated Change Control, where they are evaluated in meetings.
Which of the following statements is NOT true regarding the project charter?
A. The project charter justifies why the project is being undertaken.
B. the project charter assigns the project manager.
C. The project charter specifies any high-level schedule milestones.
D. The project charter specifies the types of contracts that will be used.
D. The project charter specifies the types of contracts that will be used.
The project charter does not specify anything about contracts. A contract with your customer would have been an input into the Develop Project Charter process, and any contracts you may use during procurement won’t be identified until later in the project.
Which of the following represents the project manager’s responsibility regarding change on a project?
A. To influence the factors that cause project change.
B. To ensure all changes are communicated to the change control board.
C. To reduce change wherever possible.
D. To prioritize change below results.
A. To influence the factors that cause project change.
the project manager must be proactive and influence the factors that cuase change. This is one of the key tenets of monitoring and controlling processes in general and Perfrom Integrated Change Control in particular.
The project management plan is made up of:
A The other planning outputs.
B. The other planning outputs, tools, and techniques.
C. The aggregate outputs of the PMIS.
D. The business case, key value justifications, and the GANTT chart.
A The other planning outputs.
The project management plan consists of many things, but the only one from this list that matches is the outputs from the other planning processes, such as risk, cost, time, quality, etc.
When changes are approved and made to the project, they should be:
A. Tracked against the project baseline.
B. Incorporated into the project baseline.
C. Included as an addendum to the project plan.
D. Approved by someone other than the project manager.
B. Incorporated into the project baseline.
Approved changes that are made to the project get factored back to the baseline.
Which statement about project agreements is true?
A. Agreements are drafted between the project manager and the key stakeholders prior to resources being expanded.
B. Agreements are generally created only when one ore more portions of the project are being procured from outside the organization.
C. Agreements are inputs to create the project charter.
D. Agreements are broadly considered to be an enterprise environmental factor.
C. Agreements are inputs to create the project charter.
Agreements are one of four inputs used to create the project charter.
Work performance informatino is used for all of the following reasons EXCEPT:
A. It provides information on resource utilization.
B. It provides informatino on which activities have started.
C. It shows what costs have been incurred.
D. It is used to help identify defects.
D. It is used to help identify defects.
The work performance informatino is all about how the work is being performed, but is not used in identifying defects.