Housing Maintenance, Repairs and Improvements - Level 3 Flashcards
What are the key principles of RICS Service Charge Resi Management Code 3rd Ed?
Code of Practice - Best Practice
- Approved by the Secretary of State - effective from 1 June 2016
- Improve standards, reasonableness and transparency in the management and administration of long leaseholder
- Ensure the timely issue of all documentation inc. budgets and YE accounts
- Reduce the risk of disputes
What are the key principles of RICS Health and Safety for Resi Property Managements 1st Ed?
Guidance Note - Best practice - Advisory
Assists those who are responsible to ensure the property under their control meets statutory obligations.
What are Landlord’s lease obligations?
- Repair and maintenance
- Insurance
- Redecoration
- YE accounts
What does ‘fit for human habitation’ means?
Under the Housing Act 2004 Consider te following; 1. repairs 2. damp 3. ventilation 4. drainage 5. utilities
How did you know the electrician was qualified?
- Safe Contractor database
2. NICEIC qualified (National Inspection Council for Electrical Installation Contracting)
What is an example of unsatisfactory EICR?
- Lack of insulation
- Incorrect wiring
- Out of date fuse board
What is a Capex Plan?
A financial forecast for major works at a property over a 5 to 10 year period.
Why is it important to accumulate a reserve fund?
- To ensure funds are held for unforeseeable large expenditure
- Good estate management as allows leaseholders to manage finances
- Normally cant demand additional funds
What happens if a leaseholder applies to the FTT under Section 19 LTA 1985?
- Apply to FTT to determine liability to pay and reasonableness of service charge
- They will review the…..(ask jamie)
What is the case of London Borough of Hounslow Vs Waaler 2017?
.
how do you montior the capex plan at the end of each year?
I update he bottom line of the capex plan at each year end and revise the year’s expenditure following yearsd opening balance.
What is the process for carrying out works to the point of instruction?
- Agree scope of works
- Carry out a detailed survey
- Produce a detailed specification
- Invite competent contractors to return tender
- Tender analysis
Why is it important to carefully plan the specifcation?
If a specification is not clearly detailed then it leaves it open to interpretation by contractors, thus they will not be comparable.
- Risk that if a specification lacks detail or clarity a project will not be completed to the required standard.
- The client doesn’t want to spend money on fees so decrease the size of the project and end up spending more in the long run.
- Don’t appoint an competent Building Surveyor or specialist.
What are the benefits of a sufficiently detailed specification?
- All unique characteristics of a building will be taken into account and therefore a realistic price obtained
- All tenders will be comparable
- There will be a provision for contingency planning
Why competitively tender a major works project?
- To achieve value for money
- Assure most competent and appropriately skilled contractor is appointed
- Reduces the risk of disputes and programme/budget run overs.
- Required under section 20 to gather multiple quotes