Hot Topics (11) Risk Management Flashcards
What is the process of risk management?
- 1- Plan Risk Management
- 2- Identify Risks
- 3- Perform Qualitative Risk Analysis
- 4- Perform Quantitative Risk Analysis
- 5- Plan Risk Responses
- 6- Control Risks
What is the key output of the Plan Risk Management process?
Risk management plan
What is the key output of the Identify Risks process?
Risk register
What key ouputs of the Perform Qualitative Risk Analysis process are added to the risk register?
Risk ranking for the project
Prioritized risks and their probability and impact ratings
Risks grouped by category
List of risks requiring additional analysis and response
List of risks requiring analysis in the near term
Watch list (noncritical risks)
What key outputs of the Perform Quantitative Risk Analysis process are added to the risk register?
Prioritized list of quantified risks
Initial amount of contingency time and cost reserves needed
Possible realistic and achievable completion dates and project costs
Quantified probability of meeting project objectives
Trends in quantitative risk analysis
What key outputs of the Plan Risk Responses process are added to the risk register?
Residual risks Contingency plans Fallback plans Risk owners Secondary risks Risk triggers Contracts Reserves for time and cost
What are the key outputs of the Control Risk process?
Work performance information Risk register updates Change requests Updates to the project management plan and project documents Updates to organizational process assets
What key outputs of the Control Risks process are added to the risk register?
Outcomes of risks reassessments and risk audits
Result of implemented risk responses
Updates to previous parts of risk management
Closing of risks that are no longer applicable
Details of what happened when risks occurred
Lessons learned
What is a risk?
A future occurrence that may or may not happen that can have a positive (opportunity) or negative (threat) impact on the project
What are the four key factors that need to be determined for each risk?
Probability
Impact
Timing
Frequency
A person who is risk averse is:
Unwilling to take risks
Define risk appetite, risk tolerance, and risk threshold.
Risk appetite: a general, high-level description of the acceptable level of risk
Risk tolerance: a measurable amount of acceptable risk
Risk threshold: the specific point at which risk becomes unacceptable
What are the inputs to the risk management process?
Project background information and other organizational process assets
Enterprise environmental factors
Project charter, network diagram, and other project documents
Project management plan (including scope baseline and the knowledge area plans)
Time and cost estimates
Procurement documents
Stakeholder register
Work performance data and reports
What are some examples of sources of risk?
Technical Project management Schedule Cost Quality Scope Resources Customer satisfaction
What are some examples of risk identification techniques?
Document reviews Information-gathering techniques SWOT analysis (Strengths, Weaknesses, Opportunities, Threats) Checklist analysis Diagramming techniques