Hot Topics (1-2) Project Management Framework Flashcards

1
Q

What is the definition of a project?

A

Temporary

Creates a unique product, service, or result

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is operational work?

A

Ongoing work to support the business and systems of organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the definition of a program?

What is the definition of a portfolio?

A

Program: A group of interrelated projects, managed in a coordinated way
Portfolio: A group of programs, individual projects, and related operational work to achieve a specific strategic business goal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is organizational project management (OPM)?

What are its benefits?

A

A framework for keeping the organization focused on its overall strategy
Provides direction for how portfolios, programs, projects, and other organizational work should be prioritized, managed, executed, and measured to best achieve the firm’s strategic goals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is OPM3?

A

A PMI model designed to help organizations determine their level of maturity in project management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a project management office (PMO)?

What are three possible formats for a PMO?

A

A department that centralizes and standardizes the management of projects

  • Supportive
  • Controlling
  • Directive
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are project constraints?

A
  • Time
  • Cost
  • Risk
  • Scope
  • Quality
  • Resources
  • Customer satisfaction

Contraints are used to help evaluate competing demands

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who are project stakeholders?

A

Anyone whose interests may be positively or negatively impacted by the project, including:

  • Project manager, Customer, Sponsor
  • Performing organization, Others départements or groups within the organization
  • Team members, Team member’s functional or operational managers
  • Sellers, Funding sources, End users, PMO
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are three primary forms of organizational structure?

A

Functional
Projectized
Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a functional organization?

A

The organization is grouped by areas of specialization (e.g. accounting, marketing)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a projectized organization?

A

The organization is grouped by project
The team has no department to go at project end
The project manager has total control of ressources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a matrix organization?

A

A blend of functional and projectized organisation where the team members have two bosses (the project manager and functional manager)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a strong matrix organization?

A

A matrix organization where the balance of power rests with the project manager instead of the functional manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a weak matrix organization?

What role might the project manager play in a weak matrix?

A

A matrix organization where the balance of power rests with the functional manager instead of the project manager
A project expediter or project coordinator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a balanced matrix organization?

A

A matrix organization where power is equally balanced between the project manager and the functional manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is a project-based organization?

A

A temporary framework for projects created to circumvent any obstacles inherent in the organization’s existing structure (whether functional, projectized, or matrix)

17
Q

What are entreprise environmental factors?

When are they used?

A

The organization’s culture and existing systems that the project will have to deal with or can make use of
They are used throughtout the project management process

18
Q

What are organizational process assets?

When are they used?

A

Company processes and procedures
Historical information
Lessons learned

They are used throughout the project management process

19
Q

What is historical information?

A

Records of past projects, including lessons learned, used to plan and manage future projects
Records of the current project that will become part of organizational process assets

20
Q

What is a project management information system?

A

The automated system to submit and track changes and monitor and control project activities

21
Q

What do lessons learned describe?

How are lessons learned used?

A

What went right, what went wrong, and what would be done differently if the project could be redone

Used in planning the project
Used by other projects in the future

22
Q

What is work performance data?

A

Measurements and details about activities gathered during project work (executing)

23
Q

What is work performance information?

A

Work performance data analyzed to make sure it conforms to the project management plan and to assess what it means for the project as a whole

24
Q

What are work performance reports?

A

Work performance information organized into reports that are distributed to the stakeholders

25
Q

What is a product life cycle?

A

The cycle of a product’s life from conception to withdrawal from the marketplace

26
Q

What i a project life cycle?

A

What you need to do to COMPLETE the work (produce the deliverables of the project)
It varies by type of product, industry, and the organization’s preferences

27
Q

Describe a plan-driven project

A

Has a predictive life cycle in which scope, schedule, and cost are determined in detail early in the life of the project, before the work begins to produce the project deliverables

28
Q

Describe a change-driven project

A

Uses iterative, incremental, or adaptive (agile) life cycles

Has varying levels of early planning for scope, schedule, and cost