HLC 22 Flashcards
Unit 1 is at 45% power steady state. A leak on the upper instrument tap (reference leg) associated with the SELECTED “Pressurizer (Pzr) Level Transmitter,” LT-1110X occurs.
Assuming NO Operator actions, which ONE of the following would be the response of the Pressurizer Pressure Level Control System?
Indicated Pzr Level / Actual Pzr Level
A. lowers / rises
B. rises / rises
C. rises / lowers
D. lowers / lowers
C.
rises / lowers
Given the following conditions on Unit 1:
* The reactor has been manually tripped and the crew is implementing 1-EOP-01,
“Standard Post Trip Actions” * The Core Heat Removal Safety Function has JUST been completed.
* Pressurizer pressure is 1590 psia
* Containment pressure is 5.5 psig
Which ONE of the following completes the statements below:
A Safety Injection Actuation signal __(1)__ occurred.
The required status of the Reactor Coolant pumps at this time is __(2)__ should be
secured.
A. 1) HAS
2) ONE RCP in each loop
B. 1) HAS
2) ALL four RCPs
C. 1) HAS NOT
2) ONE RCP in each loop
D. 1) HAS NOT
2) ALL four RCPs
A. 1) HAS
2) ONE RCP in each loop
Given the following conditions on Unit 2:
* A Loss of Coolant Accident (LOCA) has occurred
* Reactor Coolant System pressure is 75 psia
Which ONE of the following is monitored or performed with regards to Short and Long Term Core Cooling given the above conditions?
Short Term Cooling / Long Term Cooling
A. Low Pressure Safety Injection operation / Align Shutdown Cooling
Safety Injection Tanks discharge
B. Low Pressure Safety Injection operation / Align High Pressure Safety Injection
Safety Injection Tanks discharge hot and cold leg injection with a
Recirculation Actuation Signal
C. High Pressure Safety Injection operation / Align Shutdown cooling
Steam Generator steaming
D. High Pressure Safety Injection operation / Align High Pressure Safety Injection
Steam Generator steaming hot and cold leg injection with a
Recirculation Actuation Signal
B.
Low Pressure Safety Injection operation / Align High Pressure Safety Injection
Safety Injection Tanks discharge hot and cold leg injection with a
Recirculation Actuation Signal
Unit 2 is at 100% power
Given the following indications on the 2A1 Reactor Coolant Pump (RCP):
* Controlled Bleedoff (CBO) temperature is 225oF
* CBO flow is 2.5 gpm
* Vapor Seal Cavity pressure is 80 psia
* Upper Seal Cavity pressure is 2235 psia
* Middle Seal Cavity pressure is 2235 psia
Which ONE of the following describes the status of the RCP seals and required action?
A. ONLY One RCP seal has failed; perform a controlled shutdown then secure the 2A1
RCP.
B. ONLY Two RCP seals have failed; trip the reactor and secure the 2A1 RCP.
C. ONLY Two RCP seals have failed; perform a controlled shutdown then secure the
2A1 RCP.
D. Three RCP seals have failed; trip the reactor and secure the 2A1 RCP.
C.
ONLY Two RCP seals have failed; perform a controlled shutdown then secure the
2A1 RCP.
Unit 1 is operating at 100% power.
The SNPO reports that a break in the Charging header has occurred.
The following indications noted on the RTGB:
* Charging Header pressure is 0 psig
* Charging Header flow is 0 gpm
* Reactor Cavity leakage is 0.1 gpm and steady
Which ONE of the following completes the statements below:
Annunciator __(1)__ should be in alarm for this condition.
Due to the leak location, __(2)___ Charging pump(s) can be used when aligning per 1- AOP-02.03, “Alternate Charging Flow Path Through the Auxiliary HPSI Header.”
(Reference Provided)
A. 1) M-7, “Regenerative Heat Exchanger Letdown ΔP High”
2) either the 1A, 1B OR 1C
B. 1) M-28, “Regenerative Heat Exchanger Outlet Temp High”
2) either the 1A, 1B OR 1C
C. 1) M-7, “Regenerative Heat Exchanger Letdown ΔP High”
2) ONLY the 1A
D. 1) M-28, “Regenerative Heat Exchanger Outlet Temp High”
2) ONLY the 1A
D.
1) M-28, “Regenerative Heat Exchanger Outlet Temp High”
2) ONLY the 1A
Given the following conditions on Unit 1:
* The unit is currently shutdown for a refueling outage
* The Reactor Head is being removed
* The RCS level 35 feet
* Time since reactor shutdown is 250 hours
* Reactor Coolant System (RCS) temperature is 95º F
.
Which ONE of the following choices completes the statement below:
If all SDC was lost, with the conditions given above, the Time to Boil is approximately____ minutes.
(References Provided)
A. 28
B. 30
C. 37
D. 40
B. 30
Given the following conditions on Unit 1:
* The 1A and 1B Component Cooling Water (CCW) pumps are running
* The 1C CCW pump is in standby in accordance with 1-NOP-14.02, “CCW
System Operation,” and is aligned to the “B” train electrically and mechanically
* A Loss of Offsite Power (LOOP) has just occurred
* The 1B CCW pump failed to start following the LOOP
* 1 minute later, a Loss of Coolant Accident (LOCA) with SIAS and CIAS actuation occurred
Which ONE of the following describes the configuration of the CCW system at this time?
(Assume no operator actions)
A. ONLY 1 CCW pump supplying all CCW loads due to the failure of “1B” CCW pump to start.
B. Two CCW pumps supplying all CCW loads due to SIAS start of the “1C” CCW pump.
C. ONLY 1 CCW pump supplying its own safety header due to ESFAS isolation of the Non-Essential header.
D. Two CCW pumps supplying all CCW loads due to SIAS start of the “1C” CCW pump until the Non-Essential header isolates on a loss of instrument air.
C. ONLY 1 CCW pump supplying its own safety header due to ESFAS isolation of the
Non-Essential header.
Given the following conditions on Unit 1:
* The unit is operating at 100% power
* PIC-1110X, “Pressurizer (Pzr) pressure controller” is selected
* Pzr pressure is being maintained at 2250 psia with Pzr Backup Heaters B1, B2,
and B5 ON with a 10% output to the Pzr Proportional Heaters
* PT-1110Y is out of service for I&C calibration
PT-1110X begins to slowly fail high.
Which ONE of the following choices completes the statement below:
IAW 1-AOP-01.10 “Pressurizer Pressure and Level,” the operator is directed to take manual control of HIC-1100, “Spray Valve controller” and __(1)__ its output in order to __(2)__ ACTUAL Pzr Pressure.
A. 1) lower
2) lower
B. 1) lower
2) raise
C. 1) raise
2) raise
D. 1) raise
2) lower
B.
1) lower
2) raise
Given the following conditions on Unit 1:
* Reactor power is 100%
* A total loss of feedwater event occurred
* The Reactor Protection System FAILED TO AUTOMATICALLY TRIP the reactor when trip conditions were present
* No operator actions have been taken
Which ONE of the following describes the expected reactivity change AND the impact on the Reactor Coolant System (RCS) Pressure from this event?
Over the next 5 minutes, reactor power will:
A. Stay the same; an RCS over pressure condition will be prevented due to the event being within the design bases of the Pressurizer Safety valves.
B. Stay the same; an RCS pressure excursion that could potentially challenge the RCS pressure boundary integrity will be prevented by the Diverse Scram System.
C. Lower; an RCS over pressure condition will be prevented due to the event being within the design bases of the Pressurizer Safety valves.
D. Lower; an RCS pressure excursion that could potentially challenge the RCS pressure boundary integrity will be prevented by the Diverse Scram System.
D. Lower; an RCS pressure excursion that could potentially challenge the RCS
pressure boundary integrity will be prevented by the Diverse Scram System.
Given the following conditions on Unit 1:
* The unit was operating at 100% power
* A Steam Generator Tube Rupture (SGTR) occurs
* 1-EOP-04, “SGTR” is being implemented
* SIAS actuation has occurred
* A Reactor Coolant System (RCS) cool down and depressurization is in progress
The crew is evaluating RCS Void Elimination per 1-EOP-99, Appendix K, RCS Fill and Drain Method of Void Elimination.”
Which ONE of the following is an indication that voids are present in the Reactor Vessel Head?
A. RVLMS indicates segments voided.
B. Pressurizer Level lowering while spraying.
C. Pressurizer level rising while charging to the RCS.
D. The saturation temperature of the RCS is higher than the temperature in the upper Rx Head region.
A. RVLMS indicates segments voided.
Given the following:
* The Unit 1 reactor tripped from 100% power 15 minutes ago
* The 1A and 1B Auxiliary Feedwater (AFW) pump’s header flow control valves have been throttled to the desired flow rate for BOTH SGs
* The 1C AFW pump header flow control valves were closed
* The 1A and 1B Steam Generator (SG) Narrow Range levels are 10% and slowly rising
* A Loss of Offsite Power (LOOP) has just occurred and BOTH Emergency Diesel Generators (EDGs) are supplying power to their respective 4.16kVAC busses
To maintain Reactor Coolant System temperature stable, which ONE of the following describes the manual operator action that must be taken on the AFW header flow control valves in response to the LOOP?
The 1A and 1B AFW pump header flow control valves __(1)___.
The 1C AFW pump header flow control valves __(2)__.
A.
1) require throttling closed
2) require throttling closed
B.
1) remain throttled
2) require throttling closed
C.
1) require throttling closed
2) remain closed
D.
1) remain throttled
2) remain closed
C.
1) require throttling closed
2) remain closed
Given the following conditions on Unit 1:
* A Station Blackout has occurred and 1-EOP-10, “Station Blackout,” is being implemented
* The crew is evaluating Single Phase Natural Circulation criteria
* The BRCO reports the ΔT between REP CET and Thot is 18oF and increasing
Which ONE of the following choices describes:
1. The contingency action, in 1-EOP-10, “Station Blackout,” that is to be taken if Single Phase Natural Circulation criteria is BEING challenged?
AND
2. The operational implications if the temperature difference between Thot and REP CET exceeds the Single Phase Natural Circulation criteria limits?
A.
1) Verify Two Phase Natural Circulation CRITERIA.
2) The Hot Legs are becoming thermodynamically uncoupled from the core.
B.
1) Verify Two Phase Natural Circulation CRITERIA.
2) The Reactor Coolant System is approaching saturated conditions.
C.
1) Ensure proper control of Steam Generator feeding and steaming.
2) The Hot Legs are becoming thermodynamically uncoupled from the core.
D.
1) Ensure proper control of Steam Generator feeding and steaming.
2) The Reactor Coolant System is approaching saturated conditions.
C.
1) Ensure proper control of Steam Generator feeding and steaming.
2) The Hot Legs are becoming thermodynamically uncoupled from the core.
Given the following conditions for Unit 2:
* The unit is operating at 100% power
* The 2AB 4.16kVAC bus is aligned to the 2B3 4.16kVAC bus
* HVA/ACC-3C is the running air conditioning unit
* HVA/ACC-3A and HVA/ACC-3B control switches are aligned as required per 2-
NOP-25.07, “Control Room Ventilation System”
* A Loss of Offsite Power (LOOP) has occurred
Which ONE of the following describes the final configuration of HVA/ACC-3A and HVA/ACC-3B Air Conditioning units AFTER the EDG loading sequence is complete?
HVA/ACC-3A is __(1)__.
HVA/ACC-3B is __(2)__.
A.
1) running
2) not running
B.
1) not running
2) not running
C.
1) not running
2) running
D.
1) running
2) running
A.
1) running
2) not running
Given the following conditions on Unit 1:
* The unit is operating at 100% power
* A loss of the 1MB 120VAC “Vital Instrument Inverter” occurs
Which ONE of the following choices completes the statements below:
The “B” Channel Steam Generator (SG) Pressure and Level Safety channel indication will be affected on the __(1)_.
The Reactor Protection System coincidence for a reactor trip will now be __(2)__ on Low SG Pressure or Level.
A.
1) “A” and “B” SGs
2) 1 out of 3
B.
1) “A” and “B” SGs
2) 2 out of 3
C.
1) “B” SG ONLY
2) 1 out of 3
D.
1) “B” SG ONLY
2) 2 out of 3
A.
1) “A” and “B” SGs
2) 1 out of 3
Given the following conditions on Unit 1
* Unit 1 was operating at 100% power
* The 1AB busses are aligned to the “A” train
* The unit tripped and the crew is carrying out actions of EOP-01, “Standard Post Trip Actions”
* During the Maintenance of Vital Auxiliaries Safety Function, the DRCO reports that the 1AB DC bus is de-energized
Which ONE of the following actions are required in accordance with EOP-01 AND also satisfies the design basis:
Within ______ , re-energize the 1AB DC bus from the ________.
A. 10 minutes; 1AB Battery Charger
B. 10 minutes; 1B DC bus
C. 2 hours; 1AB Battery Charger
D. 2 hours; 1B DC bus
B. 10 minutes; 1B DC bus
Given the following:
* Unit 2 is operating at 100% power.
* The 2B3 4.16kVAC bus has been de-energized due to a differential current lockout
* The 2AB 4.16kVAC bus is aligned to the “A” train
* The crew was UNSUCCESSFUL in resetting the differential current lockout relay
* The US directed that the 2B Intake Cooling Water (ICW) pump control switch be placed in “Pull-to-Lock” AND the 2C ICW pump MECHANICALLY aligned to the “B” train
* The US also directed that the 2B Component Cooling Water pump (CCW) pump control switch be placed in “Pull-to-Lock” AND the 2C CCW pump MECHANICALLY aligned to the “B” train
* The 2C ICW pump and the 2C CCW pump were then started as directed by 2-AOP-47.01B, “Loss of a Safety Related AC Bus-Train B”
Which ONE of the following statements describes ALL of the consequences associated with the ICW system AND the CCW system being in this configuration per Ops Policy 503?
A.
Offsite Power Operability for two ICW pumps running on the same electrical bus;
Offsite Power Operability for two CCW pumps running on the same electrical bus.
B.
Offsite Power Operability for two ICW pumps running on the same electrical bus.
C.
Offsite Power Operability for two ICW pumps running on the same electrical bus;
Offsite Power Operability AND Emergency Diesel Generator Operability for two CCW pumps running on the same electrical bus.
D.
Offsite Power Operability AND Emergency Diesel Generator Operability for two CCW pumps running on the same electrical bus.
A.
Offsite Power Operability for two ICW pumps running on the same electrical bus;
Offsite Power Operability for two CCW pumps running on the same electrical bus.
Given the following:
* An uncomplicated trip from 100% power has occurred on Unit 2
* 2-EOP-01, “Standard Post Trip Actions” is being implemented
* Reactor power is 1.0E-6% and lowering as indicated on Wide Range Instrumentation
Which ONE of the following describes the status of the Nuclear Startup Channels?
A. Energized. They automatically energized at 1.0 E-5% power.
B. NOT energized. They will be manually energized while implementing 2-EOP-01, “Standard Post Trip Actions.”
C. Energized. They automatically energized on the reactor trip signal.
D. NOT energized. They will be manually energized after 2-EOP-02, “Reactor Trip Recovery” is entered.
D. NOT energized. They will be manually energized after 2-EOP-02, “Reactor Trip Recovery” is entered.
Given the following:
* Unit 1 Reactor is at a stable power level of 2% in preparation for plant start up
* An ESDE on the 1A Steam Generator (SG) inside containment occurred
* Reactor Coolant System (RCS) Tavg is currently 515°F and lowering
* RCS pressure is 2220 psia and lowering
* Pressurizer level is 25% and lowering
* Both Atmospheric Dump Valves (ADV’s) are in service operating in Auto
After the reactor is tripped, which ONE of the following describes:
1) The expected plant response.
AND
2) After the 1A SG dries out, operate the 1B ADV at a saturation pressure for
_____.
A.
1) BOTH SGs will depressurize at the same rate until MSIS.
2) RCS Tavg of 525oF to 535oF
B.
1) ONLY the 1A SG will depressurize.
2) the lowest RCS TCOLD
C.
1) BOTH SGs will depressurize at the same rate until MSIS.
2) the lowest RCS TCOLD
D.
1) ONLY the 1A SG will depressurize.
2) RCS Tavg of 525oF to 535oF
B.
1) ONLY the 1A SG will depressurize.
2) the lowest RCS TCOLD
Unit 2 is in Mode 2 with the following:
* A reactor startup is in progress using 2-GOP-302, “Reactor Plant Startup – Mode 3 to Mode 2”
* Reactor power is 1.0E-5%
* CEA group 5 is at 52 inches and being withdrawn in manual sequential to a planned stopping height of 60 inches
* CEA #59 does not move with the rest of the Group 5 CEAs
If the CEAs were continued to be withdrawn, which ONE of the following alarms are expected during this evolution?
A. K-29, CEA PDIL (ADS).
B. K-18, Auto Withdraw Prohibit.
C. K-11, CEA Motion Inhibit.
D. K-26, CEA Withdrawal Prohibit.
C. K-11, CEA Motion Inhibit.
Given the following:
* Unit 2 tripped from 100% due to a Loss of Offsite Power (LOOP)
* All “AB” electrical busses are aligned to the “B” side
* The 2B Charging pump is out of service with its control switch in stop
Following the trip:
* The 2A Emergency Diesel Generator (EDG) tripped on overspeed
Which ONE of the following choices completes the statement below:
If a condition requiring the crew to emergency borate existed, operators would be required to start the 2C Chg pump and emergency borate via the ___(1)____ to establish a flowpath.
If a SIAS were to subsequently occur, the 2C Chg pump breaker would __(2)__.
A.
1) 2B Boric Acid Makeup pump and Emergency Borate valve (V2514)
2) open then reclose on the load block sequencer
B.
1) Gravity Feed valves (V2508 and V2509)
2) remain closed
C.
1) 2B Boric Acid Makeup pump and Emergency Borate valve (V2514)
2) remain closed
D.
1) Gravity Feed valves (V2508 and V2509)
2) open then reclose on the load block sequencer
B.
1) Gravity Feed valves (V2508 and V2509)
2) remain closed
Given the following conditions on Unit 2:
* The reactor is operating at 100% power
* Channel “X” for Pressurizer (Pzr) Level control is SELECTED
* Channel “Y” for Pzr Level control, LT-1110Y, failed LOW
Which ONE of the following states:
1) the CURRENT status of the Pzr Heaters
AND
2) after selecting the “LEVEL” position on the Back Up Interlock Bypass Key Switch (B/U INTLK BP Key), which Pzr heaters are available?
A.
1) All Pzr heaters off
2) All
B.
1) All Pzr heaters off
2) “A” side Pzr heaters ONLY
C.
1) ONLY “B” side Pzr heaters off
2) “A” side Pzr heaters
D.
1) ONLY “B” side Pzr heaters off
2) All
B.
1) All Pzr heaters off
2) “A” side Pzr heaters ONLY
Given the following:
* Core Reload is in progress on Unit 2
* 32 Fuel Assemblies have been loaded into the core
* During insertion of the 33rd assembly, the BRCO reports that count rate has increased from 10 CPS to 24 CPS
Which ONE of the following describes the action required in accordance with 0-NOP-67.05, “Refueling Operation,” for the stated conditions?
A. Direct Reactor Engineering to assess the nuclear instrument readings used for the 1/M plot and verify that they do NOT extrapolate to “0” when fuel movement resumes.
B. Direct Reactor Engineering to validate the method being used to calculate the 1/M and renormalize the 1/M prior to inserting the next fuel assembly.
C. Stop inserting the fuel assembly and verify Shutdown Margin while maintaining the fuel assembly at the current position.
D. Stop inserting the fuel assembly and withdraw it into the Refueling Machine Hoist/Mast then verify Shutdown Margin.
D. Stop inserting the fuel assembly and withdraw it into the Refueling
Machine Hoist/Mast then verify Shutdown Margin.
Unit 1 is performing a Liquid Release of the 1A Waste Monitor Tank when the following
alarm is received:
LIQUID WASTE RAD HIGH N-37
LIQUID RELEASE FLOW CONTROL VALVE, FCV-6627X, indicates open and will not close from the RTGB.
IAW 1-AOP-06.02, “Uncontrolled Release Of Radioactive Liquids,” which ONE of the following is a required SUBSEQUENT Operator action?
A. At the 1A Waste Monitor Storage Tank, stop the 1A Waste Monitor pump from the local control box AND at the CCW platform, lock closed V21462, “Waste Monitor Pumps Discharge to Discharge Canal Isolation valve.”
B. At the 1A Waste Monitor Storage Tank, close FCV-6627X AND at the CCW platform, lock closed V21462, “Waste Monitor Pumps Discharge to Discharge Canal Isolation valve.”
C. From the Liquid Waste Control panel ONLY, stop the 1A Waste Monitor pump AND close V21462, “Waste Monitor Pumps Discharge to Discharge Canal Isolation valve.”
D. From the Liquid Waste Control panel, close FCV-6627X AND at the Waste Monitor Storage Tanks, stop the 1A Waste Monitor pump from the local control box.
A. At the 1A Waste Monitor Storage Tank, stop the 1A Waste Monitor pump from the
local control box AND at the CCW platform, lock closed V21462, “Waste Monitor
Pumps Discharge to Discharge Canal Isolation valve.”
Given the following on Unit 1:
* Several fire detectors have alarmed in the Cable Spreading Room
Which ONE of the following describes the expected actuation?
A. Halon will charge the header, but only discharge into the room when the header fuseable link melts.
B. Halon will charge the header and then automatically discharge into the room.
C. Pre-action dry pipe header will be charged with water, and then automatically discharge into the room.
D. Pre-action dry pipe header will be charged with water, but only discharge into the room when the header fuseable link melts.
B. Halon will charge the header and then automatically discharge into the room.
Given the following conditions on Unit 1:
* The reactor is operating at 100% power
* A full “B” train INADVERTENT CIAS occurred
* 1-AOP-69.01 “Inadvertent ESFAS Actuation” was entered
* Section 4.2.2 “Recovery from Inadvertent CIAS” is being performed for “B” train CIAS components
* “B” train valve V6555 “Waste Gas Containment Isolation valve” (downstream) is indicating OPEN on the RTGB
* “A” train valve V6554 “Waste Gas Containment Isolation valve” (upstream) is indicating OPEN on the RTGB
* The affected Containment Penetration is #31
Which ONE of the following MEETS the required action, if any, per 3.6.3.1, “Containment Isolation Valves?” (consider each selection independently)
A. NONE since V6554 is OPERABLE.
B. V6554 must be CLOSED ONLY.
C. V6555 must be CLOSED AND DE-ENERGIZED.
D. V6555 must be CLOSED ONLY.
C. V6555 must be CLOSED AND DE-ENERGIZED.
Given the following conditions on Unit 1:
* The reactor is at 100% power
* Increased Reactor Coolant System (RCS) activity has caused entry into 1-AOP-01.06, “Excessive RCS Activity”
* The specific activity of the RCS has stabilized at 0.15 uCi/gram Dose Equivalent (DEQ) Iodine 131
* DEQ XE-133 is at normal levels
IAW 1-AOP-01.06, which ONE of the following is a required action based on the current level of DEQ I-131 and the reason for the action?
A. Isolate letdown to prevent high gamma radiation areas in the RCA.
B. Position V6307, “Flash Tank Divert Valve,” to the Flash Tank to strip fission product gasses.
C. Commence a plant shutdown due to RCS chemistry limits being exceeded.
D. Place all available CVCS Ion Exchangers in service to provide additional mechanical filtration to reduce RCS activity.
B. Position V6307, “Flash Tank Divert Valve,” to the Flash Tank to strip fission product
gasses.
Given the following:
* Unit 2 is operating at 100% power
* The 2A Charging (Chg) pump is running
* The 2B Chg pump switch is in AUTO
* The Chg pump selector switch is in the 2A-2B position
A Small Break Loss of Coolant Accident then occurs with the following:
* The Reactor is manually tripped
* SIAS has actuated
* Pressurizer level is 25% and slowly rising
* All Charging pumps are now running
Complete the following statements:
(consider each statement independently)
The 2C CHG pump ___(1)____ following the SIAS signal.
Later in the event, if Pressurizer Level rises above Chg pump cut off set point, the 2B CHG pump (back-up) will __(2)___.
A.
1) was manually started
2) remain running
B.
1) was manually started
2) auto stop
C.
1) automatically started
2) remain running
D.
1) remains running
2) auto stop
A.
1) was manually started
2) remain running
The following conditions exist on Unit 1:
* The Reactor Coolant System (RCS) is solid, preparing for Reactor Coolant Pump sweeps IAW 1-NOP-01.05, “Filling and Venting the RCS”
* Shutdown Cooling has been secured
* RCS temperature is 130°F
* RCS pressure is 310 psia
* Secondary side of the Steam Generator (SG) is 165°F
Based upon the given conditions, which ONE of the following results could occur if an RCP is started?
A. Excessive core uplift.
B. No adverse results should be expected.
C. An RCS pressure transient outside the LTOP system capacity.
D. Allowable brittle fracture stress limits for the SG could be exceeded.
C. An RCS pressure transient outside the LTOP system capacity.
Given the following:
* The Unit 1 Reactor Coolant System (RCS) is operating on solid pressure control
* One train of Shutdown Cooling (SDC) is in service
* BOTH LCV-2210P & Q, “Letdown Level Control Valves,” are open with their controller in MANUAL
* BOTH PCV-2201P & Q, “Letdown Pressure Control Valves,” are throttled with their controller in AUTO set at 100 psig
Which ONE of the following choices completes the statement below:
If HCV-3657, “SDC Temp Control Valve,” is throttled OPEN, what is the effect on RCS temperature AND how would the Letdown Pressure Control valves respond to maintain letdown pressure on setpoint?
RCS temperature will:
A. rise causing PCV-2201P&Q to throttle open.
B. lower causing PCV-2201P&Q to throttle closed.
C. rise causing PCV-2201P&Q to throttle closed.
D. lower causing PCV-2201P&Q to throttle open.
B. lower causing PCV-2201P&Q to throttle closed.
Given the following:
* Unit 2 is in Mode 5 on Shutdown Cooling (SDC)
* The “B” SDC train is in service
* The “A” SDC train is in standby
* The following annunciator is received:
4.16KV SWGR 2B2 Δ CURRENT TRIP A-13
Which ONE of the following describes the response of the “2B” Low Pressure Safety Injection pump?
A. Continues in operation.
B. Its control breaker opens, but can be manually closed.
C. Its control breaker opens, but recloses following a time delay.
D. Stops due to loss of AC power and its breaker cannot be reclosed.
B. Its control breaker opens, but can be manually closed.
Given the following conditions:
* Unit 1 is in MODE 4
* 1A Shutdown Cooling (SDC) loop is in service for Reactor Coolant System (RCS) cooldown
* 1B1 and 1B2 Reactor Coolant Pumps (RCP) are running
* SDC flow rate returning to the core is 3400 gpm as indicated on FI-3306
* RCS temperature is 295°F and being held constant for shift turnover
* HCV-3657 “SDC Temp Control Valve,” is open and FCV-3306 “SDC Return Flow Valve,” is closed
* 2 of the 4 LPSI header injection valves are open
* The air supply line breaks on HCV-3657
Which ONE of the following choices completes the statement below:
As a result of the loss of air, HCV-3657 will __(1)__and SDC flow rate returning to the core will __(2)___.
A.
1) close
2) lower to approximately 0 gpm
B.
1) fail as is
2) remain unchanged
C.
1) close
2) lower then return to 3400 gpm
D.
1) open
2) rise to approximately 4600 gpm
A.
1) close
2) lower to approximately 0 gpm
Unit 2 is performing a cooldown per 2-GOP-305, “Reactor Plant Cooldown - Hot
Standby To Cold Shutdown,” for a refueling outage with the following conditions:
Time: 11:30
* RCS pressure is 1750 psia
* RCS temperature is 504°F
* 2A & 2B S/Gs are 740 psia
Time: 11:32
* 2A Steam Line ruptures outside Containment and just upstream of the MSIV
* RCS pressure is 1630 psia and rapidly lowering
* SG pressures are 580 psia and rapidly lowering
Which ONE of the following states:
1) What ESFAS actuation(s) must be MANUALLY actuated?
2) Which procedure will be implemented to mitigate the event?
A.
1) BOTH MSIS, and SIAS.
2) 2-EOP-05, “ESDE”.
B.
1) ONLY SIAS.
2) 2-EOP-05, “ESDE”.
C.
1) BOTH MSIS, and SIAS.
2) 2-ONP-01.01 “Plant Condition 1 Steam Generator Heat Removal LTOP Not in Effect”.
D.
1) ONLY SIAS.
2) 2-ONP-01.01 “Plant Condition 1 Steam Generator Heat Removal LTOP Not in Effect”.
C.
1) BOTH MSIS, and SIAS.
2) 2-ONP-01.01 “Plant Condition 1 Steam Generator Heat Removal LTOP Not in Effect”.
Given the following on Unit 1:
* The unit has just completed drawing a bubble from a solid plant condition
* Quench Tank pressure was noted to be 1 psig
* Pressurizer (Pzr) is being maintained at 200 psia by cycling backup Pzr heaters
* RCS temperature is 205°F
If a PORV is venting fluid to the Quench Tank (QT), which ONE of the following would apply to both the expected PORV tailpipe temperature AND the Technical Specification Limiting Condition for Operation leakage limit for this type of leakage?
(Assume 100% quality. References provided)
A. ~310ºF; 1 gpm
B. ~310ºF; 10 gpm
C. ~380ºF; 1 gpm
D. ~380ºF; 10 gpm
B. ~310ºF; 10 gpm
Given the following on Unit 1:
* Unit 1 is operating at 100% power
* LS-14-1A (“A” side CCW Surge Tank Level Switch) on the Component Cooling Water (CCW) surge tank fails low causing the following annunciator CCW SURGE TANK LEVEL HIGH/COMPARTMENT A LEVEL LOW S-6
Which ONE of the following describes the impact on CCW operation and Reactor Coolant Pump (RCP) Cooling:
A. No Non-Essential header valves isolate, “A” and “B” CCW header supplies flow to the RCPs.
B. “A” side Non-Essential header valves auto close; “B” CCW header supplies flow to the RCPs.
C. “A” side Non-Essential header valves should be manually closed; All RCPs should be secured.
D. All four Non-Essential header valves auto close; All RCPs should be secured.
A. No Non-Essential header valves isolate, “A” and “B” CCW header supplies flow to the RCPs.
On Unit 1, which ONE of the following DIRECTLY feeds the Pressurizer PORV OPEN
signal when the PORV selector switch is in:
1) NORMAL RANGE
2) LOW RANGE
DIRECTLY from the:
A.
1) RPS high pressurizer pressure trip bistables
2) Pressurizer pressure instruments PT-1103, 1104
B.
1) Pressurizer pressure instruments PT-1102 A through D
2) Pressurizer pressure instruments PT-1102 A through D
C.
1) RPS high pressurizer pressure trip bistables
2) Pressurizer pressure instruments PT-1102 A through D
D.
1) Pressurizer pressure instruments PT-1102 A through D
2) Pressurizer pressure instruments PT-1103, 1104
A.
1) RPS high pressurizer pressure trip bistables
2) Pressurizer pressure instruments PT-1103, 1104
Given the following conditions on Unit 1:
The unit is operating at 100% power.
Reactor Protection System (RPS) Channel “A” Tcold RTD (TE-1112CA) has been inadvertently set to the MAXIMUM value of the Tcold range.
Which ONE of the following describes the effect of this adjustment on the given parameters?
Channel “A” : TM/LP Trip Setpoint / Delta-T Power Indication
A. Lowers / Lowers
B. Lowers / Raises
C. Raises / Raises
D. Raises / Lowers
D. Raises / Lowers
Given the following conditions on Unit 2:
* Unit 2 is at 18% power
* The Main Generator is on-line
* The crew is raising turbine load at 1 MW/min IAW 2-GOP-201, “Reactor Plant “Startup – Mode 2 to Mode 1”
The Main Transformer 2A Differential Current Alarm has annunciated resulting in:
* Turbine tripping on a generator lockout
Which ONE of the following describes the expected plant response and subsequent actions?
The Reactor should _________.
A. remain CRITICAL; Verify SBCS quick opens to remove reactor heat and enter 2-AOP-53.03, “Main Generator”
B. remain CRITICAL; Ensure SBCS responds in pressure control mode to remove reactor heat and enter 2-AOP-53.03, “Main Generator”
C. have automatically TRIPPED; Manually trip the reactor and enter EOP-01, “Standard Post Trip Actions”
D. have automatically TRIPPED; Manually trip the reactor then enter EOP-15, “Functional Recovery,” due to the Reactivity Control Safety Function not being met
C. have automatically TRIPPED; Manually trip the reactor and enter EOP-01,
“Standard Post Trip Actions”
Given the following conditions on Unit 2:
The crew has entered 2-EOP-03, “LOCA” with the following:
* Containment Spray Actuation Signal (CSAS) has automatically actuated
* 2-HVS-1A and 2-HVS-1C, Containment Fan Coolers, are running
* 2A Containment Spray (CS) pump running with a flow rate of 2600 gpm
* 2B CS pump failed to auto start
* Containment Pressure is 7 psig and rising
* Containment Temperature is 220°F and rising
* Hydrogen Analyzers have just been placed in service
Which ONE of the following describes the status of the Containment Temperature and Pressure Safety Function and required actions (if any) per 2-EOP-03, “LOCA?”
A. Met; based on current Containment Temperature and Pressure.
B. Not Met; but will be if the HVS-1B Containment Fan Cooler is started.
C. Not Met; but will be if the 2B CS pump is started with a flow rate of 2700 gpm.
D. Met; based on ONLY 2 Containment Fan Coolers running and the 2A CS pump at its current flow rate.
C. Not Met; but will be if the 2B CS pump is started with a flow rate of 2700 gpm.
Given the following events and conditions:
* Unit 2 is operating at 100%
* The 2C Auxiliary Feedwater (AFW) pump is out of service
Time: 0200:
* A loss of off-site power (LOOP) occurred
* The 2A Emergency Diesel Generator (EDG) automatically loaded on the bus
* The 2B EDG started but its output breaker DID NOT auto close
* 2A and 2B Steam Generator (S)G levels are 10% NR lowering
Time: 0204:
“A” train of Auxiliary Feedwater (AFW) is feeding the 2A SG
Time: 0205:
The 2B EDG output breaker was manually closed
Which ONE of the following statements correctly describes the “B” Train AFW status at Time 0206, and any subsequent actions (if any)?
The 2B AFW pump:
A. is running and feeding the 2B SG. No further action is required.
B. is running but NOT feeding the 2B SG. Open the 2B AFW flow control valves to establish the desired flow rate.
C. is NOT running. Manually initiate AFAS-2 using all 4 Manual Initiation switches on RTGB-202.
D. is NOT running. Manually start the “B” train of AFW in accordance with the operator hard card.
C. is NOT running. Manually initiate AFAS-2 using all 4 Manual Initiation switches on RTGB-202.
Given the following condition on Unit 2:
Time: 0200
* A Small Break Loss of Coolant Accident has occurred
* A loss of offsite power (LOOP) occurs
* 2A and 2B Emergency Diesel Generators start and load as expected
Time: 0220
* Safety Injection Signal Actuates (SIAS)
Which ONE of the following describes the expected condition of the Containment Fan
Coolers following the LOOP, then following the SIAS?
__(1)__ Containment Cooling Fans running in ___(2)___ speed.
0200 0220
A.
1) Three Four
2) Fast Fast
B.
1) Three Four
2) Fast Slow
C.
1) Four Four
2) Fast Fast
D.
1) Four Four
2) Fast Slow
D.
1) Four Four
2) Fast Slow