Formulas Flashcards
Schedule Variance (SV)
SV = EV - PV
Schedule Variance = Earned Value - Planned Value EV = % complete * BAC > 0 positive = ahead of schedule < 0 negative = behind schedule = 0 on schedule of project is complete
Schedule Performance Index (SPI)
SPI= EV / PV
Schedule Performance Index = Earned Value / Planned Value EV = % complete * BAC SPI < 1 : behind schedule SPI = 1 : on schedule SPI > 1: Ahead of schedule
Present value (PV)
The value today of future cash flows.
PV= FV / (1+r)n
FV = future value r= interest rate N = number of times period
Net present value (NPV)
Present value of the total benefits (income or revenue) minus the cost over many times period
If positive project is a good choice unless and even better investment opportunity exists. Project with greater NPV is selected. Bigger is better (NPV)
Internal rate of return (IRR)
The higher the IRR number the better
Payback period
Refers to the length of time it takes for the organization to recover its investment in the project before it starts accumulating profit
Less is better. Net Investment / avg. annual cash flow
Cost benefit analysis
Consorts the expected cost of the project to the potential benefits
Benefits ratio > 1 = benefits are greater than the cost
Benefits ratio < 1= cost is greater than the benefit
Economic value added
Connect with whether the project returns to the company more value than the initiative costs.
Opportunity cost
Opportunity given up by selecting one pertinent over another
Sunk costs
Sink costs are expended costs. Accounting standards say that wink costs should not be considered when deciding whether to continue with a troubled project
Law of diminishing return
After a certain point adding more input (resources) will not produce a proportional increase in productivity
Working capital
Current assets minus current liabilities for an organization. It is the amount of money the company has available to invest including investment in projects
Depreciation
Straight line - same amount of depreciation every year
Accelerated depreciation - 2 forms
- double declining balance
- sum of the years digit
PM Communication (Comm.)
90%
Communication Channels
n(n-1) / 2
n = # of stakeholders (team members), including PM