Formulas Flashcards

1
Q

Present Value (PV)

A

Present Value -

The value today of future cash flows.

PV = FV / (1 + r)n

FV = future value

r = interest rate

n = number of time periods

Example: what is present value of $300,000 received 3 years from now if we expect the interest rate to be 10%?

Answer: $225,394

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Payback / Break Even Period

A

Payback / Break Even Period -

Amount of time required to recuperate costs incurred on a project - to reach the break even point.

Exam: when choosing between two project, select the one with the fastest payback period, regardless of the investment!

Example: what is the payback period if the cost of project is $200,000 and revenue is $50,000 per year,

Answer: the payback period will be 4 years.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Internal Rate of Return (IRR) / Discount Rate

A

Internal Rate of Return (IRR) / Discount Rate -

Exam: when comparing projects always select project with the highest IRR, meaning better positive return. The durations are already part of the IRR calculations and therefore irrevelant!

The rate at which an investment will yield returns.

  • Also called discount rate that makes NPV=0.
  • Similar to bank’s interest rate.
  • Normally expressed as a percentage.
  • The higher the IRR, the more lucrative the project will be.

So when the IRR is 5%, it means that for every $100 you invest, the return on investment will be $105.

Example: Project A with a projected duration of 3 years has an IRR of 9%. Project B would take 2 years and has an IRR of 6%. Which project would you select?

Answer: Project A since it has a higher IRR, meaning better positive return. Durtion is irrevelant!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Net Present Value (NPV)

A

Net Present Value (NPV) -

The sum of PVs of the expected inflows minus the outflows (investment or cost).

Exam: always select project with highest NPV, regardless of number of years!

Higher NPV is better:

> 0 = project is lucrative

= 0 = project is neither profitable nor unfavorable

< 0 = project is unfavorable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Return on Investment (ROI) / Marginal Analysis

A

Return on Investment (ROI) -

A return ratio that compares the net benefits of a project with its total cost. Subtracts costs from benefits.

Net Benefits / Total Costs

Example: project total cost was $150,000 and is expected to bring in $350,000 (total benefit) this year.

Answer: the ROI is $200,000 / $150,000 = 1.33 = 133%

Net Benefits: $350,000-150,000 = 200,000;

Cost = 150,000.

Example: Acme widget produced widgets at total cost of $50,000 and sold them for $1,200 each, for a total revenue of $60,000.

If Acme Widget produces a 51st widget at a cost of $1,500, its total cost will be $51,500 and its total revenue will be $61,200.

Should the firm produce the 51st widget?

Answer:

First 50 widgets:

Marginal benefit = $1,200 (marginal revenue) - $1,000 (marginal cost) = $200

ROI = $200 / $1,000 = 20%

Starting with 51st widget:

Marginal benefit = $1,200 (marginal revenue) - $1,500 (marginal cost) = -300

ROI = $-300 / $1,500 = -20%!

Answer is NOPE!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Discounted Cash Flow (DCF)

A

Discounted Cash Flow (DCF) -

PV of an investment’s future cash flows.

Just take the highest number; no math involved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Lifecyle Cost (TCO)

A

Lifecycle Cost (total cost of ownership) -

Developmental Cost + Maintenance & Operational

Applies to products.

Exam: when comparing projects, select project that has LOWER lifecycle costs!

Example 1:

product development cost = $30,000

operations & maint cost = $70,000

product lifecycle cost = $100,000

Example 2:

Project A started with investment of $300,000 and has lifecycle cost of $700,000. Project B started with investment of $200,000 and has lifecycle cost of $850,000. Which project would you select?

Answer:

Project A = $300,000 + $700,000 = $1,000,000

Project B = $200,000 + $850,000 = $1,050,000

Select Project A because it has lower lifecycle cost, regardless of the investment!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Opportunity Cost

A

Opportunity Cost -

Economic value of the next best alternative forgone or given up

Example: PMTI had 3 project opportunities. PMTI chose a $4M project over a $2M project and $3M projects. PMTI’s opportunity cost was $3M.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Depreciation

A

Depreciation -

A decline in value of property

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Benefit-Cost Ratio (BCR)

A

Benefit-Cost Ratio (BCR) -

Benefit / Cost

Exam: when comparing multiple projects, select the one with the highest BCR regardless of the investment!

Compares revenue (benefit) of project to its cost.

If ratio is > 1, project is profitable.

If ratio is = 1, project will break even.

If ratio is < 1, costs are higher than benefit

Example: benefits = $350,000; costs = $150,000

Answer: 2.33

Example:

Project Investment BCR Ratio

Project A $200,000 8 : 4

Project B $700,000 5 : 3

Project C $1,000,000 5 : 2

Answer:

Project C.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Scoring Models

A

Scoring Models -

Point based system using known facts to predict future outcomes. Used to examine “project worthiness” and compare it to other projects.

Weights are assigned to factors to calculate weighted average project score.

Example (see screenshot)

Answer:

Project A since it has the highest score

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Future Value (FV)

A

Future Value -

The value today of future cash flows.

FV = PV / (1 + r)n

To do this math, you need to use PV in the numerator, which is the missing element. Then do algebra to multiply the denominator by FV.

FV = future value

PV = present value

r = interest rate

n = number of time periods

Example: A project manager wants to invest money into a project. What is the future value after 2 years if the present value is $100,000 and the rate of return is 5%?

Answer:

Present value = future value / (1 + interest rate)n

$100,000 = future value / (1 + .05)2

Then do the algebra thing (multiply denominator by PV)

Future value = $110,250

How well did you know this?
1
Not at all
2
3
4
5
Perfectly