Field Delay / Scope Changes Flashcards

1
Q

Delays and scope changes identified in the field are ______.

A

Very common on almost every project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The handling of these changes can be ________.

A

The deciding factor on whether Company can successfully make a claim on the delays or changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

There are many reasons that delays ______.

A

are experienced in the field.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The delays of concern are the ones that are ________.

A

beyond the control of the company and its employees and are the responsibility of our client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Examples of delays are _____.

A

Customer-driven shutdowns from lighting or weather, permitting, operational upsets, other contractors’ interferences, truck receipts at a loading rack, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When encoutering field delays, ______.

A

document them immediately and present them to the client for confirmation and signature.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Time is of the essence when ________.

A

Notifying clients.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Many contracts state that notification is required ________.

A

within a certain amount of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The notification of the delay can be done on a ______.

A

daily T&M timesheet.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Be sure to assure the client that this is our _______.

A

Process and documenting a delay is a requirement of theirs (per their contract.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

All concerns or questions about documenting delays from customer can be directed to ______.

A

Company PM or office personnel.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Repair work is often affected by changes in scope due to _______.

A

unforeseen discovery work that adds to, or sometimes reduces, the anticipated obstacles to complete the required repairs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

In the case of changes of scope, the client should be told to send the requested changes to the company PM by the company site supervisor for _______.

A

initiation of a change order when originating from a client request.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When it is discovery work change, the required change should be communicated to the company PM by field supervision so that _______.

A

approval can be obtained prior to executing the changes in the scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

It is mandatory that field supervision have approval and direction from PM before ______.

A

executing any changes to original scope of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Drawings and materials may be required prior to ______.

A

being able to complete the scope changes.

17
Q

At any time, if you are unsure how to handle delays or changes, feel free to ______.

A

reach out to your PM or directly to R&M director for guidance.

18
Q

Often, customers will disagree that the issue is a _______.

A

scope change, delay, or other.

19
Q

Customers may even refuse to ________.

A

signed the provided T&M sheets documenting delays/changes of scope.

20
Q

The company is not saying that by signing it is a “scope change or delay”, it is ________.

A

documenting that the work was done, and the hours are accurate.

21
Q

The PM will argue the merits of the scope with the customer, but we want to _______.

A

ensure the time is captured in the event.

22
Q

If the customer refuses to sign the T&M timesheets, then the company site supervisor is to ______.

A

sign, date and note the time it was presented to the customer and the customer’s name of whom it was presented to.

23
Q

When documenting a delay/change of scope, please ______.

A

print all info legibly, sign your name, and print your name.