Fault Protection and Inspection Flashcards
Short duration overloads should operate a circuit breaker immediately - True or False?
False
A protective device operates quickly to limit the let-through energy before damage occurs, in response to what condition?
Short circuit
Short Circuit Current is a product of the Full Load Current and what?
100 / % impedance of transformer
Full Load Current is determined by the transformer KVA rating x 1000, divided by what?
root3 x V(line)
Total prospective fault current per phase is determined by the phase of supply, divided by what?
Fault per phase (Z1) and impedance of consumer mains (Z2)
Supply phase impedance is determined by dividing the phase voltage by what?
Calculated short circuit current.
Consumer mains impedance is determined how?
Table 35 of the AS/NZS 3008, then:
L x Rc x 2 / 1000
Disconnection time for a protective device on a final subcircuit with socket outlets is to be maximum ___.
0.4 seconds
What two conditions must be met in order to use SELV and PELV to provide basic and fault protection?
1 - Nominal voltage not to exceed 50 VAC or 120 VDC (ripple free) and source of supply not to exceed these values.
2 - Circuits to be electrically isolated from each other and from circuits of higher voltages.
Before commencing the _____ of an electrical installation, you must consider the nature of the current, nature of conductors, and voltage tolerances.
Design
What setting on a megger is used to test insulation resistance on a low voltage transformer test?
500V
What should ensured to be disconnected before performing an insulation resistance test?
Any electronics.
What does Out Of Range indicate during a continuity test on a transformer?
Open circuit in the winding.
What instrument is used to perform a continuity test?
Ohmmeter
What type of contact switch is used on a current transformer (CT) to avoid a voltage spike in the windings, and why?
Make-before-break.
Ensures transformer is not open-circuited while equipment is connected or disconnected.