FastTrack Schedule (39) Flashcards
This set entered on 11-21-14
- 10.14.4 Tutorial 9
- What are ASSIGNMENTS?
Assignments link a resource and ALL its data to a task or tasks in the schedule.
- The SCHEDULE VIEW and the RESOURCE VIEW draw from two different pools of information. Assignments act as:
a BRIDGE between those two pools of information
- You can create a schedule full of tasks and numerous resources, but they will not interact until:
you ASSIGN A RESOURCE TO A TASK.
- How many sub rows in each row of the Resource View?
Three:
a. The Percent Work Usage
b. The Allocated Time Usage
c. The Assignments Sub row
- What does the PERCENTAGE USAGE Sub row display?
a graph representing a resource’s currently allocated time AS A PERCENTAGE of the OVERALL available time for that resource.
- What does the ALLOCATED TIME USAGE sub row display?
a graph representing a resource’s currently allocated time in RESPECT TO THE WORK UNITS. The name of this row changes to match the Work Units YOU HAVE SET in the Document Preferences dialog.
- What does the ASSIGNMENTS sub row display?
the activity bar or bars to which a resource is assigned. ASSIGNMENT BARS display just as they do IN SCHEDULE VIEW. LINKS, HOWEVER, DO NOT DISPLAY.