FastTrack Schedule (39) Flashcards

1
Q

This set entered on 11-21-14

  1. 10.14.4 Tutorial 9
  2. What are ASSIGNMENTS?
A

Assignments link a resource and ALL its data to a task or tasks in the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. The SCHEDULE VIEW and the RESOURCE VIEW draw from two different pools of information. Assignments act as:
A

a BRIDGE between those two pools of information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. You can create a schedule full of tasks and numerous resources, but they will not interact until:
A

you ASSIGN A RESOURCE TO A TASK.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. How many sub rows in each row of the Resource View?
A

Three:

a. The Percent Work Usage
b. The Allocated Time Usage
c. The Assignments Sub row

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. What does the PERCENTAGE USAGE Sub row display?
A

a graph representing a resource’s currently allocated time AS A PERCENTAGE of the OVERALL available time for that resource.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. What does the ALLOCATED TIME USAGE sub row display?
A

a graph representing a resource’s currently allocated time in RESPECT TO THE WORK UNITS. The name of this row changes to match the Work Units YOU HAVE SET in the Document Preferences dialog.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. What does the ASSIGNMENTS sub row display?
A

the activity bar or bars to which a resource is assigned. ASSIGNMENT BARS display just as they do IN SCHEDULE VIEW. LINKS, HOWEVER, DO NOT DISPLAY.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly