FastTrack Schedule (34) Flashcards

1
Q

This set entered on 11-10-14 11-9-14-1 Section 9.2, DEFINING A WORK CALENDAR. 1. How many types of calendars are there?

A

a. Project Calendar
b. Activity Calendar
c. Resource Calendar.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. How many calendars does a project have?
A

A project is assigned just one calendar, but any ACTIVITY CAN BE ASSIGNED A SEPARATE CALENDAR, and EVERY RESOURCE HAS ITS OWN WORK CALENDAR.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. What are the four key elements of the work calendar?
A

a. Base Work Days
b. The [Selected] Calendar
c. Typical Days
d. Specific Days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. What is a BASE WORK DAY?
A

It determines how durations of work are calculated. THIS IS ONLY USED IN CALCULATIONS. You set this number in the Project tab of the DOCUMENT PREFERENCES DIALOG.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. What is the [Selected Calendar]?
A

It determines the calendar you ASSING TO A PROJECT, ACTIVITY, or RESOURCE and from which you may build a CUSTOM calendar.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. What is a Typical Week Day Calendar?
A

It allows you to set up a work schedule in which each day of the week might have different hours such as a Monday night differing from other days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly