FastTrack Schedule (32) Flashcards

1
Q

This set entered on 11-9-14. 6.12.14.1 UNDERSTANDING LEAD AND LAG TIME 1. What is LAG?

A

Lag: A unit of duration used as a delay between two tasks. Lag durations are entered as positive values. An example of this could be the predecessor task of pouring concrete prior to the successor task of building a house. If the concrete takes 2 days to cure and dry, the dependency link would require a lag of 2 days.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. What is LEAD?
A

Lead: A unit of duration used to provide an overlap, or “head-start”, between two linked tasks. Lead durations are entered as negative values. Drywall on first floor can start while framing is still going on on the second floor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. How do you set LAG/LEAD TIME?
A

INFORMATION FORM: BARS: LINKS: LAG/LEAD and make your choices.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. How do you LINK bars in CALENDAR VIEW?
A

YOU CANNOT. Bars can ONLY BE LINKED IN SCHEDULE VIEW.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. Linking ACTIVITY BARS creates:
A

a DEPENDENCY from a point on one bar the PREDECESSOR) to a point on a second bar (the SUCCESSOR).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. This “DEPENDENCY” illustrates:
A

the RELATIONSHIP that the DATES ON ONE TASK HAVE TO ANOTHER.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Example of a FINISH TO START Relationship:
A

Drywall cannot start until MECHANICAL ROUGH is complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. How do you LINK bars?
A

TOOLS controls: BAR LINK tool. Click the FINISH or START of one bar and DRAG to the START or FINISH of a second bar. A second option is to use the INFORMATION FORM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly