This card set entered on 11-9-14. 6.10.14.1 DISPLAYING SCHEDULED, REVISED, AND ACTUAL BARS. 1. How do you EDIT the LOOK of an ACTIVITY BAR?
BAR STYLE drop down list, choose DEFINE and make your choices.
- There are several ways to display a REVISED BAR. What are they?
a. SHOW REVISED AS BAR b. SHOW REVISED AS POINTS c. ALWAYS SHOW REVISED d. SHOW REVISED ONLY IF DIFFERENT THAN SCHEDULE.
- What is RESET ACTUAL?
TOOLS menu; RESET ACTUAL. If you wish to return the activity to 0% percent complete, Reset Actual does this automatically. Remember that unless you have explicitly changed them, the Revised dates are the same as the Scheduled dates.
- What is RESETTING ACTUAL DATES?
Within Scheduled, Revised, and Actual progress tracking, resetting the Actual date returns the selected bar’s Actual dates to the Revised dates. For instance, you could have changed the Actual dates of an activity by defining a % complete.
- What is RESETTING REVISED DATES?
Within Scheduled, Revised, and Actual progress tracking, resetting the Revised date sets the selected bar’s Revised dates to match the original Scheduled dates. For instance, you could have changed the Revised dates of an activity, slipping it later. If those revisions no longer apply, you want to return the Revised dates back to their original Scheduled dates.
- How do you RESET A REVISED DATE?
TOOLS menu: PROGRESS TRACKING: RESET REVISED.
- Applying Reset Revised to a bar resets the Actual and Revised dates and times to
the Scheduled dates and times. The % complete is returned to zero.
This card set entered on_____ 6.10.14.1 DISPLAYING SCHEDULED, REVISED, AND ACTUAL BARS. 1. How do you EDIT the LOOK of an ACTIVITY BAR?
BAR STYLE drop down list, choose DEFINE and make your choices.
- There are several ways to display a REVISED BAR. What are they?
a. SHOW REVISED AS BAR b. SHOW REVISED AS POINTS c. ALWAYS SHOW REVISED d. SHOW REVISED ONLY IF DIFFERENT THAN SCHEDULE.
- What is RESET ACTUAL?
TOOLS menu; RESET ACTUAL. If you wish to return the activity to 0% percent complete, Reset Actual does this automatically. Remember that unless you have explicitly changed them, the Revised dates are the same as the Scheduled dates.
- What is RESETTING ACTUAL DATES?
Within Scheduled, Revised, and Actual progress tracking, resetting the Actual date returns the selected bar’s Actual dates to the Revised dates. For instance, you could have changed the Actual dates of an activity by defining a % complete.
- What is RESETTING REVISED DATES?
Within Scheduled, Revised, and Actual progress tracking, resetting the Revised date sets the selected bar’s Revised dates to match the original Scheduled dates. For instance, you could have changed the Revised dates of an activity, slipping it later. If those revisions no longer apply, you want to return the Revised dates back to their original Scheduled dates.
- How do you RESET A REVISED DATE?
TOOLS menu: PROGRESS TRACKING: RESET REVISED.
- Applying Reset Revised to a bar resets the Actual and Revised dates and times to
the Scheduled dates and times. The % complete is returned to zero.