FastTrack Schedule (27) Flashcards

1
Q

This set entered on 6-8-14
6.8.14.3
UNDERSTANDING CONSTRAINTS.
1. What are CONSTRAINTS?

A

They are the parameters you can assign to activities to control the behavior of bars as your project changes. Constraints in FastTrack Schedule are based on the CPM (Critical Path Method) project management model and follow the CPM standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. What is a SOFT CONSTRAINT?
A

it will allow activities in your schedule to begin and end within an elastic window of time, until the activity’s start or finish comes into conflict with another dependency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. What is a MODERATE CONSTRAINT?
A

it will not allow activities in your schedule to begin and end before or after the date or time you have specified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. What is a HARD CONSTRAINT?
A

it will not allow activities in your schedule to begin or end on any date or time except those which you specified. A hard constraint effectively locks your bar finish or start and, if the bar is linked, bypasses the defined dependency if that dependency conflicts with its specified start or finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. AS SOON AS POSSIBLE constraint is:
A

SOFT. The activity is scheduled to begin at the earliest possible moment, taking into account other scheduled activities. There is no specified Constraint Date, however the Project Start Date often acts as the Constraint Date. This is the default constraint type when bars are created by entering the Duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. AS LATE AS POSSIBLE
A

SOFT. The activity is scheduled to begin at the latest possible moment, taking into account other scheduled activities. There is no specified Constraint Date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. START ON OR AFTER
A

MODERATE. The activity is scheduled to begin no earlier than on the Constraint Date you specify. If necessary, it may begin later. This is the default constraint for new activities that are entered by drawing bars.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. START ON OR BEFORE
A

MODERATE. The activity is scheduled to begin no later than on the Constraint Date you specify. If necessary, it may begin earlier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. FINISH ON OR AFTER
A

MODERATE. The activity is scheduled to end no earlier than on the Constraint Date you specify. If necessary, it may end later.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. FINISH ON OR BEFORE
A

MODERATE. The activity is scheduled to end no later than on the Constraint Date you specify. If necessary, it may end earlier.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. MUST START ON
A

HARD. The activity will only begin on the specified Constraint Date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. MUST FINISH ON
A

HARD. The activity will only end on the specified Constraint Date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly