Exam 2 Flashcards
1
Q
RCP
- Flowrate, Motor HP, Power Supply
- Flywheel purpose
- Anti-rotation device purpose. When does it actuate?
- CCW Cooling - What does it cool? CIS valves - what closes them?
- Excess flow values & setpoints
- Interlocks
A
- 100,200 gpm @ 290 ft of head each, 7000 HP Motor - P/S A-3 PA0107, 0108, 0205, 0204
- Adds inertia to shaft to allow longer coastdown time for Decay Heat Removal. Takes ~4 minutes for pump to coastdown.
- Prevents idle RCP from water wheeling. 70 RPM
- CCW: Cools Thermal Barrier H/X, motor bearings, and motor air coolers.
- CIS: Inlets: EG-HV-71,68 (outer); EG-HV-60,59 (In/Out); EG-HV-62/61 (In/Out). Closed on CIS-B (Hi-3 or manual CSAS)
- Excess flow: If FT-13 thru 16 sense > 50 gpm BB-HV-13 thru 16 will individually close. If FT-62 senses > 206 gpm EG-HV-62 will close isolating all Thermal Barrier H/X’s.
- Will not start unless: Lift oil pump running and oil pressure > 600#
2
Q
PRT (OTN-BB-00004)
- PRT level restriction prior to degas
- Hydrogen precautions
- Concern for leakage when RCS pressure < PRT pressure
- Concern for draining PRT to CTMT Normal Sumps
- Time to cooldown PRT
A
- PRT Level > 19% until degassed to prevent PRT atmosphere from going into RCS.
- H2 Precautions:
- Maintain N2 blanket to prevnt H2/02 explosive environment.
- [H2] shall be < 4% prior to venting PRT to atmosphere.
- PRT [O2] content must be < 3% prior to putting H2 on VCT.
- If Rx makeup water pressure > RCS pressure, water may leak into RCS via excess letdown line.
- If draining PRT to containment normal sumps, sump pumps cannot keep up and should only be done in emergency w/o verifying [H2] < 4%.
- PRT Cooling: 1 hr by spraying makeup water, 8 hours by circulating w/ RCDT H/X.
3
Q
RVLIS
- RVLIS inputs & purpose
A
- RVLIS - Indicates Rx Vessel level based on D/P between Rx Vessel head & seal table. Adjusted for density based on TH.
4
Q
COMS
- Purpose
- Controls
- Inputs
A
- Mitigates an overpressure at low temperature.
- COMS must be ARMED
- Block valve opens when in ARM (cannot be closed unless COMS is blocked)
- Auctioneered Low WR Temperature used to calculate Pmax & compared to channels WR Pressure. It’s used to actuate PORVs.
5
Q
Rod Banks & Groups/Speeds
A
Control Banks (25 Total)
- A: 4 (2/2) - 1 AC / 2 AC
- B: 8 (4/4) - 1 BD / 2 BD
- C: 8 (4/4) - 1 AC / 2 AC
- D: 5 (2/3) - 1 BD / 2 BD
Shutdown Banks (28 Total)
- A: 8 (4/4) - 1 AC / 2 AC
- B: 8 (4/4) - 1 BD / 2 BD
- C: 4 (one group) - SCDE
- D: 4 (one group) - SCDE
- E: 4 (one group) - SCDE
Speed
- Shutdown Banks: 64 SPM
- Control Banks:
- Manual: 48 SPM
- Auto:
- -1.5° to -3°: 8 SPM
- -4°: 40 SPM
- -5°: 72 SPM
6
Q
RCS Inventory Balance (OSP-BB-00009)
- Frequency
- Acceptance Criteria
- Basic Steps
A
- Every 72 hours for 1 hour minmum.
- Acceptance:
- Unidentified Leakage < 1 gpm
- Identified Leakage < 10 gpm
- Primary to Secondary Leakge < 150 gpd per S/G.
- Steps:
- Tave controlled within 1°F
- Pressure stable ± 15 psig
- Dilutions and borations avoided during test
7
Q
RCS WR Temperature
- Number
- Range
- What they provide inputs to.
A
- 1 TH & 1 TC per loop.
- 0° - 700°F
- Input to:
- COMS
- RVLIS
- Subcooling Monitor
- MCB Indication/Recorders
8
Q
Power/Logic Cabinet Urgent Alarms
A
Power Cabinet (Low Low RPM)
- Loose or missing card
-
Logic error
- Zero current ordered to both Stationary and Movable gripper coils @ same time
-
Regulation Failure
- Sampling resistor current not expected
-
Phase Failure
- SCR Bridge not operating properly.
-
Multiplex error
- More than 1 group of rods in 1 power cabinet try to move at once.
- Power cabinet non-urgent occurs when one instrumentation power supply fails. If caused by main power supply, attempted rod motion will cause urgent.
Logic Cabinet (LIPS)
- Loose or missing card
- Input to slave cycler incorrect
- Pulser failure
- Shutdown Bank C,D,E circuit failure.
- Logic Cabinet urgent failure prevents all auto and manual rod motion.
Urgent Failures:
- Failure alarm locks selected group, energizing both SGC & MGCs.
- “Inhibit signal prevents all rod motion from that cabinet.
- Rx Trip causes regulation and logic errors.
9
Q
Shutdown Bank Withdrawal (OTG-ZZ-0001A)
- Precautions
- Prerequisites
A
Precautions
- Avoid activities that could cause distractions in MCR.
- SR NIs operable per T/S 3.3.1
- Reactivity Management SRO must be designated.
- If counts ↑ x4 withdrawal suspended and rods inserted.
- If critical is acheived befroe S/D banks withdrawn enter OTO-ZZ-00003 for loss of SDM & initiate immediate boration.
Prerequisites
- CRS Permission
- Ensure 2 SR NIs operable
- If following refuel, request engineering for ICRR Plot Support
- Designate Reactivity Management SRO.
- Ensure reactivity management brief has been completed.
10
Q
Rod Control Logic Cabinet Components
- Purpose of:
- Pulser
- Master Cycler
- Bank Overlap Unit
- Slave Cyclers
- Bank Overlap Thumbwheels
A
- Pulser supplies output pulses to master cycler. (# of output pulses is 6x # of input pulses)
- Master Cycler is a reversible counter that correctly sequence the groups within the rod banks.
- Bank Overlap Unit is a counter that keeps a record of control bank operation, and determines the proper sequence of bank operation for the overlap scheme.
- Slave Cyclers generate the required sequence of current orders to the CRDM coils for rod motion.
Bank Overlap Thumbwheels:
- S1: 115
- A: 115
- B: 0
- S2: 228
- A: 228
- B: 113
- S3: 230
- B: 115
- C: 0
- S4: 343
- B: 228
- C: 113
- S5: 345
- C: 115
- D: 0
- S6: 458
- C: 228
- D: 113
11
Q
MCB Startup Reset Switch
A
-
Resets [POSSUM]:
- Pulse to Analog Converter to 0
- Bank Overlap unit to 0
- MCB Step Counters to 0
- Slave Cycler
- Urgent Alarm Circuits
- Master Cycler
12
Q
PZR Spray Valves
- Setpoints
- Flowrate and basis
- Bypass valves
- Connection to RCS Loops
- RCP Requirements
A
-
Setpoints
- Start Opening: Controller setting + 25 psig (2260 psig nominal)
- Full Open: Controller setting + 75 psig (2310 psig nominal)
-
Flow Rate:
- 450 gpm each.
- Sized to prevent PORV actuation on 10% setp load change.
-
Bypasses:
- Manual valve allows 0.5 gpm thru spray outlet for chemical mixing (boron) and limits thermal stress.
- Connection to RCS Loops: PCV-455 B ← Loop 1 TC; PCV-455C ← Loop 2 TC
-
RCP Requirements:
- Loop 1 or 2 RCP must be running to drive flow (D/P between spray line and surge line in Loop 4)
- Most effective if loop 4 RCP is running (due to lower static pressure in Loop 4 hot leg/surge line w/ RCP running)
13
Q
PZR (code) Safety Valves
- Number
- Setpoint
- Flowrate
- Basis
A
- Number: 3
- Setpoint: 2460 ± 49 psig
- Flowrate: 420,000 gpm each
- Basis: Prevents exceeding design pressure following 100% load loss to turbine with no dumps or rods.
14
Q
RCP Seals
- For each seal: How it works, flowrates & Leakoff Paths
- # 1 Seal ΔP limitation
- Standpipe makeup
A
-
Seal #1:
- Controlled leakage seal.
- Leakage controlled by ensuring gap b/w seal ring and runner is held constant by balancing hyrostatic forces.
- Seal injection from CVCS flows into space b/w #1 seal & bearing @ 8 gpm.
- 3 gpm flows past #1 seal (5 gpm into RCS) and into the VCT (per pump).
- DO NOT EXCEED 200 psid across the seal.
- Controlled leakage seal.
-
Seal #2:
- Face rubbing seal.
- Backpressure from #2 seal forces flow into VCT.
- On loss of injection becomes film riding.
- Allows 3 gph to RCDT.
-
Seal #3:
- Face rubbing w/ double dam.
- Backpressure from #3 seal forces water to RCDT.
- Standpipe leaks 400 cc/hr to RCDT and another 400 cc/hr to CTMT Normal Sump
-
Standpipe Makeup:
- __BB-LCV-178 thru 181 auto makeup from RMWST to maintain 26.6” - 41.5”.
- Can be manually controlled at RL021.
15
Q
PZR PORVs
- Lift setpoint & minimum system pressure
- How they operate
- Solenoid power supply & PORV designators
- Flow rate
- Block valve power supplies & designators
A
-
Lift Setpoint:
- 2335 psig (nominal)
- Variable for COMS.
- Minimum 125 psig system pressure to operate
- Reseats 2315 psig.
- 2335 psig (nominal)
-
How:
- Solenoid opens → Opens pilot → system pressure opens main valve
-
Designators/Power Supply:
- BB-PCV-455A (‘A’ Train): NK51
- BB-PCV-456A (‘B’ Train): NK44
- Flowrate: 210,000 gpm each
-
Block Valve Designators/Power Supplies:
- BB-HV-8000A (‘A Train): NG01B
- BB-HV-8000B (‘B’ Train): NG02B