Estimating Flashcards

1
Q

Affinity grouping

A

Affinity grouping involves classifying items into similar categories or collections on the basis of their likeness. Common affinity groupings include T-shirt sizing and Fibonacci numbers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Analogous estimating

A

Analogous estimating assesses the duration or cost of an activity or a project using historical data from a similar activity or project. Possibly least accurate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Function point

A

A function point is an estimate of the amount of business functionality in an information system. Function points are used to calculate a functional size measurement (FSM) of a software system. It is based on the number of user inputs, outputs, and data interactions in the system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Bottom-Up Estimating

A

A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS.
Possibly most accurate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Multipoint estimating

A

Multipoint estimating assesses cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Parametric estimating

A

Parametric estimating uses an algorithm to calculate cost or duration based on historical data and project parameters.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Relative estimating

A

Relative estimating is used to create estimates that are derived from performing a comparison against a similar body of work, taking effort, complexity, and uncertainty into consideration. Relative estimating is not necessarily based on absolute units of cost or time. Story points are a common unitless measure used in relative estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Single-point estimating

A

Single-point estimating involves using data to calculate a single value that reflects a best-guess estimate. A single-point estimate is opposed to a range estimate, which includes the best- and worst-case scenario.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Story point estimating

A

Story point estimating involves project team members assigning abstract, but relative, points of effort required to implement a user story. It tells the project team about the difficulty of the story considering the complexity, risks, and effort involved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Wideband Delphi

A

Wideband Delphi is a variation of the Delphi estimating method where subject matter experts complete multiple rounds of producing estimates individually, with a project team discussion after each round, until a consensus is achieved. For Wideband Delphi, those who created the highest and lowest estimates explain their rationale, following which everyone reestimates. The process repeats until convergence is achieved.
Planning poker is a variation of Wideband Delphi.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly