Equipment Foundations Flashcards
The two most common types of foundations used in substations and switchyards are drilled shafts and ? .
Slabs on grade
If the soil is wet or sandy, ? are often used to prevent a cave in before and during the pour.
caissons
The specification that covers zinc coatings applied by the hot-dip process to steel hardware is the ? standard.
ASTM A153
A substation control house will typically have a ? foundation.
slab on grade
A cost-effective foundation requiring less excavation and backfilling, and little or no forming, is the ? type.
auger drilled pier
If a casing is used when pouring a foundation, it is not removed until the concrete has set for 24 to 48 hours.
False
The collection pits installed around oil-filled substation equipment are a requirement of the ? .
EPA
Reinforcing steel (rebar) comes in ? .
Grade 40, 50, and 60
After adding the mixing water, concrete should be poured within ? . Concrete that has begun to set should be rejected.
1 1/2 hrs
The soil underneath a slab on grade should be thoroughly mixed and compacted to ? of the density of undisturbed soil.
95%
It is acceptable for a slab on grade to be poured on top of site stone.
False
The steel used to manufacture rebar can be billet-steel, rail-steel, or ? .
axel-steel
The reason rebar is normally placed in the shape of a grid is so that it can counter the stresses applied to the concrete in only a downward direction.
False
After completion of the concrete pour and vibration, the next step is to ? .
re-check the anchor bolts for location and alignment
A properly built transformer or oil switch foundation must be capable of withstanding compression and ? loads.
overturning