Equipment Foundations Flashcards

1
Q

The two most common types of foundations used in substations and switchyards are drilled shafts and ? .

A

Slabs on grade

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If the soil is wet or sandy, ? are often used to prevent a cave in before and during the pour.

A

caissons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The specification that covers zinc coatings applied by the hot-dip process to steel hardware is the ? standard.

A

ASTM A153

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A substation control house will typically have a ? foundation.

A

slab on grade

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A cost-effective foundation requiring less excavation and backfilling, and little or no forming, is the ? type.

A

auger drilled pier

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If a casing is used when pouring a foundation, it is not removed until the concrete has set for 24 to 48 hours.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The collection pits installed around oil-filled substation equipment are a requirement of the ? .

A

EPA

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Reinforcing steel (rebar) comes in ? .

A

Grade 40, 50, and 60

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

After adding the mixing water, concrete should be poured within ? . Concrete that has begun to set should be rejected.

A

1 1/2 hrs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The soil underneath a slab on grade should be thoroughly mixed and compacted to ? of the density of undisturbed soil.

A

95%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

It is acceptable for a slab on grade to be poured on top of site stone.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The steel used to manufacture rebar can be billet-steel, rail-steel, or ? .

A

axel-steel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The reason rebar is normally placed in the shape of a grid is so that it can counter the stresses applied to the concrete in only a downward direction.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

After completion of the concrete pour and vibration, the next step is to ? .

A

re-check the anchor bolts for location and alignment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A properly built transformer or oil switch foundation must be capable of withstanding compression and ? loads.

A

overturning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When hydraulic jacks are used to raise and level the main power transformer on a slab, point loads or ? loads are generated.

A

compression

17
Q

If water cannot be removed or if the concrete is to be dropped vertically more than six feet, the use of a ? may be implemented. This is the preferred method of pouring a drilled pier.

A

tremie pipe

18
Q

The use of ? conduit or hardware in a concrete foundation must be avoided.

A

aluminum

19
Q

If a foundation anchor bolt is too short, it is acceptable to weld an extension on it.

A

False

20
Q

Templates are used to accurately locate anchor bolts. The acceptable positioning tolerance is within ? .

A

1/16”