Element 1 Contractors (CDM) Flashcards

1
Q

Clients and contractors

A

Shared responsibilities for H and S.
Contractors possibly at greater risk due to:
Unfamiliarity with clients site, rules and procedures, lack of training, poor supervision, high risk activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Contract Types

Construction work falls under Construction (Design and Management) Regs 2015

A

Labour only - where an agency provides staff to work under employers direct control they should be treated as an employee.
Fixed Price Contract -
Separate Site - if completely separated contractor is responsible for H and S. Client may still have responsibilities e.g. noise, access and egress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CDM Requires

A

Realistic project programme
Early appointment of duty holders
Sufficient info, training, supervision to enable duty holders to secure H and S
Early identification and reduction of risks
Cooperation between duty holders and coordination of work
Consulting with and engaging with workers
H and S proportionate to risk and complexity of project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

All projects must have

A

Workers with right skills, training etc
Contractors providing apt supervision, instruction, info
Written construction phase plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Projects with more than 1 contractor must have

A

Principal designer and contractor must be appointed

Health and safety file

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Projects lasting longer than 30 days AND more than 20 workers OR exceed 500 person days

A

Client must notify project to the HSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

CDM allocates specific duties to 7 parties

A
Clients
Domestic Clients
Designers
Principal Designers
Principal Contractors
Contractors
Workers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Clients

A

Make arrangements for managing project

Welfare facilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Domestic Clients

A

duties normally transferred to contractor, principal contractor or principal designer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Designers

A

prepare or modify designs ensuring risks eliminated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Principal Designers

A

Plan, manage and coordinate H and S in pre-construction phase.
Provide info to principal contractor to help them plan, manage etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Principal Contractors

A

Plan, manage and coordinate H and S in construction phase.

Construction phase plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Contractors

A

Plan, manage and monitor work under their control

Coordinate with other contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Workers

A

Take care of own H and S
Cooperate with employer, contractor etc
Report anything untoward
Be consulted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Construction Phase Plan outlines

A

H and S arrangements
Site rules
Specific measures concerning work involving particular risks as listed in Schedule 3 of CDM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Schedule 3 particular risks

A
workers at risk of
Burial under earth, falling from height
Chemical or biological substances
Ionising radiation
high voltage lines
Drowning
Wells, underground, tunnels
divers with air supply
working with comp air atmosphere
explosives
assembly or dismantling of heavy prefab components
17
Q

Health and Safety File

A

File appropriate to characteristics of the project, containing relevant H and S info to be taken into account during any subsequent project. Only required for projects with more than one contractor.

18
Q

Health and Safety file features

A

a. Description of the work carried out
b. Any hazards not eliminated through the design and construction process e.g. asbestos
c. Key structural principles e.g. sources of stored energy, safe working loads for floors
d. Hazardous materials used e.g. lead paints
e. Info regarding removal or dismantling of plant and equipment
f. H and S info about equipment provided for cleaning and maintenance
g. The nature, location and markings of significant services
h. Info about building, plant and equipment e.g. safe access to and from service voids and fire doors.

19
Q

5 step approach how to manage contractors and ensure safe working

A
  1. Planning
  2. Choose contractor
  3. Contractors working on site
  4. Keeping a Check
  5. Review
20
Q
  1. Planning
A

Define the job
Risk Assess, the client and contractor
Specify conditions - contractors made aware of expected standards of performance

21
Q
  1. Choosing a Contractor
A

Availability, cost, competence, reliability, H and S.

References, membership of professional body etc

22
Q
  1. Contractors working on Site
A

Manage movement of contractors. Sign in controls, PTWs
All technical and managment controls in place before allowing work to start.
Induction, Instruction, Training
Cooperation and coordination
Consultation
Management

23
Q
  1. Monitoring the Contract
A

Monitor H and S performance

24
Q
  1. Reviewing the work
A

Client and contractor should review to look for future improvements