Discounted Cash Flows Flashcards
Net Present Value
present value of expected cash inflows associated with the project less the present value of the projects expected outflows, discounted at the appropriate cost of capital.
Procedure to compute NPV
- indentify all inflow and outflow
- determine approp discount rate
- use discount rate, find PV of each cash flow. inflows (+) increase NPV outflows (-) decrease NPV
- compute NPV, sum the DCFs
Internal Rate of Return
rate of return that equates the PV of an investments expected benefits (inflows) with the PV of its costs (outflows). - defined as the discount rate which the NPV of an investment is zero.
NPV Decision Rule
if project has + NPV, this amount goes to shareholders
- Accept projects with + NPV
- Reject projects with - NPV
- Two projects mutually exclusive, higher NPV accepted
IRR Analysis
Accept project with IRR greater than firms required rate of return
-Reject projects with an IRR that is less than the firms required rate of return
Hurdle Rate
rate that a projects IRR must exceed for the project to be accepted.
Opportunity Cost = IRR
NPV = 0
Opportunity Cost < IRR
NPV > 0
Why should we accept projects with a positive NPV?
Positive NPV projects will increase shareholder wealth.
IRR Rule
NPV Rule
Interpret NPV
When NPV > 0, the investment adds value because it covers the opportunity cost of capital needed to undertake it.
Positive NPV increases shareholder wealth.
Problems with IRR rule
IRR and NPV rules give the same accept/reject decision when projects are independent, but rankings may not be the same when
- project sizes differ
- timing of cash flows differ.
=> Use NPV to rank projects.
IRR will have multiple solutions when CF signs change more than once.
The IRR decision rule says:
Accept projects with an IRR that is greater than the firm’s required rate of return; Reject projects with an IRR that is less than the firm’s required rate of return.
The IRR is defined as the rate of return that equates the PV of an investment’s expected benefits with the PV of its costs…
OK
Any discount rate less than the IRR will result in a positive or negative NPV?
Positive NPV
When given NPV vs. IRR, which should you use?
You should always use the project with the greatest NPV when the IRR and NPV rules provide conflicting decisions. This is because shareholder wealth maximization is the ultimate goal of the firm.
When 2 projects are mutually exclusive (only one can be accepted), the project with the higher positive NPV should be accepted?
Yes
Time-weighted rate of return
measures compound growth. The rate at which $1 compounds over a specified performance horizon.
-Preferred method of performance measurement, because it is not affected by the timing of cash inflows and outflows.
What is the “Time-weighted rate of return”?
It measures compound growth. It is the rate at which $1 compounds over a specified performance horizon. Time-weighting is the process of averaging a set of values over time.
Steps in Time Weighted Return
1 - value portfolio immediately preceding significant additions or withdrawals.
2 - computer HPR of each subperiod
3 - compute product of (1+HPR) for each subperiod to obtain a total return for entire measurement period. If total investment period is greater than one year, must take the geometric mean of measurement period return to find annual time-weighted rate of return
Money Weighted Return
Concept of IRR to investment portfolio. defined as he internal rate of return on a portfolio, taking into account all cash inflows and outflows
- Like an IRR measure => PV(outflows) = PV(inflows)
- Periods must be equal length
- Calculating an equal HPR for all periods
Because the return rate is the same for all holding periods, the period with the most “money” has the greatest effect on the calculation.