Discharge of contract Flashcards

1
Q

What is discharge of contract?

A

When a contract comes to an end, usually by performance but could be by breach or frustration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a divisible contract?

A

Where the elements to a contract can be divided into individual segments (Ritchie v Atkinson)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

substantial performance

A

when a party has done mostly what was required under the contract, there must be payment of the amount appropriate to what has been done. - Quantum Meruit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Prevention of full performance

A

If a party prevents the innocent party from carrying out their side, the innocent party can claim to be paid on the QM basis (Plance v Colburn)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Acceptance of part performance

A

where it is agreed the other party need not fulfill their contract QM applies, but the acceptance just be a form of specific acknowledgement that the defrauding party is entitled to be paid so far. (Sumpter v Hughes)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The effects of time to performance?

A
  • THe partiess have expressley stated that time if of the essence
  • in the circumstance time for completion is critical
  • one party has failed to perform on time and the other has insisted of a new date of the contract.

(Charles Rickards LTD v Oppenheim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

how does the CRA15’ deal with time

A

Under section 52 says reasonable time

then S54 allows for a price reduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cutter v Powell

A

As the contract was for the whole voyage he had not performed the contrat

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Ritchie v Atkinson

A

The ship owner was entitled to be paid for the part of the cargo he had carried as the contract was divisible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Dakin and co. v Lee

A

Substantial performance applied as there were relatively minor defects in the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Hoenig v Issacs

A

Quantum Meruit was used to establish payment to be made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Bolton v Mahadeva

A

The defects were too great to ammount to substantial performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Young v Thames properties Ltd

A

The court used its discretion to reason a just and fair decision

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Plance v Colburn

A

An author was prevented from carrying out his contract so was paid on a QM basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Sumpter v Hedges

A

If one party has agreed the other party need not complete the entire contract, the strict rule will not apply

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Union Eagle Ltd v Golden Achievement Ltd

A

A term as to time is treated as a condition if it falls within one of the 3 categories if not it is treated as a warranty

17
Q

Charled Rickards Ltd v Oppenheim

A

This also means the right to treat it as a condition can be waived

18
Q

Discharge by Breach

A

when a contract has ended because a party didn’t or cant complete their contract

19
Q

The 3 sets of circumstance giving rise to a breach of contract are

A

Renunciation by a party of his or her liabilities under it

Impossiblity created by their own act

Total or partial failure of performance

20
Q

The 3 for repudiatory breach are

A

A breach of condition

A refusal to perform the contract

a sufficiently serious breach of an innoninate term, could become a breach of condition

21
Q

What is anticipatory breach and the leading case

A

When a party gives notice in advance that they will not be completing the contract. V can immediately sue or wait to see if performance has not taken place by the end. Hochster v de la Tour