Discharge by Performance Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What is discharge?

A

Main obligations of contract have come to an end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the strict rule?

A

Perfromance must be complete and exact
If not fulfilled their exact obligations under agreement, other party doesn’t have to fulfil their obligations either

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What happened in Cutter v Powell?

A

C tried to claim wages of husband who died before completing task
Entitled to nothing as didn’t complete work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What happened in Re Moore and Landauer?

A

C able to reject tins as they weren’t packaged in the quantities described, even though final amount was correct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the exceptions for discharge by performance?

A

Prevention of full performance
Acceptance of part performance
Divisible contracts
Substantial performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is prevention of full performance?

A

If one party prevents other from carrying out contract, innocent party can claim on a quantum merit basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is quantum merit?

A

Party can claim for work they did even though the obligation hasn’t been fulfilled as agreed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What happened in Planche v Colburn?

A

Publisher scrapped series, author able to receive quantum merit fee for prevention of full performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is acceptance of part performance?

A

Consent from both parties that’s free from pressure
If parties agree the one party doesn’t have to complete entire contract, contract must be paid on a quantum merit basis
Not consent if innocent party has no option but to take benefit for work done
Defaulting party allowed to be paid for work which they completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What happened in Sumpter v Hedges?

A

Builder ran out of money, couldn’t complete job. Customer finished work, had no choice but to finish it, didn’t consent to part performance so builder not entitled to be paid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are divisible contracts/severable contracts?

A

If contract has separate parts, it is divisible contract
Contract must be clearly divided into separate parts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What happened in Richie v Atkinson?

A

Cargo paid by the ton, only part of cargo was carried
Ship owner entitled to be paid fro the cargo he carried, did have to pay damages for breach of contract as didn’t carry entire cargo

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is substantial performance?

A

Party done substantially what is required under the contract, courts believe they have done enough
Must be paid appropriate amount
Won’t occur if contract is seen as single transaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Substantial performance - Where do these often occur?

A

In large contracts where small elements of the contract aren’t performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Substantial performance - how is the amount decided?

A

On a case by case basis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What happened in Darkin & Co v Lee?

A

Some repairs were below the standard, contract was substantially performed, builders entitled to money for wotk they did

17
Q

What happened in Hoenig v Isaacs?

A

Defective furniture supplied, decorator entitled to be paid for what he done on a quantum merit basis

18
Q

What happened in Bolton v Mahadeva?

A

Contract not substantially performed so entitled to nothing when installing defective central heating system

19
Q

What happened in Young v Thames Properties?

A

Contreact made to resurface carpark. Work was defective but contractors were paid for work done

20
Q

What is whether time of performance is important?

A

Some contracts, time is inserted
Time is a condition in following circumstances:
Parties expressly stated in contract that ‘time is of the essence’
Time of completion is critical for contract
One party hadn’t performed on time so other party insisted on another date of completion

21
Q

What happened in Union Eagle v Golden Achievement?

A

Flat for sale, completion time was 5pm, money sent at 5:10
Expressly stated that time was of the essence
Seller able to repudiate contract

22
Q

What happened in Charles Rickards v Oppenheim?

A

Car was to be built and ready for certian date, but wasn’t. Time was of the essence so able to repudiate contract and reject

23
Q

What happens if it was decided that time is not of the essence?

A

Contract must clarify this so dispute doesn’t arise again

24
Q

What are the remedies for discharge by performance?

A

Quantum merit - paid for work done
Repudiation - end contract
Specific performance - courts specify what needs to happen for dispute to be resolved
Damages - compensation when suffered loss