Design Economics & Cost Planning Flashcards
What are the RIBA stages of work?
▪ Stage 0 - Strategic Definition
▪ Stage 1 - Preparation & Brief
▪ Stage 2 - Concept design
▪ Stage 3 - Spatial Coordination
▪ Stage 4 - Technical Design
▪ Stage 5 - Manufacturing Construction
▪ Stage 6 - Handover
▪ Stage 7 - In use
Which cost plans / estimates align with these stages?
▪ RIBA Stage 0 (Target) - Initial or ‘rough’ Order of Cost Estimate
▪ RIBA Stage 1 (Target) - Order of Cost Estimate
▪ RIBA Stage 2 (Improve) - Formal Cost Plan 1
▪ RIBA Stage 3 (Improve & Control) - Formal Cost Plan 2
▪ RIBA Stage 4 (Improve & Control) - Formal Cost Plan 3 / Pre-Tender Estimate
What is the difference between tender and construction inflation?
- Tender - allowance in cost estimate/cost plan for fluctuations in the basic prices of L/P/M during the period of the estimated base date to the tender returns
- Construction - allowance in cost estimate/cost plan for fluctuations in the basic prices of L/P/M from date of tender return to construction period mid-point
What sections are included in a cost plan? (NRM1)
- Facilitating Works
- Substructure
- Superstructure
- Internal finishes
- FF&E
- Services
- Works to existing buildings
- Pre-fabricated units
- External Works
- Preliminaries
- OH&P
- Fees (Project & design)
- Risk
What are provisional sums?
They are an estimate or allowance for items without the detail, definition or design to be able to produce an accurate cost.
Or items that employer may/may not wish to carry out themselves
Defined - Contractor has made an allowance for programming and prelims
Undefined - Contractor hasn’t allowed for planning, programming or prelims and therefore may be entitled to an EoT or additional prelims.
How would you manage a provisional sum?
Add/omit using the contract
What are the sections in a pre-contract cost report?
▪ Executive Summary
▪ Control accounts
▪ Change register
▪ Value Engineering
▪ Risk
What are the sections in a post-contract cost report?
▪ Executive Summary / overview
▪ Control accounts
▪ Provisional Sums
▪ Changes / Variations
▪ Cashflow