Design Economics & Cost Planning Flashcards

1
Q

What are the RIBA stages of work?

A

▪ Stage 0 - Strategic Definition
▪ Stage 1 - Preparation & Brief
▪ Stage 2 - Concept design
▪ Stage 3 - Spatial Coordination
▪ Stage 4 - Technical Design
▪ Stage 5 - Manufacturing Construction
▪ Stage 6 - Handover
▪ Stage 7 - In use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which cost plans / estimates align with these stages?

A

▪ RIBA Stage 0 (Target) - Initial or ‘rough’ Order of Cost Estimate
▪ RIBA Stage 1 (Target) - Order of Cost Estimate
▪ RIBA Stage 2 (Improve) - Formal Cost Plan 1
▪ RIBA Stage 3 (Improve & Control) - Formal Cost Plan 2
▪ RIBA Stage 4 (Improve & Control) - Formal Cost Plan 3 / Pre-Tender Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the difference between tender and construction inflation?

A
  • Tender - allowance in cost estimate/cost plan for fluctuations in the basic prices of L/P/M during the period of the estimated base date to the tender returns
  • Construction - allowance in cost estimate/cost plan for fluctuations in the basic prices of L/P/M from date of tender return to construction period mid-point
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What sections are included in a cost plan? (NRM1)

A
  1. Facilitating Works
  2. Substructure
  3. Superstructure
  4. Internal finishes
  5. FF&E
  6. Services
  7. Works to existing buildings
  8. Pre-fabricated units
  9. External Works
  10. Preliminaries
  11. OH&P
  12. Fees (Project & design)
  13. Other project costs (Land, planning, Building Control, insurances)
  14. Risk (Design Dev, construc, Empl change, Empl other)
  15. Inflation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are provisional sums?

A

They are an estimate or allowance for items without the detail, definition or design to be able to produce an accurate cost.
Or items that employer may/may not wish to carry out themselves

Defined - Contractor has made an allowance for programming and prelims

Undefined - Contractor hasn’t allowed for planning, programming or prelims and therefore may be entitled to an EoT or additional prelims.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How would you manage a provisional sum?

A

Add/omit using the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the sections in a pre-contract cost report?

A

▪ Executive Summary
▪ Narrative on the latest financial position (based on cost plans)
▪ Value Engineering
▪ Risks & opportunities
▪ Client information items pending
▪ Overview of market conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the sections in a post-contract cost report?

A

▪ Executive Summary / overview
▪ Contract Sum
▪ Current cost
▪ Projected Final Account
▪ Provisional Sums
▪ Changes / Variations (Pending & instructed)
▪ Claims
▪ Risks
▪ Contingency Position
▪ Cashflow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the NRM?

A

The New Rules of Measurement are a guidance note that sets out best practice for measurement in the construction industry. They are produced by the RICS.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the different parts of the suite?

A

NRM1 - Order of cost estimating and cost planning for capital building works
NRM2 - Detailed measurement of construction works
NRM3 - Order of cost estimating and cost planning for maintenance works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Are there any other guidance documents for measurement you could refer to?

A

RICS Code of Measurement Practice
(Comp 6?! & IPMS?!)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between a order of cost estimate and cost plan?

A

○ Order of Cost Estimate - An estimate based on little detail, just using the employer’s initial brief. Based on benchmark data of a similar project. Typically £/m2.

○ Cost Plan - An estimate based on a specific design. Level of design available is more detailed. Rather than £/m2, you typically have an elemental breakdown, including quantities and rates.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the different types of order of cost estimate?

A

Budget - Sets the client budget. (Comes first)

Feasibility - Advises the client on the affordability of development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can you explain the sources of cost data?

A

Internal
○ Market rates app
○ Past projects
○ Tender returns
○ Quotations

External
○ BCIS
○ Spons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would you select appropriate benchmark data?

A
  • Use a combination of BCIS and past projects to find similar schemes.
  • Select 3 or 4 that are most similar and, after adjusting all for time and location, compare the average costs against the initial client brief for my scheme.
  • Need to make sure to have an awareness of the abnormals for each scheme and factor these in to your data analysis.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How would you adjust these rates / costs for benchmarking?

A

By time and location factor.

17
Q

Are you aware of the Pareto rule?

A

80/20 rule - 80% of cost is set by the time 20% of the design is undertaken.

This is why it is important as a QS to be involved in the process as early as possible.

18
Q

Can you please explain the difference between VE and scope reduction?

A

Value engineering is changing elements of the work to increase the value for money for a client, scope reduction is simply that, reducing the scope to cost cut.

19
Q

Can you provide an example of VE?

A

○ Bringing specification back in line with the clients brief in terms of internal finishes.
○ Alternative lift supplier that offered a significant cost saving.
○ Review design which could be more complicated? (cladding)
○ Review general specifications

20
Q

What is value management?

A

It is used to assess the value of a project and maximise the value for the client.
Value engineering forms a part of value management.

21
Q

What is the process of Value Management?

A

Is the overall term used to achieve value on a project. Value isn’t necessarily money related.

Split into three main categories:

  1. Value Planning - A proactive approach as to how to achieve value on the project.
  2. Value Engineering - A reactive approach to reduce costs on the scheme. Do this by scheduling out costs vs function.
  3. Value Analysis - A post project approach to review what value has been achieved.
22
Q

What are the alternatives to a CSA or BoQ?

A

○ Activity Schedule - a list of the activities that the contractor expects to be undertaken in order to complete their contractual obligations.

○ Schedule of Rates - a schedule of rates is agreed and then the contractor puts actual quants against as construction progresses.

23
Q

Can you tell me the difference between a feasibility study and a formal cost plan?

A

Feasibility report would generally be undertaken at Stage 1 and based on functional unit or cost/m2 based on the GIFA or IPMS measurement if the building was applicable to IPMS (e.g. office fit out)

24
Q

You’ve noted in your documents that you used market testing, past project data and pricing books. What is the importance of having multiple sources of cost data?

A

Reliability of rates by assessing different rates for the same element. Helps with making informed decisions.

25
Q

Can you please summarise what the RIBA Plan of Works looks to achieve and at what stages you would expect to undertake a cost estimate / cost plan

A

The RIBA Plan of Work is designed to provide a structured framework for managing the design and construction process of building projects.

▪ RIBA Stage 0 - Initial or ‘rough’ Order of Cost Estimate
▪ RIBA Stage 1 - Order of Cost Estimate
▪ RIBA Stage 2 - Formal Cost Plan 1
▪ RIBA Stage 3 - Formal Cost Plan 2
▪ RIBA Stage 4 - Formal Cost Plan 3 / Pre-Tender Estimate