Design Economics & Cost Planning Flashcards

1
Q

What are the RIBA stages of work?

A

▪ Stage 0 - Strategic Definition
▪ Stage 1 - Preparation & Brief
▪ Stage 2 - Concept design
▪ Stage 3 - Spatial Coordination
▪ Stage 4 - Technical Design
▪ Stage 5 - Manufacturing Construction
▪ Stage 6 - Handover
▪ Stage 7 - In use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which cost plans / estimates align with these stages?

A

▪ RIBA Stage 0 (Target) - Initial or ‘rough’ Order of Cost Estimate
▪ RIBA Stage 1 (Target) - Order of Cost Estimate
▪ RIBA Stage 2 (Improve) - Formal Cost Plan 1
▪ RIBA Stage 3 (Improve & Control) - Formal Cost Plan 2
▪ RIBA Stage 4 (Improve & Control) - Formal Cost Plan 3 / Pre-Tender Estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the difference between tender and construction inflation?

A
  • Tender - allowance in cost estimate/cost plan for fluctuations in the basic prices of L/P/M during the period of the estimated base date to the tender returns
  • Construction - allowance in cost estimate/cost plan for fluctuations in the basic prices of L/P/M from date of tender return to construction period mid-point
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What sections are included in a cost plan? (NRM1)

A
  1. Facilitating Works
  2. Substructure
  3. Superstructure
  4. Internal finishes
  5. FF&E
  6. Services
  7. Works to existing buildings
  8. Pre-fabricated units
  9. External Works
  10. Preliminaries
  11. OH&P
  12. Fees (Project & design)
  13. Risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are provisional sums?

A

They are an estimate or allowance for items without the detail, definition or design to be able to produce an accurate cost.
Or items that employer may/may not wish to carry out themselves

Defined - Contractor has made an allowance for programming and prelims

Undefined - Contractor hasn’t allowed for planning, programming or prelims and therefore may be entitled to an EoT or additional prelims.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How would you manage a provisional sum?

A

Add/omit using the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the sections in a pre-contract cost report?

A

▪ Executive Summary
▪ Control accounts
▪ Change register
▪ Value Engineering
▪ Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the sections in a post-contract cost report?

A

▪ Executive Summary / overview
▪ Control accounts
▪ Provisional Sums
▪ Changes / Variations
▪ Cashflow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly