definitions Flashcards
acceptance criteria
A set of conditions that are met before deliverables are accepted. See also deliverable and requirement.
Activity
A distinct, scheduled portion of work performed during the course of a project.
Activity Code
An alphanumeric value assigned to each activity that enables classifying, sorting, and filtering. See also activity identifier and activity label.
Activity Identifier
A unique alphanumeric value assigned to an activity and used to differentiate that activity from other activities. See also activity code and activity label.
Activity Label
A phrase that names and describes an activity. See also activity code and activity identifier.
Actual Cost (AC)
The realized cost incurred for the work performed on an activity during a specific time period. See also budget at completion (BAC), earned value (EV), estimate at completion (EAC), estimate to complete (ETC), and planned value (PV).
Analogous Estimating
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. See also bottom-up estimating, parametric estimating, program evaluation and review technique (PERT), and three-point estimating.
Apportioned Effort
An activity where effort is allotted proportionately across certain discrete efforts and not divisible into discrete efforts. [Note: Apportioned effort is one of three earned value management (EVM) types of activities used to measure work performance. See also discrete effort and level of effort.
Assumption
A factor in the planning process considered to be true, real, or certain, without proof or demonstration.
Backward Pass
A critical path method technique for calculating the late start and late finish dates by working backward through the schedule model from the project end date. See also forward pass.
Baseline
The approved version of a work product that can be changed using formal change control procedures and is used as the basis for comparison to actual results. See also cost baseline, performance measurement baseline, schedule baseline, and scope baseline.
Bottom-Up Estimating
A method of estimating project duration or cost by aggregating the estimates of the lower-level components of the work breakdown structure (WBS). See also analogous estimating, parametric estimating, program evaluation and review technique (PERT), and three-point estimating.
Budget at Completion (BAC)
The sum of all budgets established for the work to be performed. See also actual cost (AC), earned value (EV), estimate at completion (EAC), estimate to complete (ETC), and planned value (PV).
Change Control
A process whereby modifications to documents, deliverables, or baselines associated with the project are identified, documented, approved, or rejected. See also change control board and change control system.
Change Control Board
A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project, and for recording and communicating such decisions. See also change control and change control system.
Change Control System
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled. See also change control and change control board.