Deck 4 Flashcards

1
Q

What is Project Float?

A

The amount of time that a project can be delayed without violating the project deadline imposed by the customer, or the delivery date committed to the customer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Padding?

A

The amount of unreasonable extra time added to the estimate, just to feel confident with the estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Program Management?

A

The application of knowledge, skills, and principles to a program to achieve the program objectives and obtain benefits and control not available by managing program components individually.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements is known as ___________________.

A

The application of knowledge, skills, tools, and techniques to project activities to meet project requirements in known as <u>Project Management</u>.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Project Management?

A

The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Procurement Strategy?

A

The approach by the buyer to determine the project delivery method and the type of legally binding agreement(s) that should be used to deliver the desired results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the event that officially authorizes a project?

A

The approval of the Project Charter.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Budget?

A

The approved (cost) estimate for a project, WBS component or a schedule activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Cost Baseline?

A

The approved time-phased budget of the project (excluding any management reserves) that is used to compare actual costs to planned costs in order to determine variance and need for preventive or corrective action.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a Schedule Baseline?

A

The approved version of a schedule model that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a Scope Baseline?

A

The approved version of a scope statement, work breakdown structure (WBS), and its associated WBS dictionary, that can be changed using formal change control procedures and is used as a basis for comparison to actual results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a Baseline?

A

The approved version of a work product that can be changed only through formal change control procedures and is used as a basis for comparison to actual results.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are Specification Limits?

A

The area on either side of the mean on a control chart that reflects the customer’s requirements for a product or service. This area may be greater than or less than the area defined by the control limits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are Control Limits?

A

The area within three standard deviations on either side of the mean on a control chart that reflects the expected variation in the data.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is Planned Value (PV)?

A

The authorized budget assigned to scheduled work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When is the Benefits Management Plan developed?

A

The Benefits Management Plan is developed prior to project initiation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which is the best form of power for a Project Manager?

A

The best form of power depends upon the situation and the maturity level of the project manager. Generally speaking, personal powers (such as Expert and Referent) are better than positional powers (such as Legitimate, Reward and Punitive).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is Budget at Completion (BAC)?

A

The budget for all the work on the project. It is also the total planned value for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is Portfolio Management?

A

The centralized management of one or more portfolios to achieve strategic objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Who can authorize the use of Management Reserves?

A

The change control process is used to obtain approval to move the applicable management reserve funds into the cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is the Deming Cycle?

A

The checklist of the four stages which you must go through to get from “problem-faced” to “problem solved”. The four stages are Plan-Do-Check-Act. It is also known as Shewhart Cycle. It is used for continuous improvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is Schedule Data?

A

The collection of information for describing and controlling the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

In which document would you find a glossary of common project terminology?

A

The Communications Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

In which document would you find the template for project status reports?

A

The Communications Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is Life Cycle Cost?

A

The cost of a product over its entire life (including cost of development, acquisition, operation, support and disposal), and not just the project cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is To-Complete-Performance-Index (TCPI)?

A

The cost performance that must be achieved on the remaining work to meet a BAC (or EAC) target. It is the ratio of “remaining work” to the “funds remaining”.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What is Present Value (PV)?

A

The current value of future cash flow, discounted to reflect the time value of money and other factors such as investment risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Who defines the product scope?

A

The customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Who defines the quality of a product, service or result of a project?

A

The customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is the role of the customer in XP?

A

The customer in XP provides the requirements, sets the priorities, and steers the projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is a Finish Date?

A

The date of completion of a schedule activity, usually qualified by one of the eight following: actual, planned, estimated, scheduled, early, late, baseline, target, or current.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Give an example of Start-to-finish (SF) dependency.

A

The day shift worker (predecessor) cannot leave work until the night shift worker (successor) has taken over the command.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is meant by Risk Appetite?

A

The degree of uncertainty an organization or individual is willing to accept in anticipation of a reward.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What is risk propinquity?

A

The degree to which a risk is perceived to matter by one or more stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What is the definition of Quality?

A

The degree to which a set of inherent characteristics fulfills requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What is risk controllability?

A

The degree to which the risk owner (or owning organization) is able to control the risk’s outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What are Accepted Deliverables?

A

The deliverables that meet the acceptance criteria and have been formally signed off by the customer or sponsor through the Validate Scope process. These deliverables may be reviewed by the customer before giving a final sign-off on the entire project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What is a Project Scope Statement?

A

The description of the project scope, including major deliverables, and exclusions. It provides a basis for making future project decisions and provides a common understanding of project scope among the stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What is Variance?

A

The difference between the actual (measured) value (of scope, schedule, cost, quality, etc.) and the baseline value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

What is Float?

A

The difference between the time available for performing an activity and the time required to complete it. It is also known as Slack.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What is a Project Management Plan?

A

The document that describes how the project will be executed, monitored and controlled, and closed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

What is a Benefits Management Plan?

A

The documented explanation defining the processes for creating, maximizing, and sustaining the benefits provided by a project or program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What is Product Scope Description?

A

The documented narrative description of the product scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

What are Quality Control Measurements?

A

The documented results of Control Quality activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What are Procurement Documents?

A

The documents utilized in bid and proposal activities, including Invitation for Bid, Invitation for Negotiations, Request for Information, Request for Quotation, Request for Proposal and seller’s responses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

What is Earned Schedule (ES)?

A

The duration from the beginning of the project to the date on which the PV should have been equal to the current value of EV. On the EVM chart, it is the date on which the horizontal line through the current value of EV intersects the PV curve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

What is risk detectability?

A

The ease with which the results of the risk occurring, or being about to occur, can be detected and recognized.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

What is risk manageability?

A

The ease with which the risk owner (or owning organization) can manage the occurrence or impact of a risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Who owns the code in XP?

A

The entire team collectively owns the code in XP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

What is a Sponsoring Organization?

A

The entity responsible for providing the project’s sponsor and a conduit for project funding or other project resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What is Earned Value (EV)?

A

The estimated (monetary) value of the work accomplished expressed in terms of the budget authorized for that work. It is also referred to as the budgeted cost of work performed (BCWP).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

What is Estimate to Complete (ETC)?

A

The expected cost to complete all the “remaining work” on a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What is Estimate at Completion (EAC)?

A

The expected total cost of completing all the work on a project expressed as the sum of the actual cost to date and the estimate to complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

What is risk connectivity?

A

The extent to which the risk is related to other individual project risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

What are Enterprise Environmental Factors?

A

The external or internal factors, not under the immediate control of the team, that influence, constrain, or direct the project, program, or portfolio. Examples include organizational culture, industry standards, existing infrastructure and human capital, marketplace conditions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

What is Risk Premium?

A

The extra return in excess of (over and above) the risk-free rate of return of an investment (example, a project). It’s a compensation for the risk to the party (example, a contractor to whom the risk is transferred) that accepts the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

How does an Influence Diagram help in risk analysis?

A

The factors which influence a risk can be shown hierarchically in an influence diagram, to demonstrate their influence on key outcomes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

What is Product Scope?

A

The features and functions that characterize a product, service, or result.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

How do you calculate the float of a network path in Critical Path Method?

A

The float of a path is the difference between the duration of the Critical Path and the duration of the (given) path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Define Legitimate Power.

A

The formal authority or power derived from the position. Team members perceive the project manager as being officially empowered to issue orders. It is also known as Formal Power.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Define Governance.

A

The framework within which authority is exercised in organizations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

What is Project Governance?

A

The framework, functions, and processes that guide project management activities in order to create a unique product, service, or result to meet organizational, strategic, and operational goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

Which is better - a project with higher NPV or a project with lower NPV?

A

The higher the NPV, the better.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

What is Empiricism?

A

The idea that the best way of planning is to do work and learn from it. It is a fundamental for Scrum and agile approaches.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Which of the following are characteristics of a good information radiator?

A

The information should change over time and easy to view.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

What are Lessons Learned?

A

The knowledge gained during a project which shows how project events were addressed or should be addressed in the future with the purpose of improving future performance. They can be identified at any point during the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

What is Actual Duration?

A

The length of time between the actual start date and the data date for in-progress activities, or between the actual start date and the actual finish date for completed activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

What is meant by Risk Threshold?

A

The level of risk exposure above which risks are addressed and below which risks may be accepted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

What is a Finish-to-Finish (FF) dependency?

A

The logical relationship where the successor (“to”) activity cannot complete until the predecessor (“from”) activity completes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

What is a Finish-to-Start (FS) dependency?

A

The logical relationship where the successor (“to”) activity cannot start until the predecessor (“from”) activity completes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

How can Risk Breakdown Structure (RBS) be used in Risk Identification?

A

The lowest level of the RBS can be used as a risk identification checklist.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

What is Ceiling Price?

A

The maximum price that a buyer is willing to pay. It includes Target Price plus buyer’s share of the cost overrun.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

What is the formula for Mean?

A

The mean of n values (x1, x2, x3, .. , xn) is: (x1 + x2 + x3 + .. + xn) / n

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

What are Bidder Conferences?

A

The meetings with prospective sellers prior to the preparation of a bid or proposal to ensure all prospective vendors have a clear and common understanding of the procurement. Also known as contractor conferences, vendor conferences, or pre-bid conferences.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

What is a Project Management Team?

A

The members of the project team who are directly involved in project management activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

What is Discounted Cash Flow (DCF) method of project selection?

A

The method of discounting future cash flows at an interest rate that reflects time value of money and a risk premium. DCF is the amount that someone is willing to pay today in anticipation of future cash flows (returns).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

What is Development Approach in the context of project management?

A

The method used to create and evolve the product, service, or result during the project life cycle, such as predictive, iterative, incremental, agile, or a hybrid method.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

What is Little’s Law?

A

The more things that you work on at any given time, the longer it is going to take for each of those things to finish.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Which estimate is weighed more heavily in the beta distribution estimating?

A

The Most Likely estimate. It has 4 times more weightage than the Optimistic and Pessimistic estimates using beta distribution. The formula for expected cost using beta distribution is: cE ( cO + 4*cM + cP ) / 6 where cE is the expected cost, cO the optimistic estimate, cM the most likely estimate and cP the pessimistic estimate of the activity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Define Effort.

A

The number of labor units required to complete a schedule activity or work breakdown structure component, often expressed in hours, days, or weeks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

What is a Quality Management System?

A

The organizational framework whose structure provides the policies, processes, procedures, and resources required to implement the Quality Management Plan. The typical project Quality Management Plan should be compatible to the organization’s quality management system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Who is a Buyer?

A

The owner of the final product, a subcontractor, the acquiring organization, a service requestor, or the purchaser.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Who are sideward stakeholders?

A

The peers of the project manager, such as other project managers or middle managers who are competing or sharing project resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

What is Work Performance Information?

A

The performance data collected from controlling processes, analyzed in comparison with project management plan components, project documents, and other work performance information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

What is risk proximity?

A

The period of time before the risk might have an impact on one or more project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

What is risk dormancy?

A

The period of time that may elapse after a risk has occurred before its impact is discovered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
87
Q

What is risk urgency?

A

The period of time within which a response to the risk is to be implemented in order to be effective.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
88
Q

Who is a Project Manager (PM)?

A

The person assigned by the performing organization to lead the team that is responsible for achieving the project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
89
Q

Who is a Risk Owner?

A

The person responsible for monitoring the risks and for selecting and implementing an appropriate risk response strategy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
90
Q

Define Customer.

A

The person(s) or organization(s) that will pay for the project’s product, service, or result.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
91
Q

What are Work Performance Reports?

A

The physical or electronic representation of work performance information compiled in project documents, intended to generate decisions, actions, or awareness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
92
Q

What is a Threshold?

A

The point beyond which an event or risk becomes unacceptable and a response should be triggered.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
93
Q

What is risk strategic impact?

A

The potential for the risk to have a positive or negative effect on the organization’s strategic goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
94
Q

Define Referent Power.

A

The power derived from personality traits or charisma. It is also known as Charisma Power.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
95
Q

Define Expert Power.

A

The power derived from special knowledge or expertise.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
96
Q

What is Situational power?

A

The power gained due to unique situation such as a specific crisis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
97
Q

What is Relational power?

A

The power gained through networking, connections, and alliances.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
98
Q

Define Reward Power.

A

The power of directly or indirectly rewarding the team member. Rewards may be in the form of salary, promotion, bonus or better work assignments.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
99
Q

Define Coercive Power.

A

The power to invoke discipline or negative consequences. It may be in the form of suspension, reprimand, unpleasant assignments, etc. It is also known as Punitive or Penalty Power.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
100
Q

What is the Determine Budget process?

A

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
101
Q

What is the Develop Schedule process?

A

The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model for project execution and monitoring and controlling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
102
Q

What is the Manage Stakeholder Engagement process?

A

The process of communicating and working with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
103
Q

What is the Plan Scope Management process?

A

The process of creating a scope management plan that documents how the project and product scope will be defined, validated, and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
104
Q

What is the Plan Cost Management process?

A

The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
105
Q

What is the Plan Risk Management process?

A

The process of defining how to conduct risk management activities for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
106
Q

What is the Plan Resource Management process?

A

The process of defining how to estimate, acquire, manage, and utilize physical and team resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
107
Q

What is the Develop Project Management Plan process?

A

The process of defining, preparing, and coordinating all plan components and consolidating them into an integrated project management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
108
Q

What is the Collect Requirements process?

A

The process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
109
Q

What is the Define Scope process?

A

The process of developing a detailed description of the project and product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
110
Q

What is the Develop Project Charter process?

A

The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
111
Q

What is the Plan Communications Management process?

A

The process of developing an appropriate approach and plan for project communication activities based on the information needs of each stakeholder or group, available organizational assets, and the needs of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
112
Q

What is the Estimate Costs process?

A

The process of developing an approximation of the monetary resources needed to complete project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
113
Q

What is the Plan Stakeholder Engagement process?

A

The process of developing approaches to involve project stakeholders, based on their needs, expectations, interests, and potential impact on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
114
Q

What is the Plan Risk Responses process?

A

The process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
115
Q

What is the Plan Procurement Management process?

A

The process of documenting project procurement decisions, specifying the approach, and identifying potential sellers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
116
Q

What is Total Quality Management (TQM)?

A

The process of ensuring that the end result will meet the quality expectations of the customer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
117
Q

What is the Monitor Communications process?

A

The process of ensuring that the information needs of the project and its stakeholders are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
118
Q

What is the Control Resources process?

A

The process of ensuring that the physical resources assigned and allocated to the project are available as planned, as well as monitoring the planned versus actual utilization of resources and performing corrective action as necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
119
Q

What is the Manage Communications process?

A

The process of ensuring timely and appropriate collection, creation, distribution, storage, retrieval, management, monitoring, and the ultimate disposition of project information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
120
Q

What is the Plan Schedule Management process?

A

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
121
Q

What is the Estimate Activity Resources process?

A

The process of estimating team resources and the type and quantities of material, equipment, and supplies necessary to perform project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
122
Q

What is the Estimate Activity Durations process?

A

The process of estimating the number of work periods needed to complete individual activities with the estimated resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
123
Q

What is the Close Project or Phase process?

A

The process of finalizing all activities for the project, phase, or contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
124
Q

What is the Validate Scope process?

A

The process of formalizing acceptance of the completed project deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
125
Q

What are Documentation Reviews?

A

The process of gathering a corpus of information and reviewing it to determine accuracy and completeness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
126
Q

What is Market Research?

A

The process of gathering information at conferences, online reviews, and a variety of sources to identify market capabilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
127
Q

What is the Sequence Activities process?

A

The process of identifying and documenting relationships among the project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
128
Q

What is the Define Activities process?

A

The process of identifying and documenting the specific actions to be performed to produce the project deliverables.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
129
Q

What is the Identify Risks process?

A

The process of identifying individual risks as well as sources of overall risk and documenting their characteristics.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
130
Q

What is the Identify Stakeholders process?

A

The process of identifying project stakeholders regularly and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
131
Q

What is the Plan Quality Management process?

A

The process of identifying quality requirements and/or standards for the project and its deliverables, and documenting how the project will demonstrate compliance with quality requirements and/or standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
132
Q

What is Change Control?

A

The process of identifying, documenting, approving or rejecting changes to project documents, deliverables, or baselines (scope, schedule, cost, etc.).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
133
Q

What is the Implement Risk Responses process?

A

The process of implementing agreed-upon risk response plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
134
Q

What is the Develop Team process?

A

The process of improving competences, team member interaction, and overall team environment to enhance project performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
135
Q

What is the Direct and Manage Project Work process?

A

The process of leading and performing the work defined in the Project Management Plan and implementing approved changes to achieve the project’s objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
136
Q

What is the Control Procurements process?

A

The process of managing procurement relationships, monitoring contract performance, making changes and corrections as appropriate, and closing out contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
137
Q

What is the Control Quality process?

A

The process of monitoring and recording results of executing the quality management activities to assess performance and ensure the project outputs are complete, correct, and meet customer expectations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
138
Q

What is the Monitor Stakeholder Engagement process?

A

The process of monitoring project stakeholder relationships, and tailoring strategies for engaging stakeholders through the modification of engagement strategies and plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
139
Q

What is the Monitor Risks process?

A

The process of monitoring the implementation of agreed-upon risk response plans, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
140
Q

What is the Control Scope process?

A

The process of monitoring the status of project and product scope, and managing changes to the scope baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
141
Q

What is the Control Costs process?

A

The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
142
Q

What is the Control Schedule process?

A

The process of monitoring the status of the project to update the project schedule and manage changes to the schedule baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
143
Q

What is the Perform Quantitative Risk Analysis process?

A

The process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
144
Q

What is the Conduct Procurements process?

A

The process of obtaining seller responses, selecting a seller, and awarding a contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
145
Q

What is the Acquire Resources process?

A

The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
146
Q

What is the Perform Qualitative Risk Analysis process?

A

The process of prioritizing individual project risks for further analysis or action by assessing their probability of occurrence and impact as well as other characteristics.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
147
Q

What is Claims Administration?

A

The process of processing, adjudicating, and communicating contract claims.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
148
Q

What is the Perform Integrated Change Control process?

A

The process of reviewing all change requests, approving changes and managing changes to deliverables, organizational process assets, project documents, and the Project Management Plan, and communicating the decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
149
Q

What are Proposal Evaluation Techniques?

A

The process of reviewing proposals provided by suppliers to support contract award decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
150
Q

What is the Create WBS process?

A

The process of subdividing project deliverables and project work into smaller, more manageable components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
151
Q

What is the Manage Team process?

A

The process of tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
152
Q

What is the Monitor and Control Project Work process?

A

The process of tracking, reviewing, and reporting overall progress to meet the performance objectives defined in the project management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
153
Q

What is the Manage Quality process?

A

The process of translating the quality management plan into executable quality activities that incorporate the organization’s quality policies into the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
154
Q

What is the Manage Project Knowledge process?

A

The process of using existing knowledge and creating new knowledge to achieve the project’s objectives and contribute to organizational learning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
155
Q

What is Configuration Verification and Audit?

A

The process of verifying the correctness of the product and its components in order to ensure conformance to requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
156
Q

What is Verification?

A

The process to check whether the product (or deliverable) was built right. It is often an internal process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
157
Q

What is Validation?

A

The process to check whether the right product (or deliverable) was built. It is usually an external process and involves customer acceptance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
158
Q

What is the Closing Process Group?

A

The process(es) performed to formally complete or close a project, phase, or contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
159
Q

What is the Executing Process Group?

A

The processes performed to complete the work defined in the project management plan to satisfy the project requirements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
160
Q

What is the Initiating Process Group?

A

The processes performed to define a new project or a new phase of an existing project by obtaining authorization to start the project or phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
161
Q

What is the Planning Process Group?

A

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project was undertaken to achieve.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
162
Q

What is the Monitoring and Controlling Process Group?

A

The processes that track, review, and regulate the progress and performance of the project against the Project Management Plan; identify any areas in which changes to the plan are required; and initiate the corresponding changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
163
Q

Who develops the Acceptance Criteria on agile projects?

A

The Product Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
164
Q

Who makes the final call on priority order in the Product Backlog?

A

The Product Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
165
Q

If you want to know the project purpose, which document would you refer to?

A

The Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
166
Q

Which project document grants formal powers to a Project Manager?

A

The Project Charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
167
Q

What does a positive (+) Schedule Variance (SV) indicate?

A

The project is ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
168
Q

What does a Schedule Performance Index (SPI) value of more than 1 indicate?

A

The project is ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
169
Q

What does a negative (-) Schedule Variance (SV) indicate?

A

The project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
170
Q

What does a Schedule Performance Index (SPI) value of less than 1 indicate?

A

The project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
171
Q

What does a Cost Performance Index (CPI) value of less than 1 indicate?

A

The project is over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
172
Q

What does a negative (-) Cost Variance (CV) indicate?

A

The project is over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
173
Q

What does a Cost Performance Index (CPI) value of more than 1 indicate?

A

The project is under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
174
Q

What does a positive (+) Cost Variance (CV) indicate?

A

The project is under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
175
Q

What is the primary source of information for how the project will be planned, executed, monitored and controlled, and closed?

A

The Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
176
Q

Who can authorize the use of Contingency Reserves?

A

The Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
177
Q

Who has the ultimate responsibility for quality on a project?

A

The Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
178
Q

Who provides direction and vision of success for the project?

A

The Project Manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
179
Q

Who are the change agents in an organization?

A

The Project Managers are the change agents in an organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
180
Q

Who develops the Definition of Done on agile projects?

A

The project team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
181
Q

What is the purpose of Portfolio Management?

A

The purpose of Portfolio Management is to ensure that projects and programs are reviewed to prioritize resource allocation, and are aligned to organizational strategies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
182
Q

What is the definition of Tolerance?

A

The quantified description of acceptable variation for a quality requirement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
183
Q

Responsibility Assignment Matrix (RAM) vs Responsible, Accountable, Consult, And Inform (RACI)

A

The RACI is just one type of RAM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
184
Q

What is Percent Complete?

A

The ratio of the estimated amount of work completed to the total estimated work on an activity or a WBS component, expressed in percentage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
185
Q

What is Sharing Ratio?

A

The ratio that describes how the buyer and the seller share cost savings or cost overruns. It is usually expressed as X:Y, where X is the percentage share of the buyer, and Y is that of the seller.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
186
Q

What is Work Performance Data?

A

The raw observations and measurements made while activities are being performed. It includes % work complete, technical performance measures, activity start and finish dates, actual costs and durations, no. of defects, etc. It is collected as part of the Direct and Manage Project Work process, and is input to most M&C processes. It is combined with forecasts to generate Work Performance Reports.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
187
Q

What are the benefits of using a Resource Breakdown Structure (RBS)?

A

The RBS is used for planning, managing and controlling project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
188
Q

What is Political Awareness?

A

The recognition of power relationships, both formal and informal, and also the willingness to operate within these structures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
189
Q

What is Configuration Status Accounting?

A

The recording and reporting of all the changes to the configuration items.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
190
Q

The requirement to deliver the project within $500,000 is a __________ (Project or Product) requirement.

A

The requirement to deliver the project within $500,000 is a <u>Project</u> requirement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
191
Q

The requirement to make an earthquake-proof structure in a construction project is a __________ (Project or Product) requirement.

A

The requirement to make an earthquake-proof structure in a construction project is a <u>Product</u> requirement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
192
Q

Resource Histogram vs Resource Calendar

A

The Resource Histogram shows when resources are “needed” for the project, and the Resource Calendar shows when the resources are “available” for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
193
Q

What are Procurement Audits?

A

The review of contracts and contracting processes for completeness, accuracy, and effectiveness.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
194
Q

What is Authority?

A

The right to apply project resources, expend funds, make decisions, or give approvals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
195
Q

Which Enterprise Environmental Factors can influence the Plan Risk Management process?

A

The risk appetite, attitudes and tolerances of the organizations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
196
Q

Residual Risks vs Secondary Risks

A

The risks that remain after risk responses have been implemented are called Residual Risks. New risks that emerge as a result of applying risk response strategies are called Secondary Risks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
197
Q

Why is Scope Baseline an input to the Identify Risks process?

A

The scope baseline includes deliverables and criteria for their acceptance, some of which might give rise to risk. It also contains the WBS, which can be used for identifying risks at the project level as well as the work package or control account level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
198
Q

Why is Scope Baseline an input to the Develop Schedule process?

A

The scope statement, WBS, and WBS dictionary (components of scope baseline) have details about the project deliverables that are considered when building the schedule model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
199
Q

What is meant by Selected Sellers?

A

The sellers who have been selected to provide a contracted set of services or products.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
200
Q

Who is responsible for quality in the organization as a whole?

A

The senior management of the organization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
201
Q

What is the Shu-Ha-Ri model?

A

The Shu-Ha-Ri model is often used to address the appropriate time and opportunity for process tailoring in agile. Level 1 is Shu (follow), Level 2 is Ha (break away), and Level 3 is Ri (fluency or go beyond and transcend).

202
Q

Define Competence.

A

The skill and capacity required to complete assigned activities within the project constraints.

203
Q

Who can approve changes to the Project Charter?

A

The Sponsor

204
Q

Who usually authors the Project Charter?

A

The sponsor. The project manager may participate in the development of the project charter.

205
Q

What are the components of a Sprint Backlog?

A

The Sprint Backlog is composed of the Sprint Goal (why), a set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how).

206
Q

Why is the Stakeholder Engagement Plan an input to the Plan Quality Management process?

A

The stakeholder engagement plan provides the method for documenting the stakeholders’ needs and expectations that provide the foundation for quality management.

207
Q

What is the PMBOK® Guide?

A

The standard for managing most projects most of the time across many types of industries. It describes the project management processes used to manage a project toward a more successful outcome.

208
Q

What is a Start Date?

A

The start date of a schedule activity, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.

209
Q

Define Scope.

A

The sum of the products, services, and results to be provided as a project.

210
Q

What is Business Value?

A

The tangible and intangible benefits from an investment.

211
Q

What is the best practice in regard to the Team Charter?

A

The Team Charter works best when the team develops it, or at least has an opportunity to contribute to it.

212
Q

What is Timeboxing?

A

The technique of using a fixed duration, short cycle time of development work.

213
Q

Communication vs Communications

A

The term “communication” indicates the act of communicating, such as facilitating a meeting, giving information and active listening. The term “communications” indicates the artifacts of communication, such as memos, presentations, and emails.

214
Q

What is Voice of the Customer (VOC)?

A

The term to describe the stated and unstated customer needs or requirements.

215
Q

What is a Precedence Relationship?

A

The term used for a logical relationship in the Precedence Diagramming Method (PDM). Also referred to as logical relationship, and dependency.

216
Q

What is the Law of Diminishing Returns?

A

The theory that after a certain point, the increase in input of a process does not lead to a proportional increase in the output.

217
Q

What are Management Reserves?

A

The time and cost reserves that account for “unknown-unknowns” or simply “unknowns”.

218
Q

What is Activity Duration?

A

The time in calendar units between the start and finish of a schedule activity. In simple terms, it’s the length of time that it takes to complete an activity.

219
Q

What is a Lead?

A

The time period by which a successor activity is accelerated (or can start earlier) with respect to the predecessor on a schedule network.

220
Q

What is Cost of Quality (CoQ)?

A

The total cost of all quality related efforts throughout the product life cycle. It includes prevention and appraisal costs (cost of conformance), and failure costs (cost of non-conformance).

221
Q

What is Point of Total Assumption (PTA)?

A

The total cost on a Fixed Price Incentive Fee (FPIF) contract, above which the seller bears all cost overruns.

222
Q

Define Duration (DU or DUR).

A

The total number of work periods (days, weeks, etc.), excluding holidays or other nonworking periods, required to complete an activity or work breakdown structure component.

223
Q

What are the two pillars of Lean?

A

The two pillars of Lean are: - Continuous Improvement (or kaizen) - Respect for People

224
Q

What are Resource Requirements?

A

The types and quantities of resources required for each activity in a work package.

225
Q

What is Scope Creep?

A

The uncontrolled expansion to product or project scope without adjustments to time, cost, and resources.

226
Q

What is a Calendar Unit?

A

The unit of time used in scheduling a project. Example hours, days, weeks, months, etc.

227
Q

The verbal elements of a speech outside of spoken words, such as pitch, tone, rate, etc., are known as ______________ factors.

A

The verbal elements of a speech outside of spoken words, such as pitch, tone, rate, etc., are known as <u>paralingual</u> factors.

228
Q

Give an example of Start-to-start (SS) dependency.

A

The vote counting (successor) in the polls can begin as soon as the polling begins (predecessor).

229
Q

Why is Cost Management Plan an input to Identify Risks process?

A

The way costs are managed on the project could in itself be a source of risk on the project.

230
Q

What is the 100% rule when developing the WBS?

A

The work at the lowest levels of the WBS must add up to 100% of the project scope.

231
Q

What is a Work Package?

A

The work defined at the lowest level of the work breakdown structure for which cost and duration are estimated and managed.

232
Q

What is Conformance Work?

A

The work done to compensate for imperfections that prevent organizations from completing planned activities correctly as essential first-time work. It consists of actions that are related to prevention and inspection.

233
Q

What is Nonconformance Work?

A

The work done to deal with the consequences of errors and failures in doing activities correctly on the first attempt. In efficient quality management systems, the amount of nonconformance work will approach zero.

234
Q

What is the X in DfX?

A

The X in DfX can be different aspects of product development, such as reliability, deployment, assembly, manufacturing, cost, service, usability, safety, and quality.

235
Q

TOC

A

Theory of Constraints

236
Q

What are the two theories advocated by Douglas McGregor to categorize workers?

A

Theory X and Theory Y

237
Q

What is/are the Project Procurement Management process(es) under the Closing Process Group?

A

There is no Project Procurement Management process under the Closing Process Group.

238
Q

What is the purpose of Bidder Conferences?

A

They are used to ensure that all prospective sellers have a clear and common understanding of the procurement (both technical and contractual requirements), and that no bidders receive preferential treatment.

239
Q

How do Benefit Measurement methods of project selection work?

A

They compare the projects based on features and benefits.

240
Q

How do Constrained Optimization methods of project selection work?

A

They use complex mathematical models and algorithms to predict the success of the project.

241
Q

What is another name for Negative Risk?

A

Threat

242
Q

Threat vs Opportunity

A

Threat (or negative risk) is a risk of a loss, whereas Opportunity (or positive risk) is a risk of a gain.

243
Q

When does an agile team capture lessons learned?

A

Throughout the project

244
Q

In which part of the project life cycle is Monitor Communications process performed?

A

Throughout the project life cycle

245
Q

In a CPIF contract, which is the least important constraint?

A

Time

246
Q

In an FPIF contract, which is the least important constraint?

A

Time

247
Q

T&M

A

Time And Material

248
Q

Which type of contract should the buyer opt for if he wants the work to start soon?

A

Time and Material (T & M)

249
Q

If a project management team wants to hire the services of a risk management consultant on the project, which type of contract would be most suited for their requirement?

A

Time and Material (T&M)

250
Q

In which type of contract would you use a Request for Quotation (RFQ)?

A

Time and Material (T&M)

251
Q

Which type of contract would be most suitable when a project team needs personnel to augment its staff?

A

Time and Material (T&M)

252
Q

What is Contingency Reserve?

A

Time or money allocated in the schedule or cost baseline for known risks (or “known-unknowns”) with active response strategies. It is also known as Contingency Allowance.

253
Q

What is the purpose of procurement negotiations at the time of conducting procurements?

A

To clarify the structure, requirements, and other terms of the purchases so that mutual agreement can be reached prior to signing the contract.

254
Q

Why is Cost-Benefit Analysis done in quality planning?

A

To compare the cost of quality activities with the expected benefit. For example, if a quality improvement activity costs $10,000 and results in only a marginal increase in quality, then it’s probably not worth doing.

255
Q

What is the purpose of using Simulation technique in quantitative risk analysis?

A

To determine the likelihood of achieving specific schedule or cost targets of the project.

256
Q

Why should Perform Quantitative Risk Analysis process be repeated after Plan Risk Responses process?

A

To determine whether the overall project risk has satisfactorily decreased as a result of planned responses.

257
Q

What is the purpose of Project Schedule Network Diagrams?

A

To develop (project) schedule.

258
Q

What is the only way for a project management practitioner to resolve conflict of interest?

A

To disclose the conflict to the parties affected by the conflict and let them make a decision on how he/she should proceed.

259
Q

What is the role of an Operations Manager in an enterprise?

A

To manage business operations (such as R&D, design, manufacturing, testing, maintenance, customer service, etc.) efficiently.

260
Q

What is the purpose of a Probability and Impact Matrix?

A

To rate risks (low, moderate, high).

261
Q

What are Screening Systems used for in procurement management?

A

To shortlist sellers (eliminate those who do not meet certain minimum requirements).

262
Q

What is the primary function of a PMO?

A

To support project managers.

263
Q

What is the purpose of a spike in agile projects?

A

To test a technological approach and stop as soon as it’s clear.

264
Q

TCPI

A

To-Complete Performance Index

265
Q

What is the ratio of Work Remaining to Funds Remaining known as?

A

To-Complete Performance Index (TCPI)

266
Q

Tolerance vs Control Limits

A

Tolerances are used to determine whether individual components are acceptable, whereas Control Limits are used to control the process. Control Limits usually fall within Tolerance Limits.

267
Q

Top project managers spend about 90% of their time on a project in _____________.

A

Top project managers spend about 90% of their time on a project in <u>communicating</u>.

268
Q

What are Analogous estimates also known as?

A

Top-down estimates

269
Q

Which tool would you use to graphically represent the results of Sensitivity Analysis?

A

Tornado Diagram

270
Q

What is the formula for Total Float?

A

Total Float LF - EF or Total Float LS - ES where LF is Late Finish, EF is Early Finish, LS is Late Start and ES is Early Start. Either formula can be used.

271
Q

Total Float belongs to the ____________, whereas Free Float belongs to the ____________.

A

Total Float belongs to the <u>project</u>, whereas Free Float belongs to the <u>individual activities</u>.

272
Q

Total Float vs Free Float

A

Total Float is the amount of time an activity can be delayed without delaying the project, whereas Free Float is the amount of time an activity can be delayed without delaying any successor activity.

273
Q

What is the total power of a project manager?

A

Total Power Positional Power + Personal Power

274
Q

TPM

A

Total Productive Maintenance

275
Q

TQM

A

Total Quality Management

276
Q

What are project’s Triple Constraints?

A

Traditionally, this term referred to project’s Scope, Time and Cost. Later it was expanded to include Quality, Risk, and Customer Satisfaction. A change to one of these factors must be evaluated for impact to all the other factors, as part of integrated change control process.

277
Q

If an organization decides to use a contract in order to reduce a project risk, what kind of risk response strategy are they using?

A

Transfer

278
Q

What is the term to describe leaders who empower followers through idealized attributes and behaviors?

A

Transformational

279
Q

Which graphical analysis technique examines project performance over time to determine if performance is improving or deteriorating?

A

Trend Analysis

280
Q

What are the common forms of probability distributions used in Quantitative Risk Analysis?

A

Triangular, normal, lognormal, beta, uniform, or discrete distributions.

281
Q

A project schedule network diagram is always drawn from left to right. True or False?

A

True.

282
Q

Agreements are an input to Determine Budget. True or False?

A

True.

283
Q

Agreements are an input to Identify Stakeholders. True or False?

A

True.

284
Q

Before the baselines are established, changes are not required to be formally controlled by the Perform Integrated Change Control process. True or False?

A

True.

285
Q

Change Log is an input to Manage Stakeholder Engagement. True or False?

A

True.

286
Q

Communication preferences may vary with age of the person. True or False?

A

True.

287
Q

Configuration Management Plan is a subsidiary of the Project Management Plan. True or False?

A

True.

288
Q

Configuration Management System is a part of the Project Management System. True or False?

A

True.

289
Q

Cost Baseline is an input to Perform Quantitative Risk Analysis. True or False?

A

True.

290
Q

Cost Forecasts are an output of Control Costs. True or False?

A

True.

291
Q

Diversity is an asset for organizations. True or False?

A

True.

292
Q

Expert Judgment is a Tool and Technique in the Collect Requirements process. True or False?

A

True.

293
Q

Issue Log can be updated in the Monitor Communications process. True or False?

A

True.

294
Q

Net Present Value calculations may be included in the Benefits Management Plan. True or False?

A

True.

295
Q

Procurement Documentation are an input to Control Procurements. True or False?

A

True.

296
Q

Procurement Documentation is an input to Conduct Procurements. True or False?

A

True.

297
Q

Project Charter is an input to Define Scope. True or False?

A

True.

298
Q

Project Charter is an input to Develop Project Management Plan. True or False?

A

True.

299
Q

Project Charter is an input to Plan Risk Management. True or False?

A

True.

300
Q

Project Communications are an input to Monitor Communications. True or False?

A

True.

301
Q

Project phases can overlap. True or False?

A

True.

302
Q

Project Team Assignments are an output of Acquire Resources. True or False?

A

True.

303
Q

Project teams should identify and manage both event-based risks and non-event risks. True or False.

A

True.

304
Q

Projects are how businesses implement changes. True or False?

A

True.

305
Q

Requirements Management Plan is an input to Collect Requirements. True or False?

A

True.

306
Q

Resource Breakdown Structure is an output of Estimate Activity Resources. True or False?

A

True.

307
Q

Resource Requirements are an input to Estimate Costs. True or False?

A

True.

308
Q

Risk Register is an input to Plan Quality Management. True or False?

A

True.

309
Q

Schedule Baseline is an output of Develop Schedule. True or False?

A

True.

310
Q

Scope Baseline is an input to Define Activities. True or False?

A

True.

311
Q

Stakeholder Register is an input to Perform Qualitative Risk Analysis. True or False?

A

True.

312
Q

Stakeholder satisfaction is one of the key project objectives. True or False?

A

True.

313
Q

The project management processes are repeated in each phase of a project. True or False?

A

True.

314
Q

Verified Deliverables are an input to Validate Scope. True or False?

A

True.

315
Q

WBS is a communication tool on a project. True or False?

A

True.

316
Q

Work Performance Data are an input to Control Quality. True or False?

A

True.

317
Q

Work Performance Data is an output of an Executing process, and an input to most Monitoring and Controlling processes. True or False?

A

True.

318
Q

Work Performance Information is an output of Control Scope. True or False?

A

True.

319
Q

Work Performance Reports are an input to Manage Team. True or False?

A

True.

320
Q

Work Performance Reports are an input to Monitor Risks. True or False?

A

True.

321
Q

A project manager may be involved in benefits realization activities even after the project is complete. True or False?

A

True. A project manager may be involved in follow-on activities related to realizing business benefits from the project.

322
Q

Change control process is mandatory for every project. True or False.

A

True. Change is inevitable; therefore, some type of change control process is mandatory for every project.

323
Q

Contracts are risk mitigation tools. True or False?

A

True. Contracts or agreements may be used to transfer liability for specified risks to another party.

324
Q

Control Charts are used to track repetitive activities like manufacturing lots. They can also be used to track the project management processes. True or False?

A

True. Control Charts can be used to determine whether project management processes, such as cost and schedule variances, volume, and frequency of scope changes, are in control.

325
Q

Management Reserves are not included in the Cost Baseline. True or False?

A

True. Cost Baseline includes Contingency Reserves, but excludes Management Reserves.

326
Q

Padding duration estimates is unethical. True or False?

A

True. Padding is the amount of unreasonable extra time added to the estimate, just to feel confident with the estimate.

327
Q

Management Reserves are NOT part of the Project Cost Baseline. True or False?

A

True. Project Cost Baseline includes Project Cost Estimates and Contingency Reserves. Project Cost Budget is determined by adding Management Reserves to Project Cost Baseline.

328
Q

The Critical Path can have a negative float. True or False?

A

True. The Critical Path can have a positive, zero or negative float.

329
Q

What type of team members are ideal for an agile team - I-shaped or T-shaped?

A

T-shaped

330
Q

What is meant by T-shaped skills?

A

T-shaped skills mean deep skills in a preferred functional area, discipline, or specialty, and broad skills outside one’s core area.

331
Q

What is Variability Risk?

A

Uncertainty about some key characteristics of a planned event or activity or decision.

332
Q

What is Ambiguity Risk?

A

Uncertainty arising from lack of knowledge or understanding of certain aspects of the project.

333
Q

What do the schedule and cost probability distributions represent?

A

Uncertainty in schedule or cost estimates

334
Q

What are unknown unknowns?

A

Unknown unknowns are things we do not even know that we don’t know. These are risks that are not even identified during risk management. Unknown unknowns are managed by using Management Reserves.

335
Q

What is the output of Perform Qualitative Risk Analysis?

A

Updates to Assumptions Log, Issue Log, Risk Register and Risk Report

336
Q

What tool is widely used with agile methods to collect user requirements?

A

User stories

337
Q

What is the formula for Variance at Completion (VAC)?

A

VAC BAC - EAC

338
Q

Verified Deliverables are an input to this process and Accepted Deliverables an output. Which process is this?

A

Validate Scope

339
Q

Which process formalizes the acceptance of completed project deliverables?

A

Validate Scope

340
Q

What are other common names for Value Analysis?

A

Value Engineering or Value Management

341
Q

What is Future Value (FV)?

A

Value of an asset at a specific date in future.

342
Q

What is the formula for activity variance?

A

Variance σ^2 or ((P - O) / 6) ^ 2 where σ is the standard deviation, P the pessimistic estimate and O the optimistic estimate of the activity.

343
Q

Which technique is used for measuring deviation from baseline plans in order to determine the need for preventive or corrective actions?

A

Variance Analysis

344
Q

Variance Analysis vs Value Analysis

A

Variance Analysis is a project management technique to assess the magnitude of variance (in scope, time, cost, quality, etc.) from the baseline and determine whether corrective or preventive action is required. Value analysis is a product analysis technique to perform the same work at lesser cost.

345
Q

VAC

A

Variance at Completion

346
Q

Why are Work Performance Reports an input to the Monitor Risks process?

A

Variance data, earned value measurements and forecasting data from the Performance Reports are monitored to look for symptoms or warning signs of risks.

347
Q

What are Analytical Techniques?

A

Various techniques used to evaluate, analyze, or forecast potential outcomes based on possible variations of project or environmental variables and their relationships with other variables. Examples includes Root Cause Analysis, Regression Analysis, and Reserve Analysis.

348
Q

Verification vs Validation

A

Verification checks whether the product was built right. Validation checks whether the right product was built. Verification is usually an internal process, whereas Validation is external. Verification usually takes place before Validation.

349
Q

What comes as an output from Control Quality and goes as an input to Validate Scope?

A

Verified Deliverables

350
Q

Verified Deliverable vs Accepted Deliverable

A

Verified deliverables are the deliverables that have been checked for correctness by the Control Quality process. They are an input to Validate Scope process. Accepted Deliverables are the deliverables that meet the acceptance criteria and have been formally signed off by the customer through the Validate Scope process.

351
Q

Who proposed the Expectancy Theory?

A

Victor Vroom

352
Q

VOC

A

Voice of the Customer

353
Q

VUCA

A

Volatility, Uncertainty, Complexity, Ambiguity

354
Q

Which quality expert developed the 14 steps to Total Quality Management?

A

W. Edwards Deming

355
Q

What is a Trigger Condition?

A

Warning sign or symptom that indicates that a risk is about to occur.

356
Q

Name any 3 sources of waste in Lean Manufacturing.

A

Waste results from overburdened workers, bottlenecks, waiting, handoff, overproduction, wishful thinking, task-switching, defects, and information scatter.

357
Q

What are Predictive life cycles also known as?

A

Waterfall life cycles

358
Q

Which tool is used to categorize risks by area of project affected?

A

WBS can be used to categorize risks by area of project affected.

359
Q

WBS is a _____________-oriented hierarchical decomposition of the statement of work of the project.

A

WBS is a <u>deliverable</u>-oriented hierarchical decomposition of the statement of work of the project.

360
Q

List the project management processes that use WBS as an input.

A

WBS is not an input to any process! However, Scope Baseline, which includes the Project Scope Statement, WBS, and WBS Dictionary, is an input to several processes such as Define Activities, Estimate Costs, Determine Budget, Identify Risks, and Perform Qualitative Risk Analysis.

361
Q

How do we deal with the outcome of Residual Risks?

A

We put contingency plans in place.

362
Q

What should we do with people with whom we have a conflict or disagreement?

A

We should approach them directly and try to resolve the conflict or disagreement.

363
Q

Is providing accurate information in a timely manner something that is mandatory or something that we should aspire to do?

A

We should aspire to provide accurate information in a timely manner.

364
Q

What should we do when we come across individuals who knowingly make false allegations against others?

A

We should pursue disciplinary action against them.

365
Q

Weighted Average (PERT) vs Simple Average Three-Point Estimating

A

Weighted Average (PERT) estimate uses Beta distribution whereas Simple Average uses Triangular distribution to calculate the duration or cost estimate. Weighted Average formula is, E (O + 4M + P) / 6 and Simple Average formula is E (O + M + P) / 3, where O is the Optimistic, M is the Most Likely and P is the Pessimistic estimate.

366
Q

Weighting System vs Screening System

A

Weighting systems are used to rank sellers according to the score assigned to them based on various criteria. Screening systems are used to shortlist sellers, i.e. eliminate those who do not meet certain minimum requirements.

367
Q

What does the Herzberg’s theory say about Motivating Factors?

A

What motivates people is the work itself.

368
Q

When is a process considered to be “out of control”?

A

When a data point falls outside the control limits or when seven consecutive data points fall on the same side of the mean (either above or below the mean) on a control chart.

369
Q

When are procurements closed?

A

When all the work on a contract is completed or the contract is terminated before completing the work.

370
Q

When is quality management most effective?

A

When quality is incorporated into the planning and designing of the project and product, and when organizational culture is aware and committed to quality.

371
Q

When is price the main source selection criterion?

A

When the product, service or result is readily available in the market from a number of sellers.

372
Q

When is Contract an input to the Develop Project Charter process?

A

When the project is being done for an external customer.

373
Q

Under what circumstances is a project terminated?

A

When the project’s objectives will not or cannot be met, or when the need for the project no longer exists.

374
Q

When is it particularly important to use a RACI matrix?

A

When the team consists of internal and external resources (to ensure clear divisions of roles and expectations).

375
Q

When is Analogous estimating used?

A

When there is limited amount of detailed information on the project.

376
Q

What is the relationship between Accountability, Authority and Responsibility?

A

With Authority and Responsibility comes Accountability. Accountability Authority + Responsibility

377
Q

Which type of conflict resolution is usually the best when tensions and emotions are high?

A

Withdrawal

378
Q

WBS

A

Work Breakdown Structure

379
Q

What is Parkinson’s Law?

A

Work expands to fill the time available for its completion.

380
Q

What is the term for the planned work contained at the lowest level of the WBS?

A

Work Package

381
Q

What is the output of the Direct and Manage Project Work process that goes as an input to the Control Costs process?

A

Work Performance Data

382
Q

Work Performance Data is an ____________ (Input or Output) of Executing processes.

A

Work Performance Data is an <u>output</u> of Executing processes. Note: Work Performance Data is an output of the Direct and Management Project Work process, which integrates the performance data from all the other Executing processes.

383
Q

Work Performance Information is an output of ___________ Process Group.

A

Work Performance Information is an output of <u>Monitoring and Controlling</u> Process Group.

384
Q

Work Performance Data (WPD) vs Work Performance Information (WPI)

A

WPD are the raw observations or measurements gathered as work on the project is carried out (e.g. percent completion, quality/technical performance measures, activity start/finish dates, no. of change requests/defects, actual costs/durations, etc.) WPD is processed and analyzed to generate WPI (e.g. status of deliverables/change requests, forecasts, EV measures - SV, CV, SPI, CPI, etc.).

385
Q

What are Questionnaires?

A

Written sets of questions designed to quickly accumulate information from a large number of respondents.

386
Q

What are the 5 values of Extreme Programming (XP)?

A

XP is based on values of simplicity, communication, feedback, courage, and respect.

387
Q

Can the Point of Total Assumption (PTA) be higher (or more) than the Ceiling Price?

A

Yes

388
Q

Can the Point of Total Assumption (PTA) be lower (or less) than the Target Price?

A

Yes

389
Q

Can the seller be already in losses (profit below zero) at the Point of Total Assumption (PTA)?

A

Yes

390
Q

Is the Close Project or Phase process needed if the project is terminated before completion?

A

Yes, it is used to investigate and document the reason for project termination.

391
Q

Can a schedule network have more than one Near-Critical Path?

A

Yes. Any path with low total float is a near critical path. A schedule network may have more than one path with low total float.

392
Q

What is the Schedule Variance (SV) at the end of a completed project?

A

Zero

393
Q

In timeboxed iterations, the duration is fixed but the scope can vary. True or False?

A

TRUE

394
Q

According to Hersey and Blanchard, what are the four basic situational leadership styles?

A
  • S1. / Directing - S2. Selling / Coaching - S3. Participating / Supporting - S4. Delegating / Observing
395
Q

According to McClelland’s theory, what are the characteristics of people with need for achievement?

A
  • Seek Recognition - Prefer challenging but achievable Work - Avoid low-Risk and High-Risk situation - Prefer to Work alone or with other High-achievers
396
Q

Approved Change Requests are an input to these processes and Change Requests are an output. Which processes are these?

A
  • Direct and Manage project Work - Control quality - Control Procurements
397
Q

Change Log is an output of which process(es)?

A
  • perform Integrated Change Control - Manage Stakeholder engagement
398
Q

Deliverables produced in the Direct and Manage Project Work process are an input to which process?

A
  • Manage project knowledge - Control quality
399
Q

Give 3 examples of Alternative Dispute Resolution (ADR) techniques.

A
  • Negotiation - Mediation - Arbitration
400
Q

Give 3 examples of Cost of Conformance.

A
  • quality Training - quality planning - quality Systems
401
Q

Give 3 examples of Cost of Non-Conformance.

A
  • Rework - Scrap - Warranty Costs
402
Q

Give 3 examples of Direct Costs?

A
  • Labor Costs - Materials Costs - Equipment rental Costs
403
Q

Give 3 examples of Interactive Communication.

A
  • Face-to-Face meetings - Teleconferences - Phone calls
404
Q

Give 4 examples of Indirect Costs?

A
  • management Costs - General administration Costs - Building rental - Utility Costs
405
Q

Give 5 examples of Enterprise Environmental Factors.

A
  • Organizational culture - industry standards - Existing infrastructure - Existing human Resources - Marketplace conditions
406
Q

Give at least 3 categories of requirements.

A
  • business Requirements - Stakeholder Requirements - Solution (or Product) Requirements - Transition Requirements - project Requirements - quality Requirements
407
Q

Give at least 3 examples of Pull Communication.

A
  • Web sites - E-Learning Tools - Document repositories
408
Q

Give at least 3 examples of Push Communication.

A
  • Letters - reports - E-mails - Press releases
409
Q

Give at least three examples of risk avoidance.

A
  • Extend the Schedule - Reduce Scope - Cancel the project
410
Q

Give at least three examples of risk mitigation.

A
  • Conducting more tests - Prototyping - Designing redundancy into a System
411
Q

Give at least three examples of risk transference tools.

A
  • Insurance - Performance bonds - Warranties - Agreements
412
Q

Give examples of a few different types of stakes that stakeholders can have.

A
  • Interest - Rights (Legal or moral Rights) - Ownership - knowledge - Contribution
413
Q

Give examples of Business Risk.

A
  • Competitor Activities - Bad weather - Inflation - Recession - Customer Response - Availability of Resources
414
Q

Give examples of External Failure Costs.

A
  • Liabilities - Warranty Work - Lost business
415
Q

Give some examples of Personnel Assessment Tools that a project manager or project team can use.

A
  • Attitudinal surveys - specific Assessments - Structured Interviews - ability tests - Focus groups
416
Q

Give some examples of project stakeholders.

A
  • Customers - End users - sponsor - project management Office (PMO) - project Managers - project team - Functional Managers - Vendors
417
Q

Give three examples of formal written communication.

A
  • a Legal notice - a Change request - a tender
418
Q

Give three examples of intangible elements of business value for business driven organizations.

A
  • Goodwill
  • Brand Recognition
  • Trademarks
419
Q

Give three examples of tangible elements of business value for business driven organizations.

A
  • Monetary Assets - Fixtures - Stockholder equity
420
Q

Give three examples of techniques to crash a schedule.

A
  • Applying additional man-power to a critical path activity. - Hiring new machinery to expedite a critical path activity. - Devising a more efficient way to perform a critical path activity.
421
Q

Give two examples of business documents used on projects?

A
  • business Case - benefits management Plan
422
Q

Give two examples of formal verbal communication.

A
  • a presentation - a speech
423
Q

Give two examples of informal written communication.

A
  • An email - a hand-Written note
424
Q

How does senior management support projects?

A
  • As project sponsor - In setting objectives and priorities - In planning the project - In resolving conflicts
425
Q

How does senior management support projects? (4)

A
  • As project sponsor - In setting objectives and priorities - In planning the project - In resolving conflicts
426
Q

In order to be the most effective, project managers need to have a balance of which three skill sets?

A
  • technical project management - Leadership - business intelligence (Strategic and business management)
427
Q

In which organizational structure(s), the project has full-time administrative staff?

A
  • project-oriented - Strong Matrix
428
Q

In which process(es) are you likely to use Affinity Diagrams?

A
  • Collect Requirements
  • Manage quality
429
Q

In which process(es) is Cost of Quality considered?

A
  • Estimate Costs - Plan quality management
430
Q

In which process(es) is Critical Path Method (CPM) used?

A
  • Develop Schedule - Control Schedule
431
Q

In which process(es) would you employ Networking?

A
  • Manage project knowledge - Manage Communications - Manage Stakeholder engagement
432
Q

In which process(es) would you use Contract Management Systems?

A
  • Plan procurement management - Conduct Procurements
433
Q

In which processes are inspections performed?

A
  • Validate Scope - Control quality - Control Procurements
434
Q

In which processes are simulations and modeling techniques used?

A
  • Develop Schedule - perform Quantitative Risk Analysis
435
Q

In which processes are you likely to use Focus Groups?

A
  • Develop project Charter - Develop project management Plan - Collect Requirements
436
Q

In which processes do you apply leads and lags?

A
  • Sequence Activities - Develop Schedule - Control Schedule
437
Q

List any 3 data gathering techniques that can be used to identify project and product requirements.

A
  • Brainstorming - Interviews - Focus groups - Questionnaires and surveys - Benchmarking
438
Q

List at least 4 Product Analysis techniques.

A
  • Product breakdown - Systems Analysis - Requirements Analysis - Systems engineering - value engineering - value Analysis
439
Q

List the processes that have Resource Calendars as output.

A
  • Control Schedule - Acquire Resources - Develop team - Conduct Procurements
440
Q

List the processes that use Resource Breakdown Structure as an input.

A
  • Manage project knowledge - Estimate Activity Durations - Control Resources
441
Q

List the steps to build project resilience in dealing with emergent risks.

A
  • Include Budget and Schedule contingency for emergent Risks - Flexible project processes, including Strong Change management - Empowering project team - Frequent Review of warning signs - Stakeholder buy-In to adjust Scope and strategy In Response to emergent Risks
442
Q

List the various methods of reaching a group decision.

A
  • Voting - Autocratic Decision making - Multicriteria Decision Analysis
443
Q

Name all the Project Communications Management processes.

A
  • Plan Communications management
  • Manage Communications
  • Monitor Communications
444
Q

Name all the Project Cost Management processes.

A
  • Plan Cost management - Estimate Costs - Determine Budget - Control Costs
445
Q

Name all the Project Integration Management processes.

A
  • Develop project Charter - Develop project management Plan - Direct and Manage project Work - Manage project knowledge - Monitor and Control project Work - perform Integrated Change Control - Close project or Phase
446
Q

Name all the Project Procurement Management processes.

A
  • Plan procurement management - Conduct Procurements - Control Procurements
447
Q

Name all the Project Quality Management processes.

A
  • Plan quality management - Manage quality - Control quality
448
Q

Name all the Project Resource Management processes.

A
  • Plan Resource management - Estimate Activity Resources - Acquire Resources - Develop team - Manage team - Control Resources
449
Q

Name all the Project Risk Management processes.

A
  • Plan Risk management - Identify Risks - perform Qualitative Risk Analysis - perform Quantitative Risk Analysis - Plan Risk Responses - Implement Risk Responses - Monitor Risks
450
Q

Name all the Project Schedule Management processes.

A
  • Plan Schedule management
  • Define Activities
  • Sequence Activities
  • Estimate Activity Durations
  • Develop Schedule
  • Control Schedule
451
Q

Name all the Project Scope Management processes.

A
  • Plan Scope management - Collect Requirements - Define Scope - Create WBS - Validate Scope - Control Scope
452
Q

Name all the Project Stakeholder Management processes.

A
  • Identify Stakeholders - Plan Stakeholder engagement - Manage Stakeholder engagement - Monitor Stakeholder engagement
453
Q

Name any 3 interpersonal and team skills used for helping teams and individuals accomplish project activities?

A
  • Active Listening - conflict management - Emotional intelligence - Facilitation - Leadership - Meeting management
454
Q

Name any five tools and techniques of the Develop Schedule process.

A
  • Schedule Network Analysis - critical path Method - Resource Optimization - Data Analysis - Leads and Lags - Schedule Compression - PMIS - Agile Release planning
455
Q

Name any one data analysis tool used in the Identify Stakeholders process.

A
  • Stakeholder Analysis - Document Analysis
456
Q

Name any three estimation techniques used for estimating activity durations?

A
  • Analogous Estimating - Parametric Estimating - Three-Point Estimating - Bottom-Up Estimating
457
Q

Name any three leadership skills that a project manager should possess?

A
  • Negotiation - Resilience - communication - Problem solving - critical thinking - Interpersonal skills
458
Q

Name at least 2 processes which use Work Performance Reports as an input.

A
  • perform Integrated Change Control - Manage team - Manage Communications - Monitor Risks
459
Q

Name at least 3 interpersonal and team skills to manage a project team.

A
  • conflict management - Decision making - Emotional intelligence - Influencing - Leadership
460
Q

Name at least 3 tools and techniques used in the Determine Budget process.

A
  • Expert Judgment
  • Cost Aggregation
  • Reserve Analysis
  • Historical Information Review
  • Funding Limit Reconciliation
  • Financing
461
Q

Name at least 3 tools and techniques used in the Develop Team process.

A
  • Interpersonal and team skills - Training - Virtual teams - meetings - Colocation - Recognition and rewards - Individual and team Assessments
462
Q

Name at least three Executing processes that can result in change requests.

A
  • Direct and Manage project Work - Manage quality - Acquire Resources - Manage team - Implement Risk Responses - Conduct Procurements - Manage Stakeholder engagement
463
Q

Name the 2 data representation techniques that can be used to collect requirements.

A
  • Affinity Diagrams - Mind Mapping
464
Q

Name the different powers of a Project Manager.

A
  • Legitimate (or Formal)
  • Reward
  • Punitive (or Coercive)
  • Expert
  • Referent
465
Q

Name the five different types of development life cycles.

A
  • Predictive - Iterative - Incremental - Adaptive (Agile, Iterative, or Incremental) - Hybrid (Predictive and Adaptive)
466
Q

Name the important communication skills for a project manager?

A
  • Listening - Questioning - Educating - Fact-finding - setting and managing expectations - Persuading - Negotiating - resolving conflict
467
Q

Name the Process Groups which have the Project Management Plan or one of its subsidiary plans as an input to all their processes.

A
  • Executing - Monitoring and controlling - Closing
468
Q

Name the Project Cost Management process(es) under the Planning Process Group.

A
  • Plan Cost management - Estimate Costs - Determine Budget
469
Q

Name the Project Integration Management process(es) under the Executing Process Group.

A
  • Direct and Manage project Work - Manage project knowledge
470
Q

Name the Project Integration Management process(es) under the Monitoring and Controlling Process Group.

A
  • Monitor and Control project Work - perform Integrated Change Control
471
Q

Name the Project Resource Management process(es) under the Executing Process Group.

A
  • Acquire Resources - Develop team - Manage team
472
Q

Name the Project Resource Management process(es) under the Planning Process Group.

A
  • Plan Resource management - Estimate Activity Resources
473
Q

Name the Project Risk Management process(es) under the Planning Process Group.

A
  • Plan Risk management - Identify Risks - perform Qualitative Risk Analysis - perform Quantitative Risk Analysis - Plan Risk Responses
474
Q

Name the Project Schedule Management processes under the Planning Process Group.

A
  • Plan Schedule management - Define Activities - Sequence Activities - Estimate Activity Durations - Develop Schedule
475
Q

Name the Project Scope Management process(es) under the Monitoring and Controlling Process Group.

A
  • Validate Scope - Control Scope
476
Q

Name the Project Scope Management processes under the Planning Process Group.

A
  • Plan Scope management - Collect Requirements - Define Scope - Create WBS
477
Q

Name the two Initiating processes.

A
  • Develop project Charter - Identify Stakeholders
478
Q

Name three common strategic frameworks suitable for identifying sources of overall project risk.

A
  • PESTLE (political, Economic, Social, technological, Legal, Environmental)
  • TECOP (technical, Environmental, commercial, Operational, political)
  • VUCA (volatility, uncertainty, complexity, Ambiguity)
479
Q

Name three hierarchical charts used in Project Resource Management?

A
  • Work breakdown structure (WBS) - Organizational breakdown structure (OBS) - Resource breakdown structure (RBS)
480
Q

Name two processes which use Three-Point Estimating?

A
  • Estimate Activity Durations
  • Estimate Costs
481
Q

Pre-Assignment and Negotiation are two tools and techniques of the Acquire Resources process. Name at least one more technique of this process.

A
  • Virtual teams - Multicriteria Decision Analysis
482
Q

Quality Metrics are an input to which process(es)?

A
  • Manage quality - Control quality
483
Q

Root Cause Analysis is usually performed in which processes?

A
  • Monitor and Control project Work - Manage quality - Control quality - Identify Risks - Plan Stakeholder engagement - Manage Stakeholder engagement
484
Q

What are Agreements also referred to as?

A
  • Contracts - Purchase orders - Memoranda of Agreements (MOAs) - Service Level Agreements (SLAs)
485
Q

What are bid documents comprised of?

A
  • procurement statement of Work - description of Response format - Any other contractual Requirements
486
Q

What are Bidder conferences also known as?

A
  • Contractor conferences - Vendor conferences - Pre-Bid conferences
487
Q

What are Inspections also known as?

A
  • reviews - Product reviews - Walkthroughs
488
Q

What are Kill Points also referred to as?

A
  • Stage Gates - Phase Gates - Phase Exits - Decision Gates
489
Q

What are some of the strategic considerations or triggers for authorizing a project?

A
  • Market demand - Strategic opportunity/business need - Social need - Environmental consideration - Customer request - new Technology - Legal requirement
490
Q

What are some of the strategic considerations or triggers for authorizing a project? (7 MSSECNL)

A
  • Market demand - Strategic opportunity/business need - Social need - Environmental consideration - Customer request - new Technology - Legal requirement
491
Q

What are the 2 categories of product requirements?

A
  • Functional Requirements (features and functions) - Non-Functional Requirements (Performance, security, reliability, etc.)
492
Q

What are the 2 key inputs from stakeholder management processes to the Manage Communications process?

A
  • Stakeholder Register - Stakeholder engagement Plan
493
Q

What are the 3 pillars of empirical process control in the Scrum framework?

A
  • Transparency - Inspection - Adaptation
494
Q

What are the 3 primary forms of organizational structures?

A
  • Functional - Matrix - Projectized
495
Q

What are the 3 types of communication methods?

A
  • Interactive communication - Push communication - Pull communication
496
Q

What are the 3 types of Matrix organizations?

A
  • Weak Matrix - Balanced Matrix - Strong Matrix
497
Q

What are the 4 core values that are most important to the project management community?

A
  • Responsibility - Respect - Fairness - Honesty
498
Q

What are the 4 D’s of Delegation?

A
  • Drop (what can be dropped?) - Delay (what can be delayed?) - Delegate (what can be delegated?) - Do (what must I do?)
499
Q

What are the 4 main aspects of any Configuration Management System?

A
  • Configuration Identification
  • Configuration Control
  • Configuration Status Accounting
  • Configuration Verification and Audit
500
Q

What are the 5 key components of a basic communication model?

A
  • Encode - Transmit message - Decode - Acknowledge - Feedback/Response