DCO & Compulsory Purhcase Flashcards
What is NSIPS
Nationally Significnat Infrastructure projects
What is the main legislation for DCO
The Planning act 2008(section 14)
What are the 6 stages of DCO
Pre-application, acceptance, pre-examination, examination, decision and post decision
How does pre-examination work
One acceptredofr examination, the public are able to register wiht planing inspectorate to provide a written summary of their veiws. There are relevany respresentations. When the period has condluced, the applicatnt must certify that it has complied wihtt eh statutory requirements for giving notice of the accepted application . The examinig authortity will then set out the various stages of the examination including the periods allowed for submission of further written evidence and any hearing that the examining authortiyu will hold. Applicants and interested parties must comply with the timetable
In the pre-application are the two consultations
Perscribed persons (eh. forestry commission, parish councils, forestry commissions etc and the local community
What must the applicant prepare after getting thelocal resoonse
Statement of community consultation
Under section 48 of the Planning Act, how must the applicant publish in a notice of the proposed application
At least two successive weeks in one or more local papers in teh vicinity whcih the land is situated ad the propoed applicated relates ONe in a national newspaper adn once in the london gazette
What section is acceptance related too?
s55
How does the pre-examnation requirements work who examines the work
Examining authority will examine planning application after the receipt of planning application. They look at dates, written representtions, the period whihc the applicant must agree the statmetn
How does the examintion procees work
it is 6 month period commencing on the date of the prelimanary meeting
What letter is the examination process in accordance with
letter 8
How long do the examining authority have for examining to prepare tothe secretary of state in the decision process and what do they agree
three months- and will either procees a development cosnent order or refuse application
What is the timeline post desion for the courts to challenger the cours by judicial review
Six week statutory review
What are the postiives are DCOs
Unified authrorisation procees, certainty of outcome, certanity of timeline, compulsoary purchase powers, BNG is not currently reuired under DCOS
What are the cons of DCOS
Cost, limited flexibitlity to amend the scheme once the application has been submitted less flexibility for post consent alterations, duration from start to finish (can take a long time to get approval_ Scale- only applicable to certain projects under section 35- Nationally signifixvant Infrastructure projecta