D2-Value Driven Delivery Flashcards
Popendieck’s 7 areas of waste
Partially done
extra processes
extra features
task switching
waiting
motion
defects
Value of the project, minus the investment is
ROI
The calculation of a future amount of $$$ in today’s terms given and assumed interest rate and inflation rate
Present value
The calculation of a present amount in today’s terms given and assumed interest rate and inflation rate
Future value
Present value of a revenue stream over a series of periods
Net present value
Calculates the NPV of the cost of the project and when the NPV of the project meets or exceeds the NPV of the benefits of the project
Internal rate of return
The higher the IRR the more ____ the project is
Valuable
% Complete X BAC
Earned value
BAC
Budget at completion
Cost variance of earned value
EV-AC
Schedule variance of earned value
EV-PV
EV/AC
CPI
EV/PV
SPI
CPI
Cost performance index
SPI
Schedule performance index
Estimate at completion
BAC/CPI=EAC
Estimate to complete
EAC-AC=ETC
TCPI to meet BAC
(BAC-EV)/(BAC-AC)
TCPI to meet EAC
(BAC-EV)/(EAC-AC)
TCPI
To complete performance index
KPI examples
rate of progress, remaining work, likely completion date, likely cost remaining.
Risk identification is an _______
iterative activity
High risk items should be adressed
first
Risks can be monitored
in log or burndown
Regulations are
Requirements
Value is
the result - working software
MoSCow
Must Should Could Would like to have, but not this time
This type on analysis identifies must be one dim, attractive, indifferent, revese
Kano