Contract Practice - FINAL Flashcards
What are the reasons for having a contract?
- Clarity in business relationships, agreements, and rights of parties.
- Avoiding potential contract disputes and litigation.
- Preventing misinterpretation of communications and agreements.
- Protecting intellectual property, real property, and asset values.
What are the requirements of a contract?
- Offer by one Party
- Acceptance by the other Party
- Consideration of the Offer
- Intent to form a Contract
- Legality of Contract
- Capacity – Capacity to make agreement
What Elements of contract law are you aware of?
Unfair Contract Terms Act 1977
• This limits the extent that a party can avoid liability for breach of duty
Contracts (Rights of Third Parties Act)
It has significantly changed the traditional principle of privity of contract, whereby obligations can only be enforced by the parties to a contract. It allows a third party to enforce terms of a contract in one of two situations: firstly if the third party is specifically mentioned in the contract as someone authorized to do so, and secondly if the contract “purports to confer a benefit” on him.
In construction, may allow employer to have rights to a contract between the contractor and subcontractor. Covered in NEC3 ECC with Secondary Option Clause Y(UK) 3
Housing Grants Construction and Regeneration Act
a) Fairer payment conditions
b) Improve the cashflow of the industry
c) Ban pay when paid and pay if paid clauses
d) Introduce quicker, easier and more efficient method of dispute resolution
Advise between collateral warranty or use of the unfair contract rights of third parties act?
Act not as specific as CW but CW more costly, whichever is used should be drafted by legal department
What Different standard forms of contract are you aware of?
- JCT 2016 (Joint Contracts Tribunal)
- NEC (New Engineering Contact)
- ECC (Engineering and Construction Contract)
- FIDIC (International Federation of Consulting Engineers)
What are the Differences between NEC3 and JCT?
- 6 main options and secondary options (mix and match approach to distribute risks) JCT uses separate contracts e.g. JCT SBC D&B, SBW W/Q, X/Q etc…
- NEC written in laymen terms easy to understand
- No QS mentioned in NEC only Project Manager
- Tries a more collaborative approach to working “Mutual trust and understanding”
- Programme is a contract document (NEC) 25% of monies due can be withheld if the contractor does not submit an accepted programme
- Variation (JCT)= Compensation Event (CE) (NEC)
- Contractor can notify of a CE called (NCE) must do so within 8 weeks of becoming aware of the situation
- Valuation rules, Bill rates are not binding on CEs.
- CEs built up from first principles called Schedule of Cost Components (SCC) People, Plant, Equipment, Design and Manufacture include a % for O/H
- NEC does not have claims NO direct loss and/or expense
- Loss and/or expense is dealt with in CE
- EOT… again prolongation is dealt with in CE.
- Project Manager by accepting a CE is potentially extending the completion date
- Defects: Defects correction period (normally 2-3 weeks) contractor must “make good” in these time periods (better at dealing with defects than JCT)
- Periods of reply (incentivises the parties to respond to each other) however reality is very administration heavy.
What are the Differences between NEC3 and NEC4?
- Risk Register’ re-named the ‘Early Warning Register’
- Treated acceptance of the contractor’s programme in situations where the project manager does not respond to submission or notification
- Employer becomes ‘Client’, and ‘Works Information’ becomes ‘Scope’. Partnering becomes collaboration.
- An additional procedure includes the identification of opportunities by either party
- The secondary option X16 for retention now includes the optional provision of a retention bond instead of having money retained.
- When EW notified has to be a risk reduction meeting within 7 days
What are delay damages?
- A genuine pre-estimate of the likely loss incurred by the employer should the completion date not be met.
- X7 in NEC3 ECC. Amount defined in Part 1 of Contract Data
- If Contractor does not achieve completion date and X7 selected then delays damages are due from Contractor to Employer
What are Advanced Payments?
Covered under clause secondary option clause X14 in NEC ECC
- It allows the contractor to receive lump sum payment in advance
- The payments, values and dates should be set out in the contract particulars
- They may be used where the contractor incurs high costs at the start of a project
- E.g. items with long lead times or the need to purchase specialist plant for manufacturing
- May reduce the incentive of the contractor
- Bad for the employer’s cashflow
- Concerns over why the contractor can’t fund the expenditure – insolvency worries
What is Retention?
NEC ECC Secondary Option Clause X16 – Contract data allows for a retention free amount (Can be Nil)
It provides an incentive for the contractor to complete the works promptly
It provides some financial cushion to the employer in the event of contractor default
Retention only taken from Price of Work done to date once retention free amount has passed
Employer acts as trustee for retention and should -
- Place it in a separate bank account
- Label the account as being held in trust
- Provide the contractor with statements showing the payments and amount of money in there
- This should ensure that the money is available to the contractor in event of employer insolvency
- Employer is entitled to interest on retention
Half of the retention is released to the contractor after assessment is made at Completion of the whole of the works or in the next assessment after Employer has taken over the whole of the works if this is before Completion of the whole of the works. Other half released when the Defects Certificate issued.
Retention Bond?
- Provided by the contractor in lieu of taking retention from interim payments
- It should be to the same value as the retention deducted would have been
- Requirement should be stated in the contract
- If Contractor does not maintain retention bond the employer can deduct retention from interim payments If the bond is subsequently taken out, the retention deducted must be repaid to the contractor
- If Contract sum increases Retention can either be deducted from interim payments on the additional amount or the value of the retention bond can be increased
- May be used in difficult market conditions to aid the contractor’s cashflow
Disadvantages of Retention Bond?
- Employer would have to pay the premium for taking out the bond
- May reduce the contractor’s incentive to complete to standard and promptly
- Harms the employer’s cashflow
- The employer would not get the interest accruing on the amount of the retention bond
What are the Dispute Resolution procedures under NEC?
HGCRA - Created a statutory right for the parties of a construction contract to refer any dispute arising under that contract to adjudication.
Covered in clauses W1 and W2 in NEC ECC. W2 covers HGCRA.
If HGCRA applies then use W2, if not use W1 which contains far greater detail regarding adjudication.
Party may refer a dispute to adjudicator at any time, who is appointed under the NEC Adjudicators Contract.
If a party is not satisfied with adjudicators decision can serve notice within four weeks of decision to go to a tribunal which will be stated in Contract Data e.g litigation/arbitration. The adjudicator cannot be called as a witness.
What are common NEC Contract documents?
- Main Document (Core Clauses/Main Option/DR/Secondary Option)
- Schedule of Cost Components (BQ/AS)
- Works Information (Contractors Responsibilities, Programme)
- Site Information (Services)
- Contract Schedules (Agreement Form)
- Drawing Register
- Contract Data Part 1 (Supplied by Employer - Client Details, Access dates, Weather measurements for CE, Insurance values if provided by employer, Z Clauses)
- Contract Data Part 2 (Supplied by Contractor - details of key personnel, data for SOCC, Fee %)
NEC Early Warning Process?
Both parties must give early warning of anything that may delay the works, or increase costs as soon as they become aware of them.
They should then hold an early warning meeting to discuss how to avoid or mitigate impacts on the project.
If the contractor fails to give early warning of a possible delay to the works, or increase in costs, they will only be compensated for effects that would have remained anyway even if they had given early warning.
If the contractor fails to give early warning of an event that may give rise to a possible delay to the works, or increase in costs, within 8 weeks of becoming aware of the event, they will not be entitled to a change in price, completion date or key date, unless the project manager should have notified the event to the contractor but did not.
Notification of Compensation Event?
NEC requires notification of any matter which increases the total of the prices, delays completion, delays the meeting of a key date, or impairs the performance of the works. Notification of Compensation Events is covered under Clause 61
- Contractor Notifies
- PM has 1 week to respond and ask for a quote
- If no response Contractor notifies the PM
- After a further 2 weeks, deemed as accepted
- Contractor must notify within 8 weeks of event or it is timebarred
- 8 weeks time bar relatively untested in court.
- Can be unfair on contractor and could lead to them raising a large amount of EWNs and NCEs just to cover themselves. Leads to more admin.
What is a project managers instruction?
- Instruction by Project Manager to Contractor
- Contractor obliged under clause 27.3 to follow instruction from PM or Supervisor as long as it is in accordance with the contract.
- Usually results in a CE (EG change to works information) but not every time EG instruction to submit a programme, instruction to submit a quote for acceleration.