Contract Administration Flashcards

1
Q

What is a Collateral Warranty?

A

Collateral warranties are agreements which are associated with another ‘primary’ contract. They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the difference between JCT & NEC Contracts?

A

JCT – Contract Administrator
NEC – Project Manager

  1. Price – JCT fixed lump sum & NEC options C & D are target costs contracts
  2. Provisional Sums – JCT includes & NEC Excludes

NEC typically used for infrastructure projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

ASOS – Collateral Warranty – what could happen if there wasn’t a collateral warranty in place. Are there any other fallback positions?

A

Third Party Rights Act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the benefits of a Collateral Warranty from a client perspective?

A

Provides a contractual agreement with a third party, which otherwise would not have been there

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the QS role in arranging a collateral warranty?

A

This is the solicitor/lawyer responsibility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

JCT Standard Building Contract – What reason can a JCT be terminated?

A

i. failure to “proceed regularly and diligently with the performance of his obligations”, thereby entitling the employer to give notice of default and subsequently terminate

ii. Contractor goes into liquidation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

ASOS P3 – Can you name me one of the CDP packages under these works?

A

Co-ordination of services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why was co-ordination of services CDP?

A

The co-ordination of service wasn’t completed at point of tender, therefore this element of design was passed onto the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the risk to the client of CDP items?

A

Client loses control of the design element

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How does a verbal instruction process work under a JCT?

A

i. Contractor issues Confirmation of verbal instruction (CVI) within 7 days of receiving verbal instruction
ii. If the architect/contract administrator does not dissent from that confirmation within seven days from receipt of the written confirmation, the instruction then takes effect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the timeline for the CA to reply to a confirmation of verbal instruction?

A

Seven days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Collateral Warranty – can you give me an example of where a Collateral Warranty may be used?

A

i. Funders - banks and other lenders funding construction works who are taking a charge over the property, rather than purchasing it, will require collateral warranties

ii. Purchasers - a party that buys the development

iii. Employers to sub-contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Schedule of Amendments – Can you give me an example of some of the amendments?

A

i. Payment dates (example – change from 14 days to 28 days)

ii. May be amendments relating to Covid & Force majeure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a vesting certificate?

A

A vesting clause is a contractual term which deals with the transfer of ownership of goods and materials and a vesting certificate is a document evidencing that transfer of ownership of those goods or materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Off-site joinery at KN – tell me the tasks and actions you carried out in relation to this?

A

I visited site with the architect to ensure the MOS were there and clearly labelled

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Did you go on your own to look at these or did you take anyone else with you?

A

No, I went with an architect and took a copy of the specification

17
Q

What certificates and notices are issued under the JCT?

A
  1. Interim Certificate
  2. Certificate of Practical Completion
  3. Non-completion certificate
  4. Payment Notice
  5. Certificate of making good
18
Q

What is the purpose of a valuation?

A

To provide a recommendation for payment for the CA to certify

19
Q

How is the construction act relevant?

A

Statutory requirements relating to interval and procedure for contracts that have duration of over 45 days

20
Q

Talk me through the schedule 2 quotation process under the JCT?

A

+ sufficient information must be provided to the contractor to enable preparation of a quotation

+ prescriptive time periods exist for the preparation and acceptance of a quotation

+ the quotation must include the value of the varied work and the effects on any other work

+ supporting calculations should be submitted, with appropriate reference to the Valuation Rules

+ any requirements for an Extension of Time

+ any amounts to be paid in lieu of ascertaining Loss & Expense

+ a fair and reasonable amount in respect of the cost of preparing the quotation should be included. This fair and reasonable amount is to be paid even if the quotation is not accepted

+ method statements and resource requirements should be included if asked for by the instruction to provide the quotation

21
Q

What is the difference between Patent and Latent Defects?

A

A patent defect is one that has been identified during the works or during the defect liability period, whereas a latent defect could be concealed and may not be apparent until many years later, for example a building cracking due to inadequate foundation design

22
Q

What is a rectification period?

A

In JCT contracts, the period is typically between six to twelve months but can be as long as two years. A principal or employer who does not advise that the rectification of defects is needed and/or refuses the contractor access to the site may be in breach of contract