Contract Administration Flashcards
What are the basic differences between the JCT and NEC approaches?
JCT: Hierarchical with detailed specs.
NEC: Emphasizes collaboration, flexibility.
JCT: Clear specs, traditional structure.
NEC: Risk-sharing, project management principles.
Why is impartiality important in administering the contract?
Ensures fair treatment, contract adherence.
Resolves disputes without bias.
Fosters trust, collaboration.
Upholds contract integrity, positive relationships.
How does the role differ between the contract administrator and Employer’s Agent?
Contract administrator: impartially administers contract, certifies payments.
Employer’s Agent: represents employer’s interests, manages project, oversees design, construction, and administration duties, with decision-making involvement.
What were these minor roof repair works? (BM)
The values?
Clerestory window repairs
Additional lead repairs and replacement
Installation of additional hoppers
Replacement of weatherboarding
Upgrading rainwater goods with 5ln guttering and downpipes
£30k total
How was it confirmed the eventual works requirement for these PSUMs and the costs? (BM)
Contractor investigated required works
Reported findings and costs
Total cost: £21k
What had the contractor failed to rectify? (BM)
external works ie repairs to garden wall; partial reconstruction; £900.
How did you go about adjusting the final account sum? (BM)
I omitted the value of the works outstanding together with the OHP; prepared a new Statement of Final Account for signing.
Can you tell me the timelines for final account agreement, statement of final account, issue of the final certificate? (BM)
Refer to JCT Mechanisms flashcards