Construction Contracts Flashcards
What is a Construction Contract?
A private law between
- a person wanting something to be built (owner)
- builder (contractor)
What items are set out in a Construction Contract?
- Work to be performed
- Price / Schedule of work
- Rights and responsibilities of parties
What are the main players in Construction Projects?
- Owner
- General Contractor
- Architect
- Engineers
- Trade Contractors
- Suppliers
What are the three main standard form documents for industry in Canada?
- CCDC (Canadian Construction Document Committee)
- CCA (Canadian Contractors Association)
- MMCD (Master Municipal Construction Document)
What are the types of standard form contracts?
- Lump sum
- Unit price
- Negotiated
What is lump sum suitable for?
- Well-defined project
- Known material quantities
What are pros of lump sum
- Owner has price certainty
- Owner knows what the end project be
- Monthly payment for contractor based on completed work
What are cons of lump sum
- Risky to contractors
- Less chance to make design change
What is unit price suitable for?
- Well-defined project
- Unknown material quantity
What are pros of unit price?
- Flexible meeting
- Contractors don’t need to be as precise in takeoffs
What are cons of unit price?
- Owner has uncertainty in overall cost
- Can be manipulated by contractor
What deviation in unit price requires renegotiating?
+15%: Owner requests unit price reduction
-15%: Contractor requests unit price increase.
What are the key factors in a negotiated contracts?
- Owner chooses contractors
- O review C’s documents (complete/incomplete)
- O Chooses C based on their reputation, staff available, fee structure, etc.
What is negotiated suitable for?
- Private sector (for phased construction)
- Less in Public (to avoid abuse through favoritism)
- Complex, long-duration project
What are the 4 common fee structures of negotiated?
- Cost + % cost (Most lucrative to C, Potential to be abused)
- Cost + Fixed Fee (%of previously estimated cost, C may use expensive reimbursable materials to expedite the work)
- Cost + Fixed Fee + Profit-sharing clause (Reward on C who mizmize the cost)
- Cost + Sliding fee (Bonus for underrun, Penalty for overrun)