Construction Contracts Flashcards

1
Q

What is a Construction Contract?

A

A private law between
- a person wanting something to be built (owner)
- builder (contractor)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What items are set out in a Construction Contract?

A
  • Work to be performed
  • Price / Schedule of work
  • Rights and responsibilities of parties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main players in Construction Projects?

A
  • Owner
  • General Contractor
  • Architect
  • Engineers
  • Trade Contractors
  • Suppliers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the three main standard form documents for industry in Canada?

A
  • CCDC (Canadian Construction Document Committee)
  • CCA (Canadian Contractors Association)
  • MMCD (Master Municipal Construction Document)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the types of standard form contracts?

A
  • Lump sum
  • Unit price
  • Negotiated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is lump sum suitable for?

A
  • Well-defined project
  • Known material quantities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are pros of lump sum

A
  • Owner has price certainty
  • Owner knows what the end project be
  • Monthly payment for contractor based on completed work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are cons of lump sum

A
  • Risky to contractors
  • Less chance to make design change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is unit price suitable for?

A
  • Well-defined project
  • Unknown material quantity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are pros of unit price?

A
  • Flexible meeting
  • Contractors don’t need to be as precise in takeoffs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are cons of unit price?

A
  • Owner has uncertainty in overall cost
  • Can be manipulated by contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What deviation in unit price requires renegotiating?

A

+15%: Owner requests unit price reduction
-15%: Contractor requests unit price increase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the key factors in a negotiated contracts?

A
  • Owner chooses contractors
  • O review C’s documents (complete/incomplete)
  • O Chooses C based on their reputation, staff available, fee structure, etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is negotiated suitable for?

A
  • Private sector (for phased construction)
  • Less in Public (to avoid abuse through favoritism)
  • Complex, long-duration project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the 4 common fee structures of negotiated?

A
  • Cost + % cost (Most lucrative to C, Potential to be abused)
  • Cost + Fixed Fee (%of previously estimated cost, C may use expensive reimbursable materials to expedite the work)
  • Cost + Fixed Fee + Profit-sharing clause (Reward on C who mizmize the cost)
  • Cost + Sliding fee (Bonus for underrun, Penalty for overrun)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly