Builder's Lien Flashcards

1
Q

What is improvement in Builder’s Lien Act

A
  • anything made, erected, built, construction
  • on or under land
  • and attached to or intended to become part of it
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does BLA do?

A
  • Creates Right of Lien against holdback
  • Holdback = 10% of every payment in contract
  • No liens filed -> Holdback is paid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Types of land not subject to BLA?

A
  • Ferry properties
  • Federal undertaking
  • Highways
  • Improvement done by Ministry of Forest
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Requirement of BLA?

A

“Owner” requested the improvement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How can landlords protect themselves against liens

A

By filing “notice of interest” on the title to the land

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Types of owner under BLA?

A

Exempt
- Federal crown and their agents

Subject:
- Provincial crown and their agents
- School boards
- Municipalities
- Provincial public facility

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the trust?

A
  • BLA imposes a trust on funds received from contractors / sub-constractors for improvement. $ should be used to pay sub-contractors, workers, and material suppliers.
  • $ cant be used as other purposes until paying all trust beneficiaries
  • Beneficiaries can track improperly used $
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Engineers - Lien Rights and Trust Obligations

A
  • Engineers can file lien, but not ppl work for engineers.
  • no holdback / trust provision applies to engineers payment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Time limits under BLA

A
  • can file lien eariler, but not later
  • Lien against improvement = 45days
  • Lien aginst holdback = before holdback is released
  • Release of holdback = 55days
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

5 Triggers of Running of Time

A
  • Certificate of Completion of Contract
  • Completion of Head Contract / Improvement
  • Termination
  • Abandonment
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

3-2-1 formula

A
  • 3% of first $500,000 of contract price
  • 2% of second $500,000 of contract price
  • 1% of remaining contract price
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Will there be an extension if the certificate of completion is issued earlier?

A
  • If contract was completed before issuance of certificate of completion
  • No extension
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Completion of Head Contract

A

“Completed” in relation to contract = “substantially completed/performed”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Completion of improvement

A
  • If not considering whether contract complete -> assess whether improvement is complete
  • improvement is completed if, substantial part is ready to use or it is being used for the purpose intended
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Abandonment

A

Deemed abandonment w/ 30 days of no work

Unless stoppage by lockout, weather, holiday, strike

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Termination

A
  • Not defined by BLA
  • Will be assessed on case by case basis whether terminatino occurred
17
Q

Deadline for initiating lien action

A
  • Within 1yr of filing lien, claimant must start action to enfore lien, and file CPL (Certificate of Pending Litigation) in land title office
18
Q

Discuss the 21 day notice

A
  • Owner can deliver notice to lien claimant to commence action and file CPL within 21 days of service of notice
  • Forces claimant to decide in 1yr, whether worth commencing or not
  • Enables faster resoultion
19
Q

What is a Lien?

A

A claim which can be made against title to property in an effort to secure the recovery of money owing the lien claimant

20
Q

What is Contract A

A
  • process contract
  • arises between owner and contractor immediately after bid is submitted
  • without further formalities
21
Q

What is contract B

A
  • Bidding contract contains another term
  • Where bidder will enter into a formal construction contract if the owner awards it to him