A pressure relief valve that meets the pressure vessel code is installed on the condenser shell side to prevent an over pressure condition. A small amount of ___________________ is applied continuously to the outlet of the relief valve to prevent air in leakage in the event the valve seat leaks. (Ref. CCV SD 2.2.2)
condensate makeup
A normally closed Manual Fill Valve V-050 allows the hotwell to be filled from the _________if necessary. (Ref. CCV SD 2.2.3)
condensate storage tanks
______________ draw the initial vacuum in the condenser during startup. During normal operations, the vacuum in the condenser is maintained by ___________________. (Ref. CCV SD 2.3.2)
Liquid ring vacuum pumps, the condensing action of the steam
The volume of air in-leakage removed by each air removal skid can be directly measured by using local rotameters mounted on the separation tanks. This measured value can be used for _____________________. (Ref. CCV SD 2.3.3)
equipment performance trending
Typically, one vacuum pump runs at a time. The lag pump will be commanded to run while the lead pump is running if __________________. (Ref. CCV SD 3.0)
condenser pressure (CND_PIT214) is greater than 8 in Hg for 30 seconds