Horizontal and Vertical rebar no farther apart than 3X wall thickness or 18”
MISC FACT
Two-Way Slabs: Circular and Polygon-shaped supports to be treated like square supports with the same area
ACI 318-14: Building Code Requirements for Structural Concrete
PG 119 8.10.1.3
Licensed design professional: responsible for, in charge, of structural design and inspection
ACI 318-14: Building Code Requirements for Structural Concrete
PG 13-1.7.1
Pile Caps: Overall depth = at least 12”
ACI 318-14: Building Code Requirements for Structural Concrete
PG 194 13.4.2.1
Structural plain concrete not for us in columns or pile caps
ACI 318-14: Building Code Requirements for Structural Concrete
PG 195 14.1.5
Minimum thickness of footings cannot be less than 8”
ACI 318-14: Building Code Requirements for Structural Concrete
PG 197 14.3.2.1
Minimum thickness of bearing walls: Exterior basement and foundations = 7.5”
ACI 318-14: Building Code Requirements for Structural Concrete
PG 197 14.3.1.1
No welding of stirrups, ties, or inserts to longitudinal bars
ACI 318-14: Building Code Requirements for Structural Concrete
PG 269 18.2.8.2
At ends of concrete beam, hoop shall be at least 2x height of beam face. Loop #1 = 2” from face of support member
ACI 318-14: Building Code Requirements for Structural Concrete
PG 270 18.4.2.4
Spacing of loops shall not exceed the smaller of d/4
ACI 318-14: Building Code Requirements for Structural Concrete
PG 270 18.4.2.4 (a)
Spacing of loops shall not exceed the small of 8x diameter of smallest longitudinal member
ACI 318-14: Building Code Requirements for Structural Concrete
PG 270 18.4.2.4 (b)
Spacing of loops shall not exceed the smaller of 24x diameter of loop bar
ACI 318-14: Building Code Requirements for Structural Concrete
PG 270 18.4.2.4 (c)
Spacing of loops shall not exceed 12”
ACI 318-14: Building Code Requirements for Structural Concrete
PG 270 18.4.2.4 (d)
Exposure categories and classes; class F3 exposed to frequent freezing, thawing and water
ACI 318-14: Building Code Requirements for Structural Concrete
PG 315 T1.3.1.1
Requirements for concrete by exposure class; shows minimum PSI allowed
ACI 318-14: Building Code Requirements for Structural Concrete
PG 323 T19.3.2.1
Air content requirements for concrete exposed to freezing and thawing; exception when PSI > 5,000, a reduction of air = 1%
ACI 318-14: Building Code Requirements for Structural Concrete
PG 324 T19.3.3.1
Prestressing stands, wires and bars
ACI 318-14: Building Code Requirements for Structural Concrete
PG 330 T20.3.2.2
Concrete cover: cast-in-place pretreated concrete members
ACI 318-14: Building Code Requirements for Structural Concrete
PG 336 T20.6.1.3.2
Concrete cover: pre-cast nonprestressed or prestressed manufactured in a plant
ACI 318-14: Building Code Requirements for Structural Concrete
PG 336 T20.6.1.3.3
Deformed rebar coatings: zinc, epoxy, and zinc + epoxy
ACI 318-14: Building Code Requirements for Structural Concrete
PG 338 20.6.2.1
Parallel nonprestressed rebar placed in a horizontal layers, rebar spacing should be a 1”
ACI 318-14: Building Code Requirements for Structural Concrete
PG 411 25.2.1
Parallel nonprestressed rebar placed in 2x or more horizontal layers, rebar supports in upper layer directly over lower supports
ACI 318-14: Building Code Requirements for Structural Concrete
PG 411 25.2.2
Longitudinal reinforcement in columns, pedestals, struts = clear spacing of at least 1.5”
ACI 318-14: Building Code Requirements for Structural Concrete
PG 411 25.2.3
Development of bundled bars (rebar) - in tension or compression - individual bar increased by 20% in 3bar, 33% in 4bar
ACI 318-14: Building Code Requirements for Structural Concrete
PG 25.6.1.5
Spacing of bundled bars (rebar) - bundle bar is equivalent to th area of the diameter of the sum of individual bundled bars
ACI 318-14: Building Code Requirements for Structural Concrete
PG 25.6.1.16
Diameter of Ti bars: for #10 longitudinal bar casing enclosed by #3 rebar
ACI 318-14: Building Code Requirements for Structural Concrete
PG 25.7.2.2.1
Anchorage of circular ties: overlap of 6”, ends terminate with standard hooks to engage longitudinal bars
ACI 318-14: Building Code Requirements for Structural Concrete
PG 25.7.2.4.1
Specifications for cementitious materials: Portland cement = ASTM C150
ACI 318-14: Building Code Requirements for Structural Concrete
PG 455 T26.4.1.1.1 (a)
Quality of water used is satisfactory in natural state, no small, no pronounced taste
ACI 318-14: Building Code Requirements for Structural Concrete
PG 456 26.4.1.3
Fly ash maximum of 25% concentration
ACI 318-14: Building Code Requirements for Structural Concrete
PG 459 T26.4.2.2 (b)
Strength of concrete in post-tensioning and other applications is specified in the contract documents
ACI 318-14: Building Code Requirements for Structural Concrete
PG 462 R26.4.4.1 (c)
Never pump concrete through pipe made of aluminum or aluminum alloys
ACI 318-14: Building Code Requirements for Structural Concrete
PG 463 R26.5.2.1 (e)
Non-high early strength concrete maintained at 50 degrees and moist for 7 days to cure; exception if accelerators are used
ACI 318-14: Building Code Requirements for Structural Concrete
PG 464 26.5.3.2 (a)
High early strength concrete maintained at 50 degrees and moist for 3 days to cure; exception if accelerators are use
ACI 318-14: Building Code Requirements for Structural Concrete
PG 464 26.5.3.2 (b)
Strength test of at least 2x (6”x 12” cylinders) or 3x (4” x 8” cylinders) ASTM C31for curing and ASTM C31 for testing
ACI 318-14: Building Code Requirements for Structural Concrete
PG 464 R26.5.3. (d)
Construction Joints in floors - located in middle of 1/3 of slabs, beams, girders (non-prestressed)
ACI 318-14: Building Code Requirements for Structural Concrete
PG 466 R26.5.6.2 (b)
Construction Joint Offsets - Offset distance 2x width of intersecting beam
ACI 318-14: Building Code Requirements for Structural Concrete
PG 466 R26.5.6 (c)
Compressive strength of concrete 4,000 PSI for multi strand tendons
ACI 318-14: Building Code Requirements for Structural Concrete
PG 476 R26.10.2 (j)
Compressive strength of concrete 2,500 PSI for single strand or bar tendons
ACI 318-14: Building Code Requirements for Structural Concrete
PG 476 R26.10.2 (j)
Oversized anchorage in post-tensioning compensates for lower PSI concrete
ACI 318-14: Building Code Requirements for Structural Concrete
PG 476 R25.10.2 (k)
Forms should be braced and tied to maintain position and shape
ACI 318-14: Building Code Requirements for Structural Concrete
PG 477 26.1.1.2
Frequency of testing : Concrete samples taken not less than 1x per day, or 1x per 150 yards poured, or 1x for each 5,000 sf poured