CM - Project Planning, work breakdown Flashcards

1
Q

What is planning?

A

The process of breaking down a project into activities and establishing their mutual independencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What two things should a plan do?

A

-Represent the best thinking available at the time it is conceived.
-Should be dynamic, should change as knowledge progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is programming (scheduling) ?

A

Describes work to:
-Sequence
-Activity and duration
-Monitor, update and communicate the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a work breakdown structure?

A

Deciding what activities do we need to complete.

The process of dividing project work into smaller, more manageable components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 3 sections of work sequencing?

A

-Activity relationships (what sequence do we need to complete activites in)
-Activity duration
-Construction schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main aims of a work breakdown structure?

A

-Identify work entailed in project.
-Provide a basis for planning timeline, resource use and cost of project.
-Monitoring during construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Work breakdown structure should be devloped “top down”, what does this mean?

A

It should start at a big picture perspective, and work down to fine-detail.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When should a work breakdown structure stop?

A

At a level where activities are clearly distinguishable, and have unique start and finish parameters.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In the contruction of a bridge, would abutment be WBS 1,2,3 or 4?

A

2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In the construction of a bridge, that has abutments 1 and 2, what WBS level would formwork be classed in?

A

Level 4.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In activity relationships, what does finish-to-start (FS) mean?

A

Activity x cannot start until activity y finishes.W

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

In activity relationships, what does start-to-start mean?

A

Activity x cannot start until activity x starts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a precedence diagram?

A

A diagram where you connect related activities.

e.g. begin to A to B to C to end.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

EXAMPLE : A long retaining dam wall is to be constructed, determine the construction sequence for the retaining wall, assuming that the wall has 2 components, a base and a wall.

A

WBS level 1 : Dam retaining wall

WBS level 2 : Base and wall

WBS level 3 : Base and wall split into excavation formwork, reinforcement ….

Then determine the steps taken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does concreting wait on?

A

Formwork and reinforcement to be in place, so it is finish start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the duration of activities related to?

A

The rate at which work is completed

17
Q

What is the production rate?

A

The quantitity of work produced per unit time, e.g. 10 metres cubed per hour.

18
Q

What is the productivivity?

A

The duration of unit quantity of work, e.g. 0.1 hours per meter cubed.

19
Q

What equation links productivity and production rate?

A

Production rate = 1 / productivity

20
Q

How can activity duration be calculated?

A

From quantity of work / production rate * resources

21
Q

How do we determine the productivity?

A

From SPON’s price book.