CM - Preliminary Cost Estimate Flashcards

1
Q

What is a cost estimate?

A

A prediction of cost based on the basis of available data at a given stage of the project development.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What 5 factors play a role in the cost estimate of a project?

A

Direct costs, overheads, inflation, contingency and mark up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are direct costs?

A

Materials, labour, equipment, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are indirect costs?

A

Costs that cannot be allocated to individual activities, e.g. site management and safety.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is inflation?

A

Sustained increase in the general prices and services overtime.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is contingency?

A

Amount of money set aside to cover unexxpected costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is mark-up?

A

The profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Why do we estimate cost?

A

For financing and budgeting for the owner and contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

As we go from the conceptual estimate, to the preliminary estimate, to the detailed cost estimate, what happens to the accuracy of the estimate?

A

It is closer to the final value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What happens to the variation of actual costs from the cost estimaye as project definition increases?

A

It gets closer to the final project cost.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Prelimanary cost estimates focus on “cost rates per square metres”, what would the equation of cost be in this scenario?

A

Cost = Cost of building per square metre X floor area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the standard measurement of floor area?

A

Gross internal floor area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the gross internal floor area?

A

The area of a building measured to the internal face of the perimeter walls at each floor level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How are cost rates defined?

A

At a point in time, for a specific location, including direct and indirect costs, and mark up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the equation for the preliminary constrution cost?

A

Cost rate * Floor area * Inflation factor * Location adjustment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the equation of the contingency cost?

A

Construction cost * contingency percentage

17
Q

What does the total prelimary cost of the project equal?

A

Construction + contingency cost

18
Q

What is the equation of the inflation factor?

A

TPI used at start of construction / TPI used for cost rate in SPON

19
Q

Why do we have contingency cost?

A

To allow for risk, unforeseen costs during construction. Judgement is needed on what contingency percentage to use.